W.148Core Scientific’s $1.3B Texas filing matches its stated cost for AMD’s 110 MW

Core Scientific registered a $1.3B data center building in Hunt County, Texas, with the state licensing agency on November 13, according to Texas Data Center Watch; Data Center Dynamics reported the filing on November 15. Headlines attached the figure to a 285 MW campus, which would be $4.56M a megawatt. The state record gives no megawatts, the tracker says. Against the 110 MW AMD has leased at the site it is $11.8M a megawatt, inside the $11–12M a megawatt Core Scientific’s management quotes for its AMD builds. At that rate the 529 MW it leased in July would cost $5.8B to $6.3B. In March the company said the site could begin energizing in 2027; its deck now estimates first delivery to AMD in the first half of 2028.

Estimated cost in the Texas registration
$1.3B
one building of 341,325 square feet; registered, not approved
Per megawatt on AMD’s 110 MW lease
$11.8M
management quotes $11–12M a megawatt for the AMD builds
Per megawatt on the 285 MW in the headlines
$4.56M
285 MW is the whole site’s leasable capacity, per the company
529 MW of July leases at $11–12M a megawatt
$5.8–6.3B
against $4.4B of commitments and $804M of cash at September 30

The filing

Core Scientific registered one building. Texas Data Center Watch, a tracker of state records, says the building was registered on November 13, 2026 with the Texas Department of Licensing and Regulation: an estimated $1.3 billion for a data center core and shell building of about 341,325 square feet in Hunt County, northeast of Dallas. Data Center Dynamics reported the filing with construction running from November 2026 to September 2028, according to The CODEW’s summary. We could not read the Data Center Dynamics article or the state record directly.

A registration is not an approval. The estimated cost is the filer’s own figure. The tracker gives the scope as a core and shell building with site and infrastructure improvements, with no tenant assigned. It lists the project as under construction, citing a local newspaper.

The megawatts in the headline are not in the filing. Data Center Dynamics’ headline calls it a 285 MW data center. The tracker says the state record gives no megawatts. The 285 MW is the figure Core Scientific gave in March, as “up to,” for the leasable capacity of the whole Hunt County site, which its 10-Q puts at about 430 MW of gross utility power.

AMD’s lease there is signed. The summary of the report says AMD is “set to lease” 110 MW. Core Scientific’s 8-K shows the leases were signed on July 27, and its third-quarter deck puts Hunt County’s share at about 110 MW, with first delivery estimated in the first half of 2028.

The $1.3B is $4.56M a megawatt on the campus figure and $11.8M on AMD’s lease

The $1.3 billion estimated cost in the registration divided by each megawatt figure Core Scientific has given for the Hunt County site, in millions of dollars per megawatt. Pink: the 110 MW AMD has leased. Grey: the site’s leasable capacity and gross utility power. The pink bar’s value is in its label. The dashed lines mark $11 million and $12 million a megawatt, the build cost management quoted for the AMD leases on its November 5 call. By the tracker’s reading the registration states no megawatts; which figure it corresponds to is our inference.

0$2M$4M$6M$8M$10M$12M$14MGross utility power, 430 MWwhole site, per the 10-QGross utility power: $1,300 million ÷ 430 MW = $3.02 million per MW$3.02MLeasable capacity, 285 MWwhole site, per the companyLeasable capacity: $1,300 million ÷ 285 MW = $4.56 million per MW$4.56MAMD’s lease, 110 MW: $11.82Mper the Q3 deckAMD’s lease: $1,300 million ÷ 110 MW = $11.82 million per MWmanagement: $11–12M a MW
0$4M$8M$12M430 MWgross utility powerGross utility power: $1,300 million ÷ 430 MW = $3.02 million per MW$3.02M285 MWleasable capacityLeasable capacity: $1,300 million ÷ 285 MW = $4.56 million per MW$4.56M110 MW: $11.82MAMD’s leaseAMD’s lease: $1,300 million ÷ 110 MW = $11.82 million per MW$11–12M

Which megawatts the cost belongs to

On the campus figure the cost would be low. $1.3 billion over 285 MW is $4.56 million a megawatt, and over 430 MW it is $3.02 million. Core Scientific’s management said on November 5 that the cost of its AMD builds was holding at $11 million to $12 million a megawatt.

