W.104Oklo signed Centrus fuel contracts for up to five reactors, without disclosing quantity or price

Oklo, a reactor developer, and Centrus Energy, a uranium enricher, announced definitive contracts on November 12 for fuel to support up to five of Oklo’s Aurora reactors, with deliveries scheduled to begin in 2029 and part of the money coming from Meta’s prepayment for power. The release gives no quantity, price or reactor size. At Oklo’s stated 15 to 75 megawatts a unit, five are 75 to 375 MW, 6% to 31% of the 1.2 GW campus planned for Meta in Ohio. Centrus produced 900 kg of this fuel a year under a federal contract that ended in June, and plans capacity of 12 tonnes a year.

Reactors the fuel would support
up to 5
“for multiple years”; quantity, price and prepayment not disclosed
Five reactors, share of the Meta campus
6%–31%
75–375 MW of 1,200 MW, at Oklo’s stated 15–75 MW a unit
First deliveries scheduled
2029
the year Centrus plans its first new capacity; Meta’s first phase is targeted for as early as 2030
Centrus’s output of this fuel, to June
0.9 t a year
under a federal contract; it plans 12 t a year, and the Energy Department put US demand at 50 t a year by 2035

What was signed

Oklo and Centrus signed definitive contracts for reactor fuel. Their joint release of November 12 describes multiple definitive, multi-year contracts for high-assay low-enriched uranium, or HALEU: uranium enriched to between 5% and 20%, which Oklo’s reactors need and ordinary reactors do not. The contracts formalize a non-binding letter of intent the two signed on June 18, 2026. Centrus is to supply the fuel from its American Centrifuge Plant in Pike County, Ohio, the county where Oklo plans a campus for Meta, with deliveries scheduled to begin in 2029.

The release has no quantity, value or price. It says the contracts cover enough HALEU to support up to five Aurora powerhouses, Oklo’s name for its reactors, for multiple years. It does not give kilograms, an enrichment level, a contract value, a delivery schedule past the first year, or the size of the five reactors. It says the purchase agreements include meaningful prepayments and advances, without an amount. The fuel may also go to later Aurora plants and to refuelling Oklo’s first reactor in Idaho.

Meta is paying part of it, and is not a party. The release says Meta’s prepayment for future Oklo power supports the purchase. Oklo’s quarterly report, filed November 6, gives the mechanics: Oklo entered a supply agreement with Centrus on September 30 to support powerhouses for Meta, subject to conditions, and on November 2 an initial funding amount from Meta was released from escrow and paid directly to Centrus as a credit toward fuel orders. Neither document gives the amount. The report calls Meta a prospective customer.

The contracts depend on capacity Centrus has yet to build. The release’s risk language cites the need to satisfy contractual conditions, a long-term extension of Centrus’s lease of the Piketon site from the Department of Energy, and financing for its expansion there and in Oak Ridge, Tennessee.

Five reactors would be 75 to 375 MW, between 6% and 31% of the campus planned for Meta

Electric capacity in megawatts. Top: five Aurora powerhouses at the 15 to 75 megawatts each that Oklo’s quarterly report gives as the design’s range; the solid bar is five at 15 MW and the outline runs to five at 75 MW. Bottom: the 1.2 GW campus Oklo plans for Meta in Pike County, Ohio, targeted to reach full size by 2034. The top row is our arithmetic, not a company figure: neither the release nor the report gives a size for the Ohio units. It compares capacity, not energy delivered.

0300 MW600 MW900 MW1,200 MWFive Aurora powerhousesat Oklo’s stated 15–75 MW eachFive powerhouses at 15 MW each: 75 MW, 6.3% of the campusFive powerhouses at 75 MW each: 375 MW, 31.3% of the campus75–375 MWPlanned Meta campus, Ohiofull size targeted by 2034Planned campus in Pike County, Ohio: 1,200 MW, targeted for 20341,200 MW
03006009001,200Five powerhousesat 15–75 MW eachFive powerhouses at 15 MW each: 75 MW, 6.3% of the campusFive powerhouses at 75 MW each: 375 MW, 31.3% of the campus75–375Meta campustarget, by 2034Planned campus in Pike County, Ohio: 1,200 MW, targeted for 20341,200

How much of the campus, and how much fuel exists

Five reactors are at most 31% of the Ohio campus. Oklo’s report describes the Aurora as a 15 to 75 megawatt design. Five at 75 MW are 375 MW, 31.3% of 1,200 MW; five at 15 MW are 75 MW, 6.3%. At 75 MW the full campus would take 16 reactors. Under the January agreement the first phase is targeted for as early as 2030 and the full 1.2 GW by 2034. Oklo’s report expects its first powerhouse to be deployed in 2028–2029; its first project is in Idaho.

