W.089SoftBank had reserved more than 13 GW of gas turbines, mostly from GE Vernova, the WSJ reports. Set against GE Vernova’s 58 GW of slot reservations that is 22%, and about eight months of its turbine output; GE Vernova says the changes had no impact
SoftBank had reserved more than 13 GW of gas turbines at the peak, largely from GE Vernova, the Wall Street Journal reported on November 11, and cancelled the excess as further payments approached. Set against the 58 GW of slot reservations GE Vernova reported at the end of September, that is 22%, and about 8 months of its turbine output. A GE Vernova spokesperson told the Journal there was no negative or positive impact on the company. Its reservations fell from 63 GW to 58 GW in the third quarter, a quarter in which 13 GW converted to firm orders.
What is new
The Journal gave the reservations a size and said most were GE Vernova’s. SoftBank’s results on November 10 disclosed a ¥597.2B loss on power-generation equipment for US data centers, which W.070 set out, but gave no gigawatts and named no manufacturer in those results. According to accounts of the Journal’s report, which cites people familiar with the matter, SoftBank had reserved more than 13 GW of gas turbines at the peak, most of it from GE Vernova, for a gas plant in Ohio and other planned sites. The reservations exceeded what those projects needed. As further payments approached SoftBank cancelled the excess and, according to one person the Journal cited, unwound some orders that were further along. A GE Vernova spokesperson told the Journal there was “no negative or positive impact” on the company. We have not read the Journal’s article; the accounts are listed below.
How much was cancelled is not reported. The 13 GW is the peak total, not the cancelled amount. SoftBank’s loss has two parts: ¥457.0B of non-refundable advances written off and ¥140.2B for changing and settling contracts. It had paid ¥1,500.9B in all, so the loss is 40% of what it paid, and ¥1,043.9B of payments remains, by our subtraction. Chief financial officer Yoshimitsu Goto said on November 10, of Elon Musk’s claim that SoftBank was defaulting on turbine orders, “There is no such default.”
GE Vernova’s backlog and reservations nearly doubled in a year, to 122 GW
GE Vernova gas turbine firm backlog (solid) and slot reservation agreements (dashed), gigawatts, at each quarter end, with the total above. A slot reservation holds a production slot for a fee and is not yet a firm order. From the company’s releases and its January call.
GE Vernova gas turbine commitments by quarter
| Quarter end | Firm backlog (GW) | Slot reservations (GW) | Total (GW) | 13 GW as a share of reservations |
|---|---|---|---|---|
| Q3 2025 | 33 | 29 | 62 | 45% |
| Q4 2025 | 40 | 43 | 83 | 30% |
| Q1 2026 | 44 | 56 | 100 | 23% |
| Q2 2026 | 53 | 63 | 116 | 21% |
| Q3 2026 | 64 | 58 | 122 | 22% |
How large 13 GW is
It is the size of a quarter’s conversions at GE Vernova. GE Vernova held 58 GW of slot reservations and 64 GW of firm backlog on September 30. If all 13 GW had been GE Vernova’s, it would be 22% of the reservations and 11% of the two together; the Journal says most, not all, was. GE Vernova has said it can build about 20 GW a year from mid-2026, so 13 GW is about 8 months of output. In the third quarter it signed 11 GW of new contracts, converted 13 GW of reservations to orders and shipped 5 GW. Against Siemens Energy’s 104 GW of backlog and reservations, 13 GW is 12.5%.
GE Vernova’s third-quarter figures neither show nor rule out a cancellation. Reservations fell from 63 GW to 58 GW, the first fall in the five quarters shown. The release’s rounded figures account for it: 63 plus 8 GW newly signed minus 13 GW converted is 58 GW. Firm backlog reconciles the same way, 53 + 3 + 13 − 5 = 64 GW. The figures are whole gigawatts, the second quarter’s are 1 GW off on the same sum, and the releases do not say whether signings are net of cancellations. SoftBank booked its loss in the half year to September 30, so its cancellations were probably made by then; they are not visible in these totals. GE Vernova targets at least 130 GW under contract by the end of the year; its fourth-quarter figures will show whether it gets there.
