W.154Giga Energy’s $1B lease on 60 MW is $1.67M a megawatt-year
Giga Energy said on November 17 that it has signed a $1B lease with an undisclosed US AI cloud provider for a 60 MW data center in Hunt County, Texas; its headline gives the term as 10 years. Spread evenly, that is $1.67M per megawatt per year, or about $139 per kilowatt a month, near the low end of 7 other leases with a stated value, term and size. The building was registered with the state at $384M, the local paper reported in July, and The Information reported that Giga had raised $3.4M of equity. Giga issued the release twice, under two project names. Argentum AI’s $630M, 20-year agreement with Kyndryl for an initial 10 MW, announced the same day, works out to $3.15M.
The lease
Giga announced a $1 billion lease on 60 MW. The release announces a $1 billion lease agreement with an undisclosed US-based AI cloud provider for a 60 MW data center on about 30 acres in Hunt County, Texas. Giga will develop, own and operate the campus. It says it broke ground in July and expects the site to be ready for service in spring 2027.
The term appears only in the headline. The headline says 10-Year; the body of the release does not state a term. Giga’s website repeats the headline and gives no further terms, and Reuters calls it a 10-year lease. The release does not say whether the $1 billion is base rent or includes power, services or fit-out, or whether rent escalates.
Spread evenly, it is $1.67 million a megawatt a year. $1 billion over 10 years is $100 million a year, and over 60 MW that is $1.67 million per megawatt, or $139 per kilowatt a month. The release does not say whether the 60 MW is IT load or utility power; if it is utility power, the rate per megawatt of IT load is higher.
Giga issued the release twice. A release at 09:00 Eastern called the site Project Marl, with a Houston dateline. A second at 11:35 called it Project Clay, with a Royse City dateline. The project facts are the same in both. Giga’s website lists only Project Clay, and Reuters reported one lease. We treat them as one project; Giga has not said so.
Giga’s lease is $1.67M a megawatt-year; 6 of 7 other leases are higher
Stated lease value divided by the term in years and by megawatts, in millions of dollars per megawatt per year. Pink: Giga Energy’s lease, $1 billion over the 10 years in its headline and 60 MW. Grey: 7 other data center leases, from the stated total value, base term and megawatts, lowest first. Dashed pink: Argentum AI’s agreement with Kyndryl, $630 million over 20 years on an initial 10 MW; the release does not say what the value covers, and more megawatts would lower the rate. Leases differ in whether megawatts are IT load, in escalators and in what the tenant pays for power and fit-out, so the comparison is loose.
The leases
| Lease | Value, $M | Years | MW | $M per MW-year | $ per kW-month |
|---|---|---|---|---|---|
| Giga Energy, Hunt County | 1,000 | 10 | 60 | 1.67 | 139 |
| Applied Digital, Delta Forge 2 | 5,200 | 15 | 210 | 1.65 | 138 |
| Hut 8, Beacon Point campus | 19,600 | 15 | 704 | 1.86 | 155 |
| Host Digital, Oklahoma | 1,250 | 15 | 43 | 1.94 | 161 |
| Riot, Corsicana, for Anthropic | 28,000 | 15 | 910 | 2.05 | 171 |
| WhiteFiber, for Nscale | 865 | 10 | 40 | 2.16 | 180 |
| TeraWulf, for Anthropic | 19,000 | 20 | 401 | 2.37 | 197 |
| Bitdeer, Tydal, Norway | 4,700 | 16 | 121 | 2.43 | 202 |
| Argentum AI, at Kyndryl (initial MW) | 630 | 20 | 10 | 3.15 | 263 |
The site and the company
The state registration put the building at $384 million. The Royse City Herald-Banner reported on July 9 that Giga had taken over a project registered with the Texas Department of Licensing and Regulation at $384 million and 100,000 square feet. On 60 MW that is $6.4 million a megawatt. Such registrations may not cover all of a project’s cost, and Giga has not given one.
One year of the lease is about a quarter of that figure. $100 million a year is 26% of $384 million. That is revenue against a registered cost, before power and operating costs, and it is not a return.
Giga has raised little outside capital. The Information reported that Giga, founded in 2019, had raised $3.4 million of equity and under $5 million of debt and had lifetime revenue of more than $270 million; it sells transformers and switchgear. The registered cost is about 113 times that equity. The release names no lender or equity partner.