Centrus runs the only US plant licensed to make this fuel for commercial use, and it has made 900 kg a year. The Government Accountability Office describes Piketon as the only US facility licensed to enrich uranium up to 19.75% for commercial purposes. Its 16-centrifuge cascade produced more than 1,900 kg under Department of Energy contracts that ended on June 30, 2026 and cost about $475M from 2019, according to the GAO. No source gives its rate since. Centrus plans an initial build-out of 12 tonnes a year, with the first new capacity by 2029, the year the Oklo deliveries are scheduled to begin. The Energy Department estimated in 2024 that US demand would reach 50 tonnes a year by 2035. The three figures are not in one unit: the 900 kg is uranium hexafluoride, about 600 kg of uranium by the GAO’s conversion, and the demand figure is tonnes of uranium.

How much of that five reactors would take is not public. Oklo has not stated the fuel load of an Aurora core in the documents we read. The one reference point is the 5 tonnes of recovered fuel Idaho National Laboratory awarded it in 2019 for its first Idaho reactor. Oklo also carried $68.7M of prepaid enriched uranium on its balance sheet at September 30, from nothing at the end of 2025; the report does not name the supplier.

Oklo is one of several customers for the same new capacity. Centrus’s contingent commitments for output from capacity it has yet to build rose from about $3.0B at June 30, before the X-energy agreement announced on August 6, to about $5.4B at September 30, of which $5.1B was under definitive agreements; contracts with Radiant and Antares were announced in September. The November 12 release repeats $5.4B. Oklo’s September 30 agreement may already be inside that figure, and neither company says how much of it is Oklo’s.

Centrus has made 0.9 tonnes of HALEU a year and plans 12; the Energy Department sees demand of 50 by 2035

Tonnes of HALEU a year. Centrus’s output under the federal contract that ended June 30, 2026, 900 kg a year from one 16-centrifuge cascade (pink); the initial build-out Centrus plans, with first new capacity by 2029 (dashed); and US demand by 2035 as the Department of Energy estimated in 2024, cited by the Government Accountability Office (faint grey). The planned capacity is a company plan that depends on financing and a lease extension. Other suppliers are also building capacity and are not shown. The units differ: the 900 kg is uranium hexafluoride, about 0.6 tonnes of uranium; the demand figure is tonnes of uranium; the source gives no unit for the 12 tonnes.

0 t10 t20 t30 t40 t50 tCentrus’s output to June 2026one 16-centrifuge cascade, under a federal contractCentrus: 900 kg of HALEU, as uranium hexafluoride, a year from its 16-centrifuge cascade under the Department of Energy contract that ended June 30, 20260.9 tCentrus’s planned initial build-outfirst new capacity by 2029Centrus: an initial build-out of 12 tonnes of HALEU a year, with first new capacity by 202912 tUS demand by 2035the Department of Energy’s 2024 estimateDepartment of Energy, 2024, as cited by GAO: demand of 50 tonnes of HALEU a year by 203550 t
0 t10 t20 t30 t40 t50 tCentrus, to Junefederal contractCentrus: 900 kg of HALEU, as uranium hexafluoride, a year from its 16-centrifuge cascade under the Department of Energy contract that ended June 30, 20260.9 tCentrus, plannedfirst capacity by 2029Centrus: an initial build-out of 12 tonnes of HALEU a year, with first new capacity by 202912 tUS demand, 2035DOE, 2024Department of Energy, 2024, as cited by GAO: demand of 50 tonnes of HALEU a year by 203550 t

Centrus’s commitments for new capacity went from $3.0B to $5.4B in one quarter; Oklo’s part is not broken out

Centrus’s contingent customer commitments for enriched uranium from capacity it has yet to build, $ billions, at two dates: under definitive agreements (strong grey) and other commitments (grey). They cover both HALEU and the low-enriched uranium ordinary reactors use, and depend on Centrus building the capacity. The November 12 release gives the same $5.4B total as the September 30 figure.