13 GW is 22% of GE Vernova’s reservations and about what it converted to orders in a quarter
Gas turbine capacity in gigawatts. SoftBank’s figure (pink) is the peak total reserved across suppliers as the Journal reported it, “more than” 13 GW; the amount cancelled is not known. Dashed bars are slot reservations at September 30, 2026. Anthropic’s 1.7 GW is Caterpillar gas-fired generators, type not disclosed, shown for scale.
GE Vernova’s reservations fell by 5 GW in the third quarter as 13 GW became orders
GE Vernova slot reservation agreements, gigawatts: the June 30 total, reservations newly signed in the third quarter, reservations converted to firm orders, and the September 30 total. All four figures are from the company’s releases and are rounded to whole gigawatts; they reconcile for the quarter, which neither shows nor rules out a cancellation of a few gigawatts.
What it cost, and where the slots go
Spread over 13 GW, the loss is at most about $287 a kilowatt. That divides the $3.73B loss by everything reserved. Only part was cancelled, so the loss per cancelled kilowatt was higher by an amount that is not disclosed, and because the Journal’s figure is “more than” 13 GW the average is an upper bound. The $9.48B paid in all is at most about $729 a kilowatt reserved. Both figures divide all of SoftBank’s power-equipment payments, which cover purchase contracts as well as reservations, by turbine gigawatts. New turbines cost $2M to $2.5M a megawatt, $2,000 to $2,500 a kilowatt, according to Aurora Energy Research figures Reuters reported on November 9, and Anthropic agreed to pay about $2,000 a kilowatt, including engineering and construction, for generators another developer had ordered (W.049).
The advances were non-refundable, and analysts say the supplier can reassign the slot. GE Vernova’s shares closed down 3.89% on November 10, the day of SoftBank’s results. JPMorgan analysts wrote that day that GE Vernova could reassign slots to waiting customers if deliveries were delayed or cancelled, according to Options Trading Report. Reuters reported on November 9 that US delivery times for new turbines are about six years and that global orders exceed 100 GW against estimated production capacity of 60 to 70 GW, citing Wood Mackenzie. SoftBank said it holds rights to rebates of up to $2.1B on future equipment purchases, subject to conditions, and has recognised no asset for them.
SoftBank wrote off ¥457.0B of the ¥1,500.9B it had paid
SoftBank’s cumulative payments for power-generation equipment (“Silver Bands 7”) to September 30, 2026, the non-refundable advances written off in the half year, and the remainder, ¥ billions. The further ¥140.2B for changing and settling contracts is part of the ¥597.2B loss but is not shown, because the release does not say whether it came out of payments already made.
What this changes on inthesingularity.ai
- W.070 reported the loss without a size in gigawatts. The Journal’s figure supplies one: more than 13 GW reserved at the peak, mostly from GE Vernova.
- W.085 suggested tracking firm backlog and reservations for Siemens Energy and GE Vernova each quarter. This adds a reason to track the flows as well: new reservations, conversions and any cancellations. GE Vernova’s new signings fell to 11 GW in the third quarter from 20 GW in the second.
