W.157Google will buy 50 MW of superhot geothermal from Quaise for more than $500M

Quaise Energy said on November 17 that Google will buy 50 MW from Project Obsidian, its first plant at Newberry Volcano in Oregon, beginning as early as 2030. The release gives no price or term; Canary Media reported that Quaise confirmed the agreement is worth more than $500M, and that Quaise said the plant will cost about $350M. That is at least $10M per megawatt of contract against $7M of build cost. Spread over 15 to 25 years at a 90% capacity factor it is at least $51 to $85 per MWh, below the roughly $106 that recent Nevada geothermal offers carried. Quaise has not yet drilled a commercial well with its millimeter-wave method.

Agreement value, per Quaise
>$500M
not in the release; term and price not disclosed
Capacity Google will buy
50 MW
beginning as early as 2030; 1.9% of US geothermal capacity today
Contract value per megawatt
≥$10M
against about $7M a megawatt of plant cost, per Quaise
Floor price if spread over 20 years
≥$63
per MWh at a 90% capacity factor; our assumption, not a disclosed price

The agreement

Google will buy 50 MW from Quaise’s first plant. Quaise’s release says Google will purchase 50 MW from Project Obsidian in Central Oregon, beginning as early as 2030, to support its data center operations in The Dalles. OPB places the project on the southern flank of Newberry Volcano. Quaise calls it a power purchase agreement and says it is signed. No utility is named as a party or as the delivery route; the release mentions Northern Wasco County PUD only in describing local rates.

The dollar figure is not in the release. The release states no price, value or term, and OPB reported that the companies did not disclose the sale price. Canary Media reported that the agreement is worth more than $500 million, per Quaise’s confirmation; the Wall Street Journal, which we could not read, also reported the figure, according to a summary. We take it as the total over the term. Whether it is nominal or includes escalation is not stated.

Canary Media reported in March that the first 50 MW was already contracted. It reported on March 3 that Quaise had signed a power purchase agreement for the first 50 MW with an undisclosed customer. No source says whether the November announcement names that customer or describes a new contract.

The plant costs about $350 million, Quaise says. On 50 MW that is $7 million a megawatt, the same per kilowatt as Fervo’s stated cost for the first phase of its Cape Station in Utah. The agreement value is at least 1.4 times the plant cost. Quaise had raised $280 million by August and has been selected for up to $25 million from the Department of Energy, subject to negotiation.

The agreement is worth more than $500M; the plant costs about $350M

Millions of dollars. Pink: the value of the agreement, more than $500 million, per Quaise, as reported by Canary Media; the bar is drawn at $500 million and the true figure is higher by an amount not stated. Black: the cost of the 50 MW plant, about $350 million, per Quaise. Strong grey: the funding Quaise had raised to date at the final close of its Series B on August 27. Grey: the Department of Energy support for which Quaise was selected, up to $25 million. The first is revenue over an undisclosed term and the others are capital, so the bars are for scale.

0$100M$200M$300M$400M$500M$600MAgreement valuemore than $500M, per Quaise; term not disclosedAgreement value: more than $500 million, per Quaise, as reported by Canary Media>$500MCost of the 50 MW plantabout $350M, per QuaisePlant cost: about $350 million, per Quaise~$350MQuaise funding raised to dateat the Series B close in AugustTotal raised to date at the Series B final close, Aug 27, 2026: $280 million$280MDepartment of Energy supportselected for up to $25M, subject to negotiationDepartment of Energy: selected for up to $25 million, subject to negotiation≤$25M
0$200M$400M$600MAgreement valuemore thanAgreement value: more than $500 million, per Quaise, as reported by Canary Media>$500MPlant costaboutPlant cost: about $350 million, per Quaise~$350MRaised to dateAug 2026Total raised to date at the Series B final close, Aug 27, 2026: $280 million$280MDOE supportup toDepartment of Energy: selected for up to $25 million, subject to negotiation≤$25M

What price that implies

The term decides it, and the term is not disclosed. At a 90% capacity factor, 50 MW produces 394,200 MWh a year. $500 million spread evenly over 15 years is $85 per MWh; over 20 years, $63; over 25 years, $51. Each is a floor, because the value is more than $500 million. The capacity factor and the terms are our assumptions.

