Wire · Data centers · AIB Data Centers, Nebius

W.151AIB Data Centers has $25.5M of cash and restricted cash for a $760–780M Nebius build

AIB Data Centers, a former bitcoin host listed on NYSE American, reported third-quarter results on November 16. It has a 12-year agreement to give Nebius 50 MW in South Carolina, with the first 25 MW hall targeted for the fourth quarter of 2027. It estimated on November 10 that the site will cost about $760–780M, or $15.2–15.6M per megawatt of IT load. At September 30 it had $25.5M of cash and restricted cash, about 3% of that, and its 10-Q says no project-level financing has been arranged. Revenue fell 81% to $0.8M after it switched off substantially all of its hosting operations. Nebius has paid its prepayment into escrow; the amount is not disclosed.

Cash and restricted cash, September 30
$25.5M
$10.2M of it restricted as letter-of-credit collateral
Estimated cost of the South Carolina site
$760–780M
$15.2–15.6M per megawatt of IT load, including land
Contracted to Nebius
50 MW
12 years from each hall’s start; contract value not disclosed
Third-quarter revenue
$0.8M
down 81%; net loss $4.8M

The results

AIB has little revenue while it rebuilds. Third-quarter revenue was $813,229, down 80.8% from $4,227,285 a year earlier. The company de-energized substantially all of its bitcoin hosting operations in South Carolina on June 5 and is redeveloping it as an AI data center it calls CLT1. Its 10-Q says the board approved winding down the hosting business on November 11.

Costs moved the other way. Selling, general and administrative expense was $4.0 million, 5.0 times the $0.8 million of a year earlier. Cost of revenues exceeded revenue, for a gross loss of $0.9 million before depreciation against a gross profit of $1.0 million. The net loss was $4.8 million.

The balance sheet is small and unlevered. AIB had $15.3 million of cash and $10.2 million of restricted cash at September 30, total assets of $91.4 million and equity of $78.2 million. It says it has no traditional debt; its liabilities include $5.3 million of deferred consideration for the Texas site. Most of the cash came from a June offering of 38.3 million shares at $1.65, which raised $59.0 million net.

Contracted power is about 120 MW. That is 65 MW at CLT1 under a 15-year electric service agreement, plus a Texas site bought in September with 15 MW energized and up to 40 MW more. The release calls the total approximately 120 MW, up approximately 85%.

AIB’s $25.5M of cash and restricted cash is about 3% of the $760–780M the site is estimated to cost

AIB Data Centers’ resources and the estimated cost of its CLT1 site, in millions of dollars. Pink: cash and restricted cash at September 30, 2026. Grey: the net proceeds of its June 2026 offering and its total assets at September 30. Faint grey: the financing the company showed as an illustration in its September deck, on a cost of about $800 million; it called this not a projection or guidance, and its 10-Q says no project-level financing has been arranged. Black with an outline: the company’s November 10 estimate of total development cost, $760 million to $780 million including land. Nebius’s prepayment, paid into escrow, is not shown because the amount is not disclosed.

0$200M$400M$600M$800MCash and restricted cash, Sep 30$10.2M of it restrictedCash $15.3 million plus restricted cash $10.2 million = $25.5 million at September 30, 2026$25.5MNet proceeds, June 2026 offering38.3M shares at $1.65Net proceeds of the June 2026 public offering: $59.0 million$59.0MTotal assets, Sep 30includes goodwill and intangiblesTotal assets at September 30, 2026: $91.4 million$91.4MIllustrative financing, per the deckEquity12.5% of about $800MIllustrative equity: $100 million$100MPreferred equity17.5% of about $800MIllustrative preferred equity: $140 million$140MConstruction debt70% of about $800MIllustrative construction debt: $560 million$560MThe site, November 10 estimateEstimated development costincluding landEstimated development cost of CLT1: about $760 million to $780 million, including landUpper end of the estimate: $780 million$760–780M
0$400M$800MCash, Sep 30incl. restrictedCash $15.3 million plus restricted cash $10.2 million = $25.5 million at September 30, 2026$25.5MJune offeringnet proceedsNet proceeds of the June 2026 public offering: $59.0 million$59.0MTotal assetsSep 30Total assets at September 30, 2026: $91.4 million$91.4MIllustrativeEquity12.5%Illustrative equity: $100 million$100MPreferred equity17.5%Illustrative preferred equity: $140 million$140MConstruction debt70%Illustrative construction debt: $560 million$560MThe siteEstimated costincl. landEstimated development cost of CLT1: about $760 million to $780 million, including landUpper end of the estimate: $780 million$760–780M

The build and who pays for it

The site costs about thirty times the company’s cash and restricted cash. AIB estimated on November 10 that CLT1 will cost approximately $760 million to $780 million including land, of which about $630 million to $645 million is construction. Over 50 MW of IT load that is $15.2 million to $15.6 million a megawatt. Cash and restricted cash of $25.5 million is 3.3% to 3.4% of the estimate. The $10.2 million of restricted cash secures letters of credit; on the $15.3 million of unrestricted cash alone the cost is about 50 times.

