W.078Venture Global plans off-grid power for about 5 GW of AI compute by 2031 and has signed no customer. At the $5–7B per 250 MW its chief executive cited, 5 GW of data centers would cost $100–140B
Venture Global, the LNG exporter with plants in Louisiana, said on November 10 it expects to deliver the first 250 MW of AI compute from its own gas-fired power in late 2028, scaling to about 5 GW by the end of 2031, with potential for 10 GW by 2034. It has not signed a customer. At the $5–7B per 250 MW building that its chief executive cited as an industry benchmark, 5 GW of data centers would cost $100–140B before chips.
What Venture Global said
The power deals and the 10 GW ambition date from October; the 2028 start and the 5 GW target for 2031 are new. On October 15 Venture Global disclosed frame agreements, signed October 9, with GE Vernova and Baker Hughes for equipment for up to 16 power islands of 720 MW each, combined-cycle gas units, plus transformers and switchgear from GE Grid Solutions. With its third-quarter results it called an off-grid AI utility a potential new, additive line of business, to be built on land it controls at two sites in Cameron and Plaquemines parishes, Louisiana. Chief executive Mike Sabel said on the call that compute would come in 250 MW buildings and that the first 250 MW should come online in late 2028.
Little of it is firm yet. Beyond reservation fees and the capacity already reserved, the agreements carry no binding obligations until further reservations or purchase orders are signed, the October filing says; Venture Global has reserved eight of the remaining 15 islands with GE Vernova, with purchase orders for those expected from early 2027; the first island’s purchase order is expected by the end of 2026. The grid agreement has definitive reservations for the first five equipment packages. The equipment would cost about $17.2B if every order went ahead, subject to adjustment. On the call Sabel said the company had not yet signed deals with tenants, which it wants to be investment-grade companies and hyperscalers.
Up to 11.52 GW of new generation for up to 10 GW of compute
GW. Power islands are generating capacity: about 4.5 GW across six islands ordered, under construction or operating, as of October 15 (the November 10 release says about 4 GW); and up to 16 new islands of 720 MW, the solid part showing the eight islands reserved with GE Vernova (5.76 GW); the first island, whose purchase order is expected by the end of 2026, and the other seven are not reserved. Compute targets are the company’s, in GW of data-center capacity; the 2034 figure is a potential, “subject to customer commitments, market demand, and other commercial considerations.”
What it would cost
The data centers would cost far more than the power. Sabel said the rest of the industry builds such 250 MW buildings for $5–7B each, excluding chips; the company gave no cost or capex guidance of its own for the AI business. At that benchmark, the 20 buildings needed for 5 GW come to $100–140B, 2.2× to 3.1× Venture Global’s $44.6B of debt at September 30, and 10 GW to $200–280B. Sabel said the company plans to lease the buildings to investment-grade tenants on triple-net terms and does not expect to need outside equity for its current build plans; he said most of the capital would be needed in 2029 and 2030.
Per kilowatt, the equipment price is below other recent figures, though none measure the same thing. Spread over 11.52 GW, the $17.2B comes to about $1,490 a kilowatt, though it also covers grid equipment for up to 21 projects and excludes construction. Anthropic agreed to pay $3.4B, about $2,000 a kilowatt, for 1.7 GW of Caterpillar generators ordered by another developer, OnePWR, the FT reported; the price may include installation. IEEFA put the newest combined-cycle plant proposals at $2,500 a kilowatt or more in April. If all 16 islands used GE Vernova turbines, 11.5 GW would be about 9% of the 122 GW of gas-power backlog and slot reservations GE Vernova reported at September 30, some of which may already be counted there; the split between GE Vernova and Baker Hughes is not disclosed.
At the benchmark Sabel cited, 5 GW of data centers would cost $100–140B, more than twice the company’s debt
$B. Grey: Venture Global’s adjusted EBITDA, 2026 guidance and the cumulative 2027–29 figure Sabel gave on the call (“in excess of”). Pink: current and long-term debt at September 30. Strong grey: the October frame agreements if all purchase orders proceed. Bottom rows: our arithmetic, the number of 250 MW buildings times $5–7B; the dashed segment spans the range.