Recent geothermal prices are higher than those floors. CTVC reported Fervo’s Corsac Station agreement with NV Energy, the 115 MW project that supplies Google, at $107 per MWh for 15 years, and Ormat’s Heber 1 extension at $86 with a 1.5% annual escalator. Three geothermal offers in NV Energy’s 2026 resource plan averaged $105.56, Oilprice.com reported from the filing. At $105.56, 50 MW would earn about $41.6 million a year and pass $500 million in about 12 years.

So either the term is short or the price is below Nevada’s. A value near $500 million at Nevada prices implies a term of about 12 years. A term of 20 years or more at Nevada prices would imply a value well above $500 million, which “more than” allows. The disclosed facts do not separate the two.

Spread over 15 to 25 years, $500M is $51 to $85 per MWh, below recent geothermal prices

Dollars per megawatt-hour. Dashed pink: $500 million divided by an assumed term and by 394,200 MWh a year (50 MW at a 90% capacity factor); the term is not disclosed, the capacity factor is our assumption, and each bar is a floor because the value is more than $500 million. Strong grey: geothermal prices reported for other agreements and offers, by CTVC and by Oilprice.com from NV Energy’s filing; none is a company-published contract price that we read directly.

0$20$40$60$80$100$120Quaise and Google: $500M spread over an assumed term15 years$667K per MW a year$500 million ÷ 15 years ÷ 394,200 MWh a year = $84.6 per MWh; a floor, since the value is "more than" $500 million≥$8520 years$500K per MW a year$500 million ÷ 20 years ÷ 394,200 MWh a year = $63.4 per MWh; a floor, since the value is "more than" $500 million≥$6325 years$400K per MW a year$500 million ÷ 25 years ÷ 394,200 MWh a year = $50.7 per MWh; a floor, since the value is "more than" $500 million≥$51Geothermal prices reported elsewhereFervo Corsac Station, with NV Energy15 years, per CTVC; supplies GoogleFervo Corsac Station, with NV Energy: $107 per MWh (15 years, per CTVC; supplies Google)$107NV Energy geothermal offers, 2026weighted average of three offers, as reportedNV Energy geothermal offers, 2026: $105.56 per MWh (weighted average of three offers, as reported)$106Ormat Heber 1, 52 MW25 years, escalating 1.5% a year, as reportedOrmat Heber 1, 52 MW: $86 per MWh (25 years, escalating 1.5% a year, as reported)$86
0$40$80$120Quaise, if spread over15 years$500 million ÷ 15 years ÷ 394,200 MWh a year = $84.6 per MWh; a floor, since the value is "more than" $500 million≥$8520 years$500 million ÷ 20 years ÷ 394,200 MWh a year = $63.4 per MWh; a floor, since the value is "more than" $500 million≥$6325 years$500 million ÷ 25 years ÷ 394,200 MWh a year = $50.7 per MWh; a floor, since the value is "more than" $500 million≥$51BenchmarksFervo CorsacFervo Corsac Station, with NV Energy: $107 per MWh (15 years, per CTVC; supplies Google)$107NV Energy offersNV Energy geothermal offers, 2026: $105.56 per MWh (weighted average of three offers, as reported)$106Ormat Heber 1Ormat Heber 1, 52 MW: $86 per MWh (25 years, escalating 1.5% a year, as reported)$86
The arithmetic by term
Assumed term$M a year$K per MW-year$ per MWh, floor
15 years33.366784.6
20 years25.050063.4
25 years20.040050.7

The technology and the size

The first phase does not use the new drill. Quaise’s method uses millimeter waves from a gyrotron to melt and vaporize rock. The November release says phase 1 uses conventional drilling to reach superhot conditions and that phase 2 is expected to be the first to use millimeter-wave drilling. Canary Media reported that the method is still being tested in Texas. Quaise’s April release put its two well systems at average temperatures of about 315°C and 365°C, about 5 km down.

A confirmation well was being drilled in September. That is from Quaise’s Department of Energy announcement of September 22. We found no later statement of depth or temperature reached. Quaise must also build a 10-mile line to a substation in La Pine, OPB reported.