The site is below the Texas grid’s large-load threshold. A county commissioner said in August, the Herald-Banner reported, that the facility is proposed at 60 MW, under the 75 MW at which the grid operator treats a connection as a large load. Giga’s co-founder Brent Whitehead told county commissioners in July that power would come from Farmers Electric Cooperative over existing lines and that the company sought no tax abatement, the paper reported. He projected about $7.2 million a year of county property tax.
The schedule has shortened on paper. The release’s subheadline says the project will finish in under 8 months. In July the company told commissioners about 12 months, with completion in mid-2027.
The $1B lease is 2.6 times the $384M registered for the building
Millions of dollars. Pink: the lease value Giga announced. Dashed pink: one year of it if spread evenly over the 10 years in the headline, 1,000 ÷ 10; the release gives no payment schedule. Black: the cost in the state registration for the building, as reported by the Royse City Herald-Banner on July 9; it may not include all equipment. Grey: the $3.4 million of equity The Information reported Giga had raised, which at this scale is barely visible.
Argentum AI and Kyndryl
A second headline value came out the same day. Argentum AI announced a 20-year, $630 million data center collaboration with Kyndryl for an initial 10 MW at Kyndryl’s facility in Boulder, Colorado, to run Nvidia B300 systems. The release does not say who pays whom or what the $630 million covers.
On the initial 10 MW it is $3.15 million a megawatt a year. That is $263 per kilowatt a month, above every lease in the first chart. The parties say they intend to broaden the collaboration; if the value covers more than 10 MW, the rate is lower.
It is small for Kyndryl. $630 million over 20 years is $31.5 million a year, about 0.2% of Kyndryl’s latest quarterly revenue annualized. Reuters reported in October that Argentum, founded in 2025, was in talks for $5 billion of chip financing.
At about $139 per kilowatt a month, Giga’s lease sits in the turnkey range Fermi gave
Dollars per kilowatt a month. Pink: Giga’s lease value spread evenly, $1.6667 million ÷ 12 ÷ 1,000. Faint grey with an outline: the ranges for powered shell and turnkey leases that Fermi gave in November, the first on its call and the second in its slides as Investing.com described them, as used in W.097; they describe market deals in general. Dashed pink: Argentum AI’s agreement with Kyndryl on its initial 10 MW. Giga’s figure may include items other than fixed rent, which the release does not specify.
What this changes on inthesingularity.ai
- W.151 proposed a table of data center agreements by value per megawatt-year. This post adds five: Giga at $1.67 million, Hut 8, Host Digital, Bitdeer and, with caveats, Argentum.
- What does a blue Texas mean for the data center boom? Lead: a 60 MW site sized under the 75 MW large-load threshold and served by a cooperative’s existing lines. The pack could count projects sized below the threshold.
- W.148 used a state registration for Core Scientific’s Hunt County site. Giga’s is in the same county, at $6.4 million a megawatt on the registered figure.
- Who funds the neoclouds? Lead: a landlord with $3.4 million of reported equity building for an unnamed AI cloud provider, with no financing disclosed.
Sources and method
| Item | Figure | Source |
|---|---|---|
| The lease | A $1 billion lease agreement with an undisclosed US-based AI cloud provider; “10-Year” in the headline; 60 MW data center on about 30 acres in Hunt County, Texas, which Giga will develop, own and operate; ground broken in July; ready for service in spring 2027; finished in under 8 months, per the subheadline; about 300 construction jobs and 24 permanent jobs at an estimated $116,000 to $180,000 a year; closed-loop cooling | Giga Energy release, Project Clay, Nov 17 |
| The lease | The same terms under the name Project Marl, issued earlier the same day with a Houston dateline | Giga Energy release, Project Marl, Nov 17 |
| The lease | One 10-year lease, worth about $1 billion, for the project named Clay | Reuters, via SRN News, Nov 17 |
| The lease | Giga’s site repeats the release headline for Project Clay; its modular builds are described as nine months from shovel-ready to rack-ready | Giga Energy website |
