W.142TensorWave will host 457 MW of AMD chips for OpenAI, with no value or sites disclosed
TensorWave said on November 16 that it has a six-year agreement to provide OpenAI with 457 MW of dedicated capacity on AMD chips at several US sites, expected to start coming online in the first half of 2027 and to be complete by early 2028. It gave no contract value, named no sites and said nothing about who pays for the chips. The capacity equals 7.6% of the 6 GW OpenAI agreed to deploy with AMD. TensorWave’s Series A and B rounds total $450 million, and six days earlier its 222 MW lease at a Texas campus was terminated. Rates from three other contracts would put 457 MW over six years anywhere from about $5 billion to about $37 billion, depending on what the price covers.
What was announced
TensorWave will provide OpenAI with 457 MW of IT capacity for six years. Its release of November 16 calls the capacity dedicated and single-tenant. The headline says more than 450 MW and the body gives 457 megawatts of IT capacity. The release does not say when the six years start.
The chips are AMD’s. The capacity will use AMD Instinct MI455X GPUs in AMD’s Helios rack systems, at multiple US data center sites designed for those racks. The release describes the agreement as part of OpenAI and AMD’s previously announced partnership, which dates from October 2025, and calls TensorWave the first publicly announced neocloud provider supporting it.
The dates are expectations. Capacity is expected to begin coming online in the first half of 2027, with full deployment expected by early 2028.
The release leaves out most of the economics. It gives no contract value, price or minimum payment. It does not say who buys or owns the chips, how the build is financed, or whether AMD or OpenAI provides credit support or prepayment. It names no sites or landlords. It does not say whether the 457 MW counts toward OpenAI’s 6 GW commitment to AMD or toward the milestones in AMD’s warrant. The Next Web reported that neither company disclosed the value or the sites, and we found no report that gives either.
The agreement is 32 times TensorWave’s existing Tucson deployment and about twice the lease it lost
Megawatts. Black: TensorWave’s existing deployment at a TECfusions site in Tucson, per DCD. Strong grey: 20 MW of leases it added at two TECfusions sites for delivery in the first half of 2026. Faint grey: its lease at Fermi America’s Texas campus, measured as total facility power, which was terminated on November 10. Pink: the OpenAI agreement, measured as IT capacity. Grey: a 1 GW infrastructure agreement with TECfusions signed in October 2024. Dashed pink: the more than 2 gigawatts of long-term capacity TensorWave says it has secured, for which it lists no sites. The rows mix IT capacity, facility power and framework agreements, and the Tucson row is one site, not all of TensorWave’s operating capacity.
TensorWave’s capacity and money
TensorWave is small against what it has agreed to deliver. Its June release said 8,192 AMD MI325X GPUs were online. DCD reported an existing 14.4 MW deployment at Tucson and 20 MW of added leases at two TECfusions sites. The OpenAI agreement is 32 times the Tucson figure.
Its Series A and B rounds total $450 million. It raised $100 million in May 2025 and $350 million in June 2026 at a $1.55 billion valuation, both rounds co-led by Magnetar and AMD Ventures. It also announced a $43 million SAFE round in October 2024, which brings the total to $493 million. We found no disclosed debt facility.
A 222 MW lease in Texas ended six days before the announcement. Fermi America signed a lease with a TensorWave subsidiary on August 9 for 222 MW of total facility power, worth about $6.5 billion over 15 years. Fermi said on October 13 that it had signed a credit support agreement with AMD supporting the lease. The lease required conditions that included project-level financing. Fermi said on November 3 that they had not been fully met by October 31. Its 10-Q says the lease terminated on November 10 in accordance with its terms, and its release of November 12 says the AMD credit support ended with it. Neither gives a reason. W.097 covers what Fermi signed in its place.
The “more than 2 gigawatts” claim has not changed. TensorWave used the phrase in June, before the Fermi lease, and again on November 16, after it ended. The one large component we could identify is the 1 GW TECfusions agreement of October 2024. The OpenAI agreement would take 23% of 2 GW.
457 MW equals 7.6% of the 6 GW OpenAI agreed to deploy with AMD
Megawatts. Pink: the TensorWave agreement, 457 MW of IT capacity. Strong grey: the first 1 gigawatt of OpenAI’s agreement with AMD, which AMD’s October 2025 release said was set to begin in the second half of 2026. Black: the whole 6 gigawatt agreement. AMD’s release does not say whether its gigawatts are IT capacity, and TensorWave’s does not say whether its 457 MW counts against them; the percentage is our division.