On AMD’s 110 MW it matches. $1.3 billion over 110 MW is $11.82 million a megawatt. Management’s range applied to 110 MW gives $1.21 billion to $1.32 billion. The registration reads as the full cost of the building for AMD, not a shell for the whole campus. No source we read states this; it is our inference from the arithmetic.

The floor area points the same way. $1.3 billion over 341,325 square feet is about $3,809 a square foot. The four other Texas registrations below range from $446 to $1,000 a square foot. If the building holds 110 MW, that is about 322 watts a square foot.

Other Texas registrations run lower per megawatt. The tracker’s readings of four other filings give $2.88 million to $6.25 million a megawatt. State estimates often cover one scope of work, so they are a loose comparison: the tracker lists a separate $448 million fit-out registration for Vantage’s building, and Stream’s figure includes a substation. JLL forecast an average global construction cost of $11.3 million a megawatt for 2026, Quartz reported.

On AMD’s 110 MW the filing is $11.8M a megawatt; four other Texas filings are $2.9M to $6.3M

Estimated cost divided by megawatts for five Texas data center registrations, in millions of dollars per megawatt, from Texas Data Center Watch’s readings of state records. Pink: Core Scientific’s Hunt County building over AMD’s 110 MW, a megawatt figure from the company and not the filing. Grey: four other registrations, with megawatts as the tracker lists them. The dashed line is JLL’s forecast of the average global construction cost for 2026, $11.3 million a megawatt, as Quartz reported it. Registrations state the filer’s estimate and differ in scope; Vantage’s is for the shell only.

0$2M$4M$6M$8M$10M$12M$14MCore Scientific, Hunt County$1.3B, AMD’s 110 MWCore Scientific, Hunt County: $1.3B, AMD’s 110 MW = $11.82 million per MW$11.82MStream, Wilmer DFWC1$300M, 48 MWStream, Wilmer DFWC1: $300M, 48 MW = $6.25 million per MW$6.25MKati 2 Building 1, Willacy County$472M, 112 MWKati 2 Building 1, Willacy County: $472M, 112 MW = $4.21 million per MW$4.21MDigital Realty DFW45, Garland$300M, 80 MWDigital Realty DFW45, Garland: $300M, 80 MW = $3.75 million per MW$3.75MVantage TX12, San Antonio$277M, 96 MWVantage TX12, San Antonio: $277M, 96 MW = $2.88 million per MW$2.88MJLL 2026 global average: $11.3M
0$4M$8M$12MCore Scientific$1.3B, AMD’s 110 MWCore Scientific, Hunt County: $1.3B, AMD’s 110 MW = $11.82 million per MW$11.82MStream$300M, 48 MWStream, Wilmer DFWC1: $300M, 48 MW = $6.25 million per MW$6.25MKati 2 Building 1$472M, 112 MWKati 2 Building 1, Willacy County: $472M, 112 MW = $4.21 million per MW$4.21MDigital Realty DFW45$300M, 80 MWDigital Realty DFW45, Garland: $300M, 80 MW = $3.75 million per MW$3.75MVantage TX12$277M, 96 MWVantage TX12, San Antonio: $277M, 96 MW = $2.88 million per MW$2.88MJLL: $11.3M
The registrations
RegistrationEstimated cost, $MMWSquare feet$M per MW$ per sq ft
Core Scientific, Hunt County1,300110 (company)341,32511.823,809
Stream, Wilmer DFWC1300.048360,7506.25832
Kati 2 Building 1, Willacy County471.8112471,8844.211,000
Digital Realty DFW45, Garland300.080672,0003.75446
Vantage TX12, San Antonio276.996432,8002.88640

The AMD leases

Hunt County is about a fifth of the July agreement. Core Scientific signed 529 MW of 15-year leases on July 27. AMD leases 377 MW directly at Pecos, Muskogee and Hunt County. An unnamed neocloud leases 152 MW at Dalton and Auburn, with a credit support agreement among it, Core Scientific and AMD. Hunt County’s 110 MW is 21% of the total and the last to deliver.