Sources and method
| Item | Figure | Source |
|---|---|---|
| WSJ report | SoftBank reserved well over 13 GW of turbines, largely from GE Vernova; cancelled excess reservations and unwound some more advanced orders; GE Vernova said the changes had “no negative or positive impact” | Zack Eiseman, overnight digest of the WSJ report, Nov 11 |
| WSJ report | More than 13 GW at the peak, most from GE Vernova, for a 9.2 GW gas plant in Ohio and other planned sites; GE Vernova ships roughly 20 GW a year | OfficeChai, Nov 11 |
| WSJ report | Excerpts: largely from GE Vernova, per people familiar with the orders; excess cancelled as additional payments loomed; one person on the unwound orders; a GE Vernova spokesperson on impact; reservation fees are non-refundable | Edge and Odds, Nov 11 |
| SoftBank | Payments $9.5B (¥1.5T); loss $3.7B (¥597.2B) = $2.9B (¥457.0B) + $0.9B (¥140.2B); $6.6B allocated to the Ohio project and others; rights to rebates of up to $2.1B on future purchases, no asset recognised | SoftBank Group, investor presentation, Nov 10 |
| SoftBank | Silver Bands 7: ¥1,500.9B ($9.48B) paid; loss ¥597.2B ($3.73B) = ¥457.0B of non-refundable advances + ¥140.2B of contract changes and settlements | Kabucho, summary of the Nov 10 release, as in W.070 |
| SoftBank | Advances $2.85B and settlements $0.88B; about $6.6B of payments still allocated to equipment; Goto: “There is no such default.” | The Deep Dive, Nov 10 |
| GE Vernova | Sep 30, 2026: backlog 64 GW, slot reservations 58 GW; 11 GW of new contracts (8 reservations, 3 orders); 13 GW converted; 5 GW shipped; at least 130 GW under contract targeted by year-end | GE Vernova, third-quarter release, Oct 28 |
| GE Vernova | Jun 30, 2026: backlog 53 GW, reservations 63 GW; 20 GW of new contracts; 20 GW of yearly output in the third quarter of 2026 and 24 GW in 2028 | GE Vernova, second-quarter release |
| GE Vernova | Mar 31, 2026: backlog 44 GW, reservations 56 GW | GE Vernova, first-quarter release |
| GE Vernova | Backlog and reservations 33 and 29 GW at Sep 30, 2025; 40 and 43 GW at Dec 31, 2025; capacity of about 20 GW a year from mid-2026 | GE Vernova, fourth-quarter 2025 call, Jan 28 |
| GE Vernova | JPMorgan, in a Nov 10 note: GE Vernova could shift orders to waiting customers if deliveries were delayed or cancelled | Options Trading Report, Nov 11 |
| GE Vernova | Shares closed at $797.04 on Nov 10, down 3.89% | MarketScreener, Nov 10 |
| Turbine market | New turbines cost $2M–2.5M a megawatt (Aurora Energy Research); US delivery times of about six years; global orders above 100 GW against estimated production capacity of 60–70 GW (Wood Mackenzie) | Reuters, via BOE Report, Nov 9 |
| Siemens Energy | 65 GW firm backlog and about 39 GW of slot reservations at Sep 30, 2026 | W.085, from the earnings call as reported by Investing.com |
| Anthropic | $3.4B for 1.7 GW of Caterpillar generators | W.049 |
We did not read the Journal’s article; its contents are taken from the accounts listed, which give the size as “well over” or “more than” 13 GW. Ratios use 13 GW. The true GE Vernova figure could be higher, since the total is more than 13 GW, or lower, since not all of it was GE Vernova’s. Shares: 13 ÷ 58 = 22.4%; 13 ÷ 122 = 10.7%; 13 ÷ (65 + 39) = 12.5%. Output: 13 ÷ 20 = 0.65 years = 7.8 months. Reservations: 63 + 8 − 13 = 58. Backlog: 53 + 3 + 13 − 5 = 64. Loss: 457 + 140.2 = 597.2; 597.2 ÷ 1500.9 = 39.8%; 1500.9 − 457 = 1043.9; in dollars 9.48 − 2.85 = 6.63. Per kilowatt: $3.73B ÷ 13 GW = $287; $9.48B ÷ 13 GW = $729; $3.4B ÷ 1.7 GW = $2,000. Dollar amounts for SoftBank are as reported with its results.
Wire reports are written within hours of the news, on a six-hour schedule. Each lists its sources and shows the arithmetic behind its figures. Not investment advice.