AMD’s side
AMD said its first Helios racks at OpenAI came online in the third quarter. Its prepared remarks of November 3 said lead customers including OpenAI brought first Helios racks online in the quarter and that MI455X shipped in volume. It reported Data Center revenue of $8,546 million, up 97% from a year earlier and 64% of $13,377 million of revenue, and guided to about $17 billion of revenue for the fourth quarter. It did not say how much of OpenAI’s first gigawatt has been deployed.
AMD is an investor in the host. AMD Ventures co-led both of TensorWave’s rounds, and AMD had signed a credit support agreement tied to TensorWave’s Fermi lease. The November 16 release mentions no AMD financing for the OpenAI capacity.
AMD’s shares fell with the sector. Motley Fool reported AMD down 4.4% at 10:53 am Eastern on November 16 and attributed it to a new US export rule, covered in W.141. It did not mention this agreement.
At other contracts’ rates, 457 MW for six years is about $5 billion at a facility lease’s rate or $27–37 billion at cloud contracts’
An illustration, in billions of dollars; TensorWave disclosed no value. Each dashed pink bar multiplies 457 MW by 6 years (2,742 megawatt-years) by the rate per megawatt-year of another contract. The Fermi lease TensorWave lost: about $6.5 billion over 15 years for 222 MW of facility power, a data center lease whose release does not mention chips. IREN’s contract with Microsoft: approximately $9.7 billion over 5 years for 200 MW of IT load, with IREN supplying the chips. Oracle’s with OpenAI: $300 billion over 5 years for about 4.5 GW, as first reported by the Wall Street Journal in September 2025. The contracts differ in scope, term and megawatt basis, and which structure TensorWave’s follows is not disclosed.
The rates
| Contract | $ billion | Years | MW | $M per MW a year | × 2,742 MW-years, $B |
|---|---|---|---|---|---|
| Fermi and TensorWave, terminated | 6.5 | 15 | 222 | 1.95 | 5.4 |
| IREN and Microsoft | 9.7 | 5 | 200 | 9.70 | 26.6 |
| Oracle and OpenAI, as reported | 300 | 5 | 4,500 | 13.33 | 36.6 |
What it could cost to build
The capital needed is many times TensorWave’s equity on any published estimate. Investing.com reported in November 2025 that Bernstein put the cost of AI data center capacity at about $35 billion a gigawatt and that Nvidia’s own figure was $50–60 billion a gigawatt. At Bernstein’s figure 457 MW is about $16.0 billion. The $450 million from TensorWave’s Series A and B rounds is 2.8% of that. Neither estimate is specific to AMD’s racks, and the release does not say how much of the cost falls on TensorWave, OpenAI, AMD or landlords.
TensorWave’s Series A and B rounds total $450 million; 457 MW would cost about $16 billion at Bernstein’s estimate
Billions of dollars. Pink: the $450 million TensorWave raised in its Series A and B rounds, which leaves out a $43 million SAFE round in October 2024. Strong grey: its valuation as stated at the June 2026 round. Faint grey: the contracted revenue of the Fermi lease over its initial 15-year term, before it was terminated. Dashed pink: 457 MW multiplied by Bernstein’s estimate of about $35 billion per gigawatt of AI capacity, an illustration; who would pay for the capacity is not disclosed. The rows are different kinds of amount and are shown for scale.
What this changes on inthesingularity.ai
- Will AI compute run short or long through 2030? Lead: the first named third-party host for OpenAI’s AMD capacity, with dates: 457 MW expected between the first half of 2027 and early 2028. It is 46% of one gigawatt.
- Who funds the neoclouds? Lead: a neocloud whose Series A and B rounds total $450 million taking on capacity that would cost about $16 billion at one published estimate. The financing has not been disclosed, and a lease that depended on project financing ended on November 10.
- Lead: the sites. TensorWave names none. A landlord’s filing or release naming TensorWave as tenant would show where the 457 MW is and on what terms.
- Lead: AMD’s filings. Any guarantee or credit support for TensorWave’s obligations could be disclosed in AMD’s filings; its support for the Fermi lease was disclosed in Fermi’s releases.