At management’s rate the whole build costs about $6 billion. 529 MW at $11 million to $12 million a megawatt is $5.82 billion to $6.35 billion. The 10-Q lists about $4.4 billion of purchase and construction commitments, $804 million of cash and equivalents and $4.3 billion of long-term debt at September 30. The company says completing the AMD and neocloud sites will need more external financing.

None of the AMD leases is paying yet. The 10-Q says none had commenced at September 30. Third-quarter colocation revenue of $215.4 million, 92% of revenue, came from 485 MW billing, and CoreWeave was about 84% of nine-month revenue.

AMD holds a warrant and an option. The warrant covers up to 30 million shares at $23.47, vesting at 12,222 shares per megawatt, or about 6.5 million shares on 529 MW. AMD may lease a further 1,925 MW through December 28, 2028, which the 10-Q says is not a binding commitment.

Hunt County’s 110 MW is the last of the 529 MW to deliver, in the first half of 2028

Megawatts leased under Core Scientific’s July 27, 2026 agreements by site, approximate, from its third-quarter 2026 deck, with the estimated first delivery. Pink: Hunt County, leased by AMD. Grey: the other two sites AMD leases directly. Faint grey: the two sites leased by an unnamed neocloud with AMD credit support. The five sum to 529 MW; the 8-K gives 377 MW direct and 152 MW for the neocloud.

050100150200Pecos, TexasAMD directPecos, Texas: 185 MW, leased by AMD; first delivery estimated 1H 2027185 MW · 1H 2027Dalton, Georgianeocloud, AMD credit supportDalton, Georgia: 120 MW, leased by an unnamed neocloud; first delivery estimated 2H 2027120 MW · 2H 2027Hunt County, TexasAMD directHunt County, Texas: 110 MW, leased by AMD; first delivery estimated 1H 2028110 MW · 1H 2028Muskogee, OklahomaAMD directMuskogee, Oklahoma: 82 MW, leased by AMD; first delivery estimated 2H 202782 MW · 2H 2027Auburn, Alabamaneocloud, AMD credit supportAuburn, Alabama: 32 MW, leased by an unnamed neocloud; first delivery estimated 1H 202732 MW · 1H 2027
0100200PecosAMD directPecos, Texas: 185 MW, leased by AMD; first delivery estimated 1H 2027185 MWDaltonneocloudDalton, Georgia: 120 MW, leased by an unnamed neocloud; first delivery estimated 2H 2027120 MWHunt CountyAMD directHunt County, Texas: 110 MW, leased by AMD; first delivery estimated 1H 2028110 MWMuskogeeAMD directMuskogee, Oklahoma: 82 MW, leased by AMD; first delivery estimated 2H 202782 MWAuburnneocloudAuburn, Alabama: 32 MW, leased by an unnamed neocloud; first delivery estimated 1H 202732 MW

Timing and Texas

Delivery is estimated for 2028. In March Core Scientific said Hunt County could begin energizing in 2027 and reach full power by 2029. Its deck now estimates first delivery to AMD in the first half of 2028, and the registration, as reported, runs construction to September 2028.

The filing arrives between an election and an inauguration. Gina Hinojosa won the governor’s race on November 3 after pledging what she called “a moratorium” on data center approvals until the Legislature acts, the Texas Tribune and KWTX reported. She takes office on January 19, 2027.

No source we read says the filing protects the project. Pauses ordered from August under Governor Abbott cover environmental permits and new grid energization approvals, by Gibson Dunn’s account. It names the grid operator, the utility commission, the environmental agency and the water board and does not mention the licensing agency, though it quotes the directive as saying no state agency should advance data center approvals until an audit is done. Core Scientific’s 10-Q says Hunt County has an approved ERCOT interconnection ramp schedule. Management said on the call that the site has its stormwater permits and that air permits are still with the environmental agency. The 10-Q says the company cannot predict future policy changes.

Colocation revenue reached $215.4M in the third quarter on 485 MW, none of it from AMD

Core Scientific’s colocation revenue by quarter, in millions of dollars, with the megawatts billing in each under the quarter, from its third-quarter 2026 deck. Strong grey: the third quarter of 2026. Grey: the three quarters before. The revenue is from existing customers, chiefly CoreWeave; the 10-Q says none of the AMD leases had commenced at September 30.