| The site | Giga took over a project that BT Gateway Data Center LLC registered with the Texas Department of Licensing and Regulation on June 23: $384 million, 100,000 square feet, in unincorporated Hunt County east of Royse City | Royse City Herald-Banner, Jul 9 |
| The site | About 30 acres; power from Farmers Electric Cooperative over existing lines, with Giga paying for upgrades; no tax abatement sought; projected county property tax of about $7.2 million a year; construction of about 12 months, finishing in mid-2027; 20 to 24 permanent jobs | Royse City Herald-Banner, Jul 21 |
| The site | Proposed at 60 megawatts, below the 75 MW threshold for large loads at the Texas grid operator | Herald-Banner, via Yahoo, Aug 7 |
| Giga Energy | Founded in 2019; $3.4 million of equity and under $5 million of debt raised; lifetime revenue of more than $270 million; sells transformers and switchgear | The Information |
| Argentum AI | A 20-year, $630 million data center collaboration for an initial 10 MW at Kyndryl’s Boulder, Colorado facility, for Nvidia B300 systems; deployment under way | Argentum AI release, Nov 17 |
| Argentum AI | Founded in 2025; in talks for $5 billion of chip financing, two sources said | Reuters, via The Star, Oct 27 |
| Argentum AI | Kyndryl’s revenue in the quarter to September 30, 2026: $3,651 million | Kyndryl release, Nov 4 |
| Other leases | Bitdeer, Tydal: about $4.7 billion over a 16-year base term on 121 MW of IT load; about $202 per kW a month on average, with electricity passed through | Bitdeer release, Aug 4 |
| Other leases | Host Digital: about $1.25 billion over a 15-year base term on 43 MW of critical IT load | HCWC release, Aug 31 |
| Other leases | Hut 8, Beacon Point: $19.6 billion of base-term value on 704 MW of IT load under 15-year leases | Hut 8 release, Jul 20 |
| Other leases | Applied Digital, Delta Forge 2: about $5.2 billion over 15 years on 210 MW. WhiteFiber and Nscale: about $865 million over 10 years on 40 MW | W.151 |
| Other leases | Riot and Anthropic, Corsicana: about $28 billion over 15 years on 910 MW | W.010 |
| Other leases | TeraWulf and Anthropic: about $19 billion over 20 years on 401 MW | W.013 |
| Benchmarks | Powered shell $64–80 and turnkey $130–163 per kW a month, from Fermi’s third-quarter call (powered shell) and Investing.com’s account of its slides (turnkey) | W.097 |
What we read. Both Giga releases, Giga’s website, Reuters’ report, three Herald-Banner articles, The Information’s profile, Argentum’s release, Kyndryl’s results release and the Bitdeer, HCWC and Hut 8 releases. Figures for the other leases are from earlier Wire posts and were not checked again. Arithmetic. Giga: 1,000 ÷ 10 = 100; ÷ 60 = 1.667; × 1,000,000 ÷ 1,000 ÷ 12 = $138.9 per kW a month. Other leases, $ million per MW per year: 5,200 ÷ 15 ÷ 210 = 1.65; 19,600 ÷ 15 ÷ 704 = 1.86; 1,250 ÷ 15 ÷ 43 = 1.94; 28,000 ÷ 15 ÷ 910 = 2.05; 865 ÷ 10 ÷ 40 = 2.16; 19,000 ÷ 20 ÷ 401 = 2.37; 4,700 ÷ 16 ÷ 121 = 2.43. Argentum: 630 ÷ 20 = 31.5; ÷ 10 = 3.15; $262.5 per kW a month; 31.5 ÷ (3,651 × 4) = 0.22%. Registered cost: 384 ÷ 60 = 6.40; 1,000 ÷ 384 = 2.60; 100 ÷ 384 = 26.0%; 384 ÷ 3.4 = 113. Conflicts between sources. The two releases name the project Marl and Clay and carry different datelines. Construction is under 8 months in the releases’ subheadline, about 12 months in the July presentation and nine months on Giga’s product page. Permanent jobs are 24 in the releases and 20 to 24 in July. Reuters says about $1 billion; the release says $1 billion. Limits. That Marl and Clay are one project is our reading of identical facts; if they were two leases the totals would double and the rate would not change. The tenant, the payment schedule, escalators, what the $1 billion covers, the financing and the build cost are not disclosed. The registered cost is as reported by the local paper from a state filing made by the previous developer and may not match what Giga builds. The megawatts in the comparison are not on one basis: some are IT load, and Giga’s and Argentum’s are unspecified. Bitdeer’s rate includes services, with electricity passed through. Argentum’s rate uses an initial capacity and an undefined value. The benchmarks are a third party’s, as reported second-hand from its call and from an account of its slides.
Wire reports are written within hours of the news, on a six-hour schedule. Each lists its sources and shows the arithmetic behind its figures. Not investment advice.