Sources and method
| Item | Figure | Source |
|---|---|---|
| The agreement | A 6-year agreement with OpenAI; 457 megawatts of IT capacity (“more than 450MW” in the headline); dedicated, single-tenant; AMD Instinct MI455X GPUs in AMD Helios racks; multiple US sites; expected to begin coming online in the first half of 2027, full deployment expected by early 2028; TensorWave has secured more than 2 gigawatts of long-term data center capacity | TensorWave release, Nov 16 |
| The agreement | Neither company disclosed the value or the sites | The Next Web, Nov 16 |
| OpenAI and AMD | A 6 gigawatt agreement; the first 1 gigawatt, of MI450 chips, set to begin in the second half of 2026; a warrant for up to 160 million AMD shares vesting with deployment and other milestones | AMD release, Oct 6, 2025 |
| AMD | Third quarter of 2026: revenue $13,377 million; Data Center segment $8,546 million, up 97%; fourth-quarter revenue outlook about $17 billion | AMD 8-K exhibit, Nov 3 |
| AMD | Lead customers including OpenAI brought first Helios racks online in the third quarter; MI455X shipped in volume in the quarter | AMD prepared remarks, Nov 3 |
| TensorWave | Series B of $350 million at a $1.55 billion valuation; 8,192 MI325X GPUs online; more than 2 gigawatts of long-term capacity secured | TensorWave release, Jun 10 |
| TensorWave | Series A of $100 million, co-led by Magnetar and AMD Ventures; refers to an earlier SAFE round, announced in October 2024 at $43 million | TensorWave release, May 14, 2025 |
| TensorWave | Leases for 20 MW across two TECfusions sites, 10 MW each; an existing 14.4 MW deployment at Tucson; a 1 GW infrastructure agreement signed in October 2024 | DCD |
| Fermi lease | 222 MW of total facility power; about $6.5 billion over the initial 15-year term; phased delivery from the second half of 2027; subject to conditions including guaranties and financing | Fermi release, Aug 10 |
| Fermi lease | Signed August 9, 2026; terminated November 10, 2026, in accordance with its terms after the closing date passed | Fermi 10-Q for Sep 30, 2026 |
| Fermi lease | Credit support agreement with AMD for the lease, October 13, 2026; amount not disclosed | Fermi release, Oct 13 |
| Fermi lease | Closing conditions not fully satisfied by October 31, 2026, including project-level financing | Fermi release, Nov 3 |
| Fermi lease | The lease and the associated AMD credit support agreement were terminated | Fermi release, Nov 12 |
| Other contracts | IREN and Microsoft: approximately $9.7 billion over a 5-year term for 200 MW of critical IT load, with IREN buying the GPUs | IREN release, Nov 3, 2025 |
| Other contracts | Oracle and OpenAI: $300 billion over 5 years from 2027 for about 4.5 GW, attributed to the Wall Street Journal | The Decoder, Sep 2025 |
| Other contracts | The same Oracle terms, described without a named source | Blockspace via Yahoo, Jul 22 |
| Cost per gigawatt | Bernstein: about $35 billion per gigawatt; Nvidia: $50–60 billion | Investing.com, Nov 1, 2025 |
| Shares | AMD down 4.4% at 10:53 am Eastern on November 16, attributed to a new export rule | Motley Fool, Nov 16 |
What we read. TensorWave’s release in two syndicated copies, AMD’s and Fermi’s releases and filings, and the reports listed. We could not open DCD’s report of the agreement. The Oracle figures are the Wall Street Journal’s as relayed by other outlets. Megawatt bases. TensorWave’s 457 MW is IT capacity. Fermi’s 222 MW is total facility power. AMD’s 6 gigawatts are not defined in its release. We divide across these without adjusting, and say so where we do. Arithmetic. 457 ÷ 6,000 = 7.62%; 457 ÷ 1,000 = 45.7%. 457 × 6 = 2,742 MW-years. 100 + 350 = $450 million; with the 43 million SAFE round, $493 million, which would be 3.1% of the capital cost below. 457 ÷ 14.4 = 31.7; 457 ÷ 222 = 2.06; 457 ÷ 2,000 = 22.9%. Fermi: 6,500 ÷ 15 ÷ 222 = $1.95 million per MW a year; × 2,742 = $5.35 billion. IREN: 9,700 ÷ 5 ÷ 200 = $9.70 million; × 2,742 = $26.60 billion. Oracle: 300,000 ÷ 5 ÷ 4,500 = $13.33 million; × 2,742 = $36.56 billion. Capital cost: 0.457 GW × 35 = $16.00 billion; at Nvidia’s 50–60, $22.9–27.4 billion. 450 ÷ 15,995 = 2.8%. 8,546 ÷ 13,377 = 63.9%. Conflicts between sources. The Fermi lease is dated August 9 in the 10-Q and was announced August 10; its 15-year term runs from the final delivery phase, so our yearly rate is approximate. The 10-Q says it terminated in accordance with its terms; the November 12 release says Fermi and TensorWave terminated it. Not used. A secondary report that TensorWave runs about 10,000 GPUs on about 14 MW across three states, and revenue figures for it, none of which we could trace to a primary source; the share of the Fermi lease that was IT load; and estimates of AMD’s revenue per gigawatt from a third-party model.
Wire reports are written within hours of the news, on a six-hour schedule. Each lists its sources and shows the arithmetic behind its figures. Not investment advice.