0$80M$160M$240MQ4 2025: colocation revenue $31.3 million; 120 MW billing$31.3MQ4 2025120 MW billingQ1 2026: colocation revenue $77.5 million; 225 MW billing$77.5MQ1 2026225 MW billingQ2 2026: colocation revenue $136.7 million; 395 MW billing$136.7MQ2 2026395 MW billingQ3 2026: colocation revenue $215.4 million; 485 MW billing$215.4MQ3 2026485 MW billing
0$80M$160M$240MQ4 2025: colocation revenue $31.3 million; 120 MW billing$31.3MQ4 2025120 MWQ1 2026: colocation revenue $77.5 million; 225 MW billing$77.5MQ1 2026225 MWQ2 2026: colocation revenue $136.7 million; 395 MW billing$136.7MQ2 2026395 MWQ3 2026: colocation revenue $215.4 million; 485 MW billing$215.4MQ3 2026485 MW

What this changes on inthesingularity.ai

  • What does a blue Texas mean for the data center boom? Lead: a $1.3 billion Texas building registered ten days after the election, at a site that already had an ERCOT ramp schedule and stormwater permits and is still working on air permits. The pack could track which large Texas projects hold which approvals before January 19.
  • Who funds the neoclouds? Lead: Core Scientific’s AMD build, $5.8 billion to $6.3 billion at management’s rate for 529 MW, against $4.4 billion of commitments and a stated need for more external financing.
  • W.142. TensorWave’s 457 MW for OpenAI and Core Scientific’s 529 MW are both built around AMD hardware; here AMD is tenant or credit support, and the sites and schedule are disclosed.
  • Lead: a per-megawatt series from Texas registrations, with megawatts taken from company disclosures where the filing gives none.

Sources and method

ItemFigureSource
The filingCore Scientific filed with the Texas Department of Licensing and Regulation for a data center in Hunt County: $1.3 billion; 341,325 square feet of core and shell; construction November 2026 to September 2028; headline figure of 285 MW; AMD set to lease 110 MW; near a 190 MW battery storage systemData Center Dynamics, Nov 15, as summarised by The CODEW
The filingState record as read by the tracker: registered November 13, 2026; estimated cost $1.3 billion for a 341,326 square foot data center core and shell building with site and infrastructure improvements; no megawatts stated; tenant not assigned; project listed as under construction, citing the Herald-Banner; a separate $448 million fit-out registration for Vantage TX12. Other registrations: Stream, Wilmer DFWC1, $300 million, 48 MW, 360,750 square feet; Kati 2 Building 1, Willacy County, $472 million, 112 MW, 471,884 square feet; Digital Realty DFW45, Garland, $300 million, 80 MW, 672,000 square feet; Vantage TX12, San Antonio, $277 million, 96 MW, 432,800 square feetTexas Data Center Watch, verified Nov 16
The AMD leasesLeases signed July 27, 2026: 377 MW of critical IT load leased by AMD at Pecos, Muskogee and Hunt County; 152 MW leased by a neocloud at Auburn and Dalton, each with a credit support agreement among Core Scientific, the neocloud and AMD; 15-year terms with three five-year extensions; warrant to AMD for up to 30 million shares at $23.47, vesting at 12,222 shares per MWCore Scientific 8-K, dated Jul 27
The AMD leasesBy site, approximately: Pecos 185 MW, first delivery estimated 1H 2027; Dalton 120 MW, first delivery estimated 2H 2027; Hunt County 110 MW, first delivery estimated 1H 2028; Muskogee 82 MW, first delivery estimated 2H 2027; Auburn 32 MW, first delivery estimated 1H 2027; total contracted revenue of more than $24 billion across about 1.1 GW; colocation revenue and billing MW by quarter: Q4 2025 $31.3 million, 120 MW; Q1 2026 $77.5 million, 225 MW; Q2 2026 $136.7 million, 395 MW; Q3 2026 $215.4 million, 485 MWCore Scientific Q3 2026 deck, Nov 5
Core ScientificHunt County site: about 430 MW of gross utility power; purchase closed May 5, 2026 for about $232.5 million. AMD may lease a further 1,925 MW through December 28, 2028, not a binding commitment. No AMD lease had commenced at September 30. An approved ERCOT interconnection ramp schedule for Hunt County. Purchase and construction commitments of about $4.4 billion; long-term debt $4,302 million; 1,120 MW leased and 485 MW billable; CoreWeave about 84% of nine-month revenueCore Scientific 10-Q, Sep 30
Core ScientificQ3 2026 revenue $232.9 million, of which colocation $215.4 million; cash and equivalents $803.9 millionCore Scientific release, Nov 5
Core ScientificManagement on the cost of the AMD builds: holding at $11 million to $12 million a megawatt; Pecos and Hunt County have their stormwater permits; air permits still being worked through with the state environmental agencyQ3 2026 call transcript, Motley Fool, Nov 5
Core ScientificManagement described AMD’s backing of the neocloud leases as full credit support for the 15-year termGlobal Data Center Hub, Oct 20
The siteAnnounced in March 2026 as a campus of 430 MW gross and up to 285 MW leasable that could begin energizing in 2027 and reach full power by 2029Data Center Dynamics, Mar 2026
The siteSite in the Wieland community of Hunt County, on land owned by Telios, in collaboration with Core Scientific; Farmers Electric Cooperative is the area’s electricity provider; the developers said they would not seek tax incentiveseExtra, Mar 25
TexasGina Hinojosa won the governor’s race on November 3 after pledging a moratorium on data center approvals until the Legislature actsTexas Tribune, Nov 4
TexasHinojosa’s pledge, in an October 22 video: a moratorium on all data center approvalsKWTX, Nov 4
TexasDirectives issued under Governor Abbott from August 2026 paused environmental permits and new large-load energization approvals pending an audit; the directive says no state agency should advance data center regulatory approvals until then; audit reports due December 10; Legislature convenes January 12, 2027; inauguration January 19, 2027Gibson Dunn
BenchmarkJLL forecast an average global construction cost of $11.3 million per MW for 2026Quartz, May 2026