50 MW is small for Google. It is 0.14% of the nearly 35 GW of clean energy agreements the release says Google signed from 2010 to 2025, and an eighth of the 396 MW Google agreed to buy from Fervo’s Cape Station in September. It is 1.9% of the 2.7 GW of US geothermal capacity in the EIA’s February article.

Quaise plans more at the site. Its April release describes a second phase targeting 250 MW, and Canary Media reported it is seeking buyers for a further 200 MW. Its chief executive estimates the project could generate about 1 GW in the next decade, OPB reported.

At 50 MW, the Quaise agreement is the smallest of Google’s firm-power deals shown

Megawatts. Pink: Quaise’s Project Obsidian. Strong grey: five other agreements Google has announced for power that runs around the clock, from the reports listed under Sources, with the date announced. Duane Arnold is the size of the plant under a 25-year agreement; Kairos is a total by 2035; the others are the contracted amount. Technologies and start dates differ.

0100200300400500600700Quaise, Project ObsidianNov 2026; superhot geothermal, as early as 2030Quaise, Project Obsidian: 50 MW, beginning as early as 203050 MWNextEra, Duane Arnold nuclear restartOct 2025; plant size; 25-year agreementNextEra, Duane Arnold nuclear restart: 610 MW (Oct 2025; plant size; 25-year agreement)610 MWKairos Power, advanced nuclearOct 2024; by 2035Kairos Power, advanced nuclear: 500 MW (Oct 2024; by 2035)500 MWFervo, Cape Station geothermalSep 2026; online 2028Fervo, Cape Station geothermal: 396 MW (Sep 2026; online 2028)396 MWCommonwealth Fusion SystemsJun 2025; fusionCommonwealth Fusion Systems: 200 MW (Jun 2025; fusion)200 MWFervo, Nevada geothermalJun 2024; through NV EnergyFervo, Nevada geothermal: 115 MW (Jun 2024; through NV Energy)115 MW
0350700QuaiseNov 2026Quaise, Project Obsidian: 50 MW, beginning as early as 203050 MWDuane ArnoldOct 2025NextEra, Duane Arnold nuclear restart: 610 MW (Oct 2025; plant size; 25-year agreement)610 MWKairos PowerOct 2024Kairos Power, advanced nuclear: 500 MW (Oct 2024; by 2035)500 MWFervo, CapeSep 2026Fervo, Cape Station geothermal: 396 MW (Sep 2026; online 2028)396 MWCommonwealthJun 2025Commonwealth Fusion Systems: 200 MW (Jun 2025; fusion)200 MWFervo, NevadaJun 2024Fervo, Nevada geothermal: 115 MW (Jun 2024; through NV Energy)115 MW

What this changes on inthesingularity.ai

  • inthesingularity.ai has no tracker of firm-power agreements for data centers. Lead: a table by megawatts, start date, term and price where disclosed. This one is 50 MW, as early as 2030, more than $500 million, term undisclosed.
  • W.154 compared data center leases by value per megawatt-year. A power contract can be put on the same footing once its term is known: $500K per megawatt-year at 20 years here, against $1.67 million for Giga’s lease, which is for data center capacity.
  • W.104 covered Oklo’s fuel contracts, which disclosed neither quantity nor price. This agreement discloses a quantity and a floor on value, and not the price.
  • A figure to watch for: the term, which would turn the $500 million into a price.