Definitive agreementsOther commitments
0$2B$4B$6BAs of Jun 30, 2026second-quarter results, before X-energyJun 30, 2026: $2.4B under definitive agreementsJun 30, 2026: $0.6B of other commitments$3BAs of Sep 30, 2026third-quarter results; repeated November 12Sep 30, 2026: $5.1B under definitive agreementsSep 30, 2026: $0.3B of other commitments$5.4B
0$2B$4B$6BJun 30Jun 30, 2026: $2.4B under definitive agreementsJun 30, 2026: $0.6B of other commitments$3BSep 30Sep 30, 2026: $5.1B under definitive agreementsSep 30, 2026: $0.3B of other commitments$5.4B

What Oklo has to spend

Oklo has $3.13B and almost no revenue. At September 30 it held $1,550M of cash and $1,581M of marketable securities. In the nine months to that date it raised $2.29B gross by selling 32.6M shares at an average of $70.19, used $111M of cash in operations and spent $281M on property and equipment, $392M together. Revenue was $3.1M and the loss from operations $195.2M. For 2026 it guides to $120–150M of operating cash use and $400–500M of capital spending.

No reactor of this design is licensed. Oklo is building its first Aurora in Idaho under Department of Energy authorization. Its report says it is uncertain when, if at all, it will obtain Nuclear Regulatory Commission approvals, and does not report a pending application for a commercial licence; it gives no licensing status for Ohio.

Oklo holds $3.13B after raising $2.29B from share sales this year, against $3.1M of revenue in nine months

Oklo, $ billions on the axis. Cash and marketable securities at September 30, 2026 (black); and, for the nine months to that date, gross proceeds from share sales (strong grey), purchases of property and equipment and cash used in operations (pink), and revenue (grey), from the 10-Q. The revenue bar is too small to see at this scale.

0$1B$2B$3BCash and marketable securitiesSeptember 30Cash and equivalents $1,550M plus marketable securities $1,581M$3.13BNine months to September 30, 2026Equity raised, grossGross proceeds from at-the-market share sales: $2,289M$2.29BPurchases of property and equipmentPurchases of property and equipment: $280.9M$281MCash used in operationsCash used in operating activities: $110.9M$111MRevenueRevenue: $3.1M$3.1M
0$1B$2B$3BCash and securitiesSeptember 30Cash and equivalents $1,550M plus marketable securities $1,581M$3.13BJan–Sep 2026Equity raisedGross proceeds from at-the-market share sales: $2,289M$2.29BCapital spendingPurchases of property and equipment: $280.9M$281MOperating cash usedCash used in operating activities: $110.9M$111MRevenueRevenue: $3.1M$3.1M
Oklo’s third quarter ($M)
ItemQuarterNine months
Revenue1.93.1
Loss from operations71.0195.2
Net loss41.7123.3
Cash used in operationsn/a110.9
Purchases of property and equipmentn/a280.9
Gross proceeds from share salesn/a2,289
Cash and marketable securities, September 303,131

What this changes on inthesingularity.ai

  • Lead for a tracker of nuclear power contracted to data centers: the Oklo–Meta campus should be carried as a 1.2 GW target with fuel contracted for up to five reactors, 75–375 MW on Oklo’s stated unit sizes, not as 1.2 GW of contracted supply.
  • W.062 covered nuclear deals from plants that already run. Lead: for new reactors of this type HALEU supply is one constraint: the one US plant licensed to make it commercially produced 0.9 tonnes a year under its federal contract. Centrus’s build-out schedule is a series to follow.
  • Lead: the quantity and price in the Oklo–Centrus contracts, and the amount of Meta’s prepayment, are undisclosed. Oklo’s annual report or a contract exhibit may give them.