What we read. Core Scientific’s 8-K, 10-Q, third-quarter release and deck, a transcript of its call, Texas Data Center Watch’s readings of state records, The CODEW’s summary of the Data Center Dynamics report and the other reports listed. We could not read the Data Center Dynamics article, which is linked as the trigger, or the state record itself, so the cost, floor area and construction dates of the filing rest on two secondary readings that agree on those. Arithmetic. Per megawatt, $ million: 1,300 ÷ 430 = 3.02; 1,300 ÷ 285 = 4.56; 1,300 ÷ 110 = 11.82. Management’s range: 110 × 11 = 1,210; 110 × 12 = 1,320; 529 × 11 = 5,819; 529 × 12 = 6,348. Floor area: 1,300 million ÷ 341,325 = $3,809 a square foot; 110 million watts ÷ 341,325 = 322 watts a square foot. Other registrations: 300.0 ÷ 48 = 6.25; 471.8 ÷ 112 = 4.21; 300.0 ÷ 80 = 3.75; 276.9 ÷ 96 = 2.88. Sites: 185 + 120 + 110 + 82 + 32 = 529; 110 ÷ 529 = 20.8%. Warrant: 529 × 12,222 = 6.47 million shares. Colocation share: 215.4 ÷ 232.9 = 92.5%. Land: 232.5 ÷ 430 = $0.54 million per gross megawatt. Conflicts between sources. The tracker dates the registration November 13; the summary of Data Center Dynamics says filed November 15, the date of its report. The floor area is 341,325 square feet in the summary of Data Center Dynamics and 341,326 in the tracker. The summary says AMD is set to lease; the 8-K shows signed leases. The 8-K’s 377 MW and 152 MW sum to 529; the 10-Q and deck say approximately 530 MW. Data Center Dynamics’ headline attaches 285 MW to the filing; the tracker says the record states none. Limits. That the $1.3 billion corresponds to AMD’s 110 MW is an inference from the match with management’s range; the tracker gives the scope as core and shell with site and infrastructure improvements and the tenant as not assigned, which neither confirms nor rules it out. The megawatts for the other registrations are the tracker’s. The cost of the full 529 MW applies a range management quoted on a call and is not company guidance for a total. We do not use Core Scientific’s quarterly capital expenditure, which its release, cash flow statement and call give on bases we could not reconcile.