The frame agreements come to about $1,490 a kilowatt of generation
$ per kW of generating capacity. These measure different things: Venture Global’s $17.2B covers power-island equipment and grid gear if every order proceeds, not construction; Anthropic’s figure is generators bought from another developer’s orders; IEEFA’s is the whole cost of a new combined-cycle plant, excluding financing and pipelines.
The quarter
The LNG business grew. Third-quarter revenue rose 43% to $4.76B and adjusted EBITDA 69% to $2.58B, on 124 cargoes against 100 a year before. Venture Global raised its 2026 adjusted EBITDA guidance to $10.0–10.3B from $8.7–9.1B, a rise of 14% at the midpoint, and Sabel said cumulative adjusted EBITDA for 2027 to 2029 would be in excess of $30B. Its shares rose before the open on November 10.
What this changes on inthesingularity.ai
- When does replacing old GPUs beat building new power?: the frame agreements give an equipment price of about $1,490 a kilowatt for combined-cycle islands, lower per kilowatt than generator and plant figures, which cover different scopes; it excludes construction.
- Can markets fund the AI buildout?: Venture Global’s plan puts the data-center cost on tenants through triple-net leases; $100–140B by 2031 at the cited benchmark is a figure to set against the pack’s financing supply if a tenant signs.
- Worth tracking: the first power-island purchase order, due by the end of 2026, and the first tenant.
Sources and method
| Item | Figure | Source |
|---|---|---|
| Q3 2026 | Revenue $4.76B; net income attributable to common stockholders $2.55B; adjusted EBITDA $2.58B; 2026 EBITDA guidance $10.0–10.3B from $8.7–9.1B; debt and cash; off-grid AI utility described as a potential new, additive line of business; compute from late 2028 to about 5 GW by end-2031; sites in Cameron and Plaquemines parishes | Venture Global Q3 2026 release (8-K), Nov 10 |
| Call | First 250 MW in late 2028; potential for 10 GW by 2034; 250 MW buildings; no customer signed; $5–7B per 250 MW building excluding chips as an industry benchmark; triple-net leases with investment-grade tenants; 2027–29 EBITDA in excess of $30B | Q3 2026 call transcript, Motley Fool, Nov 10 |
| Frame agreements | Up to 16 power islands, deliveries through 2034; GE Vernova reservation for 8 of the remaining 15; first purchase order expected by end-2026; grid gear for up to 21 projects; about $17.2B if all orders proceed; no binding obligations beyond reservation fees and reserved capacity | Venture Global 8-K, Oct 15 (event Oct 9) |
| Frame agreements | Up to sixteen new 720 MW combined-cycle units; up to 10 GW of compute by end-2034, subject to customer commitments, market demand and other commercial considerations; about 4.5 GW across 6 existing islands | Venture Global press release, Oct 15 |
| Comparison | Newest combined-cycle proposals cost at least $2,500 per kW, excluding financing and pipelines | IEEFA, Apr 8, 2026 |
| Comparison | Anthropic to pay $3.4B for 1.7 GW of Caterpillar generators, FT reported | GuruFocus, via Yahoo Finance, Nov 9 |
| Comparison | GE Vernova gas power backlog and slot reservations: 122 GW at Sept 30 | GE Vernova Q3 2026 release, Oct 28 |
We could not load Venture Global’s posted call remarks; call statements are from the Motley Fool transcript. Power: 16 × 720 MW = 11,520 MW; 8 × 720 = 5,760 MW reserved, plus the first island; 11.52 ÷ 10 = 1.15 GW of generation per GW of compute at the 2034 potential. Data centers: 5,000 MW ÷ 250 = 20 buildings × $5–7B = $100–140B; 10,000 ÷ 250 = 40 × $5–7B = $200–280B. Debt: 1,694 + 42,918 = 44,612M; 100 ÷ 44.61 = 2.24, 140 ÷ 44.61 = 3.14. Per kW: $17.2B ÷ 11520000 kW = $1493, about $1,490; $3.4B ÷ 1,700,000 kW = $2000. GE Vernova share, if all islands were its turbines: 11.52 ÷ 122 = 9.4%. Quarter: 4756 ÷ 3329 = up 42.9%; 2583 ÷ 1525 = up 69.4%; guidance midpoint 10.15 ÷ 8.9 = up 14.0%.