Sources and method

ItemFigureSource
The contractsMultiple definitive, multi-year contracts; enough HALEU to support up to five Aurora powerhouses for multiple years; deliveries scheduled to begin in 2029 from Centrus’s plant in Pike County, Ohio; prepayments and advances; Meta’s prepayment for future Oklo power supports the purchase; the contracts formalize a June 2026 letter of intent; Centrus has secured $5.4 billion in customer contracts and commitments; conditions and risksOklo and Centrus, joint release, filed by Centrus, Nov 12
The contractsDate of the announcementInvesting.com, Nov 12
BeforeLetter of intent, non-binding, for up to five Aurora powerhouses with deliveries from 2029; the 5 tonnes of recovered fuel awarded in 2019NEI Magazine, Jun 23
BeforeDate of the letter of intent, June 18, 2026Centrus, release, Jun 18
OkloA HALEU supply agreement with Centrus entered September 30, subject to conditions; an initial funding amount from Meta released from escrow and paid to Centrus on November 2; Aurora of 15–75 megawatts electric; first powerhouse in 2028–2029; cash and marketable securities of $3,131M; loss from operations of $71.0M in the quarter and $195.2M in nine months; revenue; cash used in operations $110.9M; purchases of property and equipment $280.9M; $2,289M gross from share sales at an average of $70.19; prepaid enriched uranium of $68.7M; 2026 guidance; licensingOklo, 10-Q for the third quarter of 2026, Nov 6
MetaPrepayment agreement announced January 9, 2026 for a 1.2 GW campus in Pike County, Ohio; first phase as early as 2030; full capacity by 2034World Nuclear News, Jan 9
CentrusContingent commitments of about $5.4B, $5.1B of it under definitive agreements, at September 30; total backlog of $7.0B; cash of $2,236M; revenue of $55.5MCentrus, third-quarter release, Nov 4
CentrusContingent commitments of about $3.0B, $2.4B of it under definitive agreements, at June 30Centrus, second-quarter release, Aug 5
CentrusX-energy agreement announced August 6; HALEU as uranium enriched to between 5% and 20%World Nuclear News, Aug 6
HALEU supply900 kg a year from a 16-centrifuge cascade; more than 1,900 kg produced; a planned initial build-out of 12 tonnes a year, first new capacity by 2029; a Department of Energy task order of June 30, 2026 with a $900M base, 1 tonne due by March 2032, and options at $17M a tonnePOWER, Jul 2
HALEU supplyCost of the demonstration and production contracts of about $475M from 2019 to June 30, 2026; Piketon as the only US facility licensed to enrich uranium to 19.75% for commercial purposes; 900 kg of uranium hexafluoride as about 600 kg of uranium; Department of Energy estimate (2024) of 50 tonnes a year of demand by 2035; 21.2 tonnes expected available for demonstrations by the end of 2028GAO-26-107385, Aug 20
HALEU supplyRadiant and Antares contracts announced September 9 and 17American Nuclear Society, Sep 21

The release is the joint Oklo and Centrus statement as Centrus filed it with the SEC; the exhibit carries no date, and the date is from news reports. We give no share prices: we could not confirm closing prices for November 12. Capacity: 5 × 15 = 75 MW and 5 × 75 = 375 MW; 75 ÷ 1,200 = 6.25%; 375 ÷ 1,200 = 31.25%; 1,200 ÷ 75 = 16 units. The 15–75 MW range is what Oklo’s 10-Q gives for the Aurora design; no source gives the size of the Ohio units, and the 10-Q says the design may later reach 100 MW and higher, which would raise the upper figure. These are shares of nameplate capacity, not of energy. Fuel: Centrus’s rate under the federal contract was 900 kg a year, 0.9 tonnes. Centrus’s 900 kg is uranium hexafluoride, about 0.6 tonnes of uranium by the GAO’s conversion; the 50-tonne demand figure is tonnes of uranium; the source gives no unit for the 12 tonnes. We therefore give no ratio between them. We do not estimate the fuel five reactors need, because Oklo has not published a core load. Centrus: 5,400 − 3,000 = 2,400 ($M) between June 30 and September 30, 92 days. Oklo: 1550.1 + 951.8 + 629.0 = 3130.9, against the 3130.8 the 10-Q totals; 110.9 + 280.9 = 391.8.

Wire reports are written within hours of the news, on a six-hour schedule. Each lists its sources and shows the arithmetic behind its figures. Not investment advice.