Sources and method

ItemFigureSource
The agreementGoogle will purchase 50 MW from Project Obsidian in Central Oregon beginning as early as 2030, for its data center operations in The Dalles; no price, value or term stated; 200 to 400 construction jobs and more than 50 permanent jobs; Google signed over 240 agreements for nearly 35 GW of clean energy from 2010 to 2025Quaise Energy release, Nov 17
The agreementWorth more than $500 million, per Quaise’s confirmation; the plant will cost about $350 million to build; Quaise is seeking buyers for a further 200 MW at the site; millimeter-wave drilling is still being tested in TexasCanary Media, Nov 17
The agreementOriginal report of the agreement and its valueThe Wall Street Journal, Nov 17 (not read; as summarized by Nasha Niva)
The agreementThe companies did not disclose the sale price; Quaise must build a 10-mile line to a substation in La Pine; three Google data centers in The Dalles; Quaise’s chief executive estimates the project could generate about 1 GW in the next decade; the project is on the southern flank of Newberry VolcanoOPB, Nov 17
QuaiseA power purchase agreement for the initial 50 MW was already signed with an undisclosed customerCanary Media, Mar 3
QuaisePhase 1 of at least 50 MW as early as 2030; a second phase targeting 250 MW; two well systems averaging about 315°C and 365°C at about 5 kmQuaise release, Apr 22
QuaiseSeries B final close of $180 million, including $35 million from Nabors Industries; $280 million raised to dateThinkGeoEnergy, Aug 27
QuaiseSelected for up to $25 million of Department of Energy support, subject to negotiation; a confirmation well was being drilledQuaise release, via Business Wire, Sep 22
QuaiseThe first wells are drilled conventionally; millimeter-wave drilling at the site as early as 2027Canary Media, Jul 7
BenchmarksFervo’s Corsac Station agreement with NV Energy: $107 per MWh for 15 years. Ormat Heber 1: 52 MW, 25 years, $86 per MWh escalating 1.5% a yearCTVC, Sep 2, 2025
BenchmarksNevada regulators approved the 115 MW Fervo agreement that supplies Google under the Clean Transition TariffThinkGeoEnergy, May 2025
BenchmarksNV Energy’s 2026 resource plan: three geothermal offers at $105 to $107 per MWh, weighted average $105.56 across 180 MWOilprice.com, Oct 20, citing the filing
BenchmarksFervo Cape Station: $7,000 per kW for its first phase, per the companyCanary Media, Sep 28
Google’s agreementsFervo Cape Station: 396 MW, online in 2028Power Engineering, September 2026
Google’s agreementsKairos Power: 500 MW by 2035; first unit of 50 MW in Tennessee by 2030ESG Dive, August 2025
Google’s agreementsCommonwealth Fusion Systems: 200 MW from its fusion project in VirginiaS&P Global, June 2025
Google’s agreementsNextEra’s Duane Arnold: a 25-year agreement on a 610 MW plant restarting by early 2029World Nuclear News, October 2025
ScaleUS geothermal summer capacity of 2.7 GW; 2,695.5 MW in the Electric Power Monthly table the article linksEIA, Feb 19

What we read. Quaise’s release of November 17; Canary Media’s and OPB’s reports; Quaise’s earlier releases and reports of its funding; and reports of the comparison agreements. We could not read the Wall Street Journal article and found no statement published by Google itself or any utility or regulatory filing. Arithmetic. 500 ÷ 50 = 10.0; 350 ÷ 50 = 7.0; 500 ÷ 350 = 1.43. Output: 50 × 8,760 × 0.9 = 394,200 MWh a year. Price floors: 500,000,000 ÷ 15 ÷ 394,200 = 84.6; 500,000,000 ÷ 20 ÷ 394,200 = 63.4; 500,000,000 ÷ 25 ÷ 394,200 = 50.7. Per megawatt-year, $ thousand: 500 ÷ 15 ÷ 50 = 667; 500 ÷ 20 ÷ 50 = 500; 500 ÷ 25 ÷ 50 = 400. At Nevada’s average: 394,200 × 105.56 = $41.61 million a year; 500 ÷ 41.61 = 12.0 years. Shares: 50 ÷ 2,695.5 = 1.85%; 50 ÷ 35,000 = 0.14%; 50 ÷ 396 = 0.126. Conflicts between sources. The value is more than $500 million in Canary Media and in summaries of the Journal, a flat $500 million in one trade post, and undisclosed in OPB’s report and the release. Duane Arnold is given as 610 MW and as 615 MW. Quaise’s phase 1 is “at least 50 MW” in April and “more than 50 MW by 2030” in September. Limits. The term, price, escalator and conditions are not disclosed, so every price here is an assumption-driven floor. A 90% capacity factor is typical of geothermal plants but is not a figure from the parties. The benchmark prices come from a newsletter and from a report of a utility filing. The megawatts in the last chart are not on one basis. Whether power is delivered physically to The Dalles or matched on the grid is not stated.