None of the project financing is arranged. The 10-Q says CLT1 needs capital significantly in excess of the cash on hand and that no project-level financing has been arranged. The release says Northland Capital Markets is advising on project-level debt and preferred equity. In September the company showed an illustration of $560 million of construction debt, $140 million of preferred equity and $100 million of equity.

AIB says Nebius’s prepayment will fund the equity. Its chief executive said on an October 1 call that the prepayment is larger than the $100 million equity requirement, according to a transcript. The September deck says equity may still need to be raised for the project. The 10-Q says Nebius paid its fit-out charge and security deposit into escrow on October 20, and the release says AIB has received a first draw. Neither gives an amount. In an October 7 letter the chief executive said the company does not currently anticipate needing common equity at the corporate level.

The share price is below the June offering. StockTitan’s and TradingView’s quote pages showed a close of $0.7601, down about 9% on the day. Neither page dates the figure; Robinhood showed about $0.75 for November 16. The results came out after that day’s close, so the price does not reflect them. It is 54% below the $1.65 offering price. On 76.4 million shares it is a market value of about $58 million.

AIB’s deck implies $2.2M per megawatt a year from Nebius; the contract value is not disclosed

Total contract value divided by years and megawatts, in millions of dollars per megawatt per year. Dashed pink: the rate AIB’s September investor deck shows for its Nebius agreement, $1.32 billion over 12 years and 50 MW. AIB has not stated a contract value, and its chief executive said on the October 1 call that it cannot disclose one, so the bar is the deck’s implication and not a reported figure. Grey: two other data center agreements, from the stated total value, term and megawatts. Terms differ in what the tenant pays for power and fit-out, so the rates are a loose comparison.

0$0.5M$1M$1.5M$2M$2.5MAIB, for Nebius, South Carolinaimplied by its deck: $1.32B, 12 years, 50 MWAIB's deck: $1,320 million ÷ 12 years ÷ 50 MW = $2.20 million per MW per year; the contract value is not disclosed$2.20MWhiteFiber, for Nscale$865M, 10 years, 40 MWWhiteFiber, for Nscale: $865 million ÷ 10 years ÷ 40 MW = $2.16 million per MW per year$2.16MApplied Digital, Delta Forge 2$5,200M, 15 years, 210 MWApplied Digital, Delta Forge 2: $5,200 million ÷ 15 years ÷ 210 MW = $1.65 million per MW per year$1.65M
0$1M$2MAIB, for Nebiusdeck-impliedAIB's deck: $1,320 million ÷ 12 years ÷ 50 MW = $2.20 million per MW per year; the contract value is not disclosed$2.20MWhiteFiber10 yrs, 40 MWWhiteFiber, for Nscale: $865 million ÷ 10 years ÷ 40 MW = $2.16 million per MW per year$2.16MApplied Digital15 yrs, 210 MWApplied Digital, Delta Forge 2: $5,200 million ÷ 15 years ÷ 210 MW = $1.65 million per MW per year$1.65M

The Nebius agreement

Nebius takes 50 MW for 12 years. The agreement, signed on September 25, covers two halls of about 25 MW each. The term runs 12 years from each hall’s rent commencement, with two five-year renewal options and a parent guarantee from Nebius Group N.V., the 10-Q says. The monthly charge escalates annually; the amount is not stated.

The deck implies about $2.2 million a megawatt a year. AIB’s September deck shows an implied rate from $1.32 billion over 12 years and 50 MW. WhiteFiber’s agreement with Nscale in North Carolina works out to $2.16 million and Applied Digital’s Delta Forge 2 lease to $1.65 million. On the October 1 call a moderator cited an analyst estimate of about $1.25 billion for the contract, and the chief executive said AIB’s rate is above three peers’. AIB projects stabilized net operating income of about $90.5 million in year five, which would be 11.6% to 11.9% of the estimated cost.

The filing and the call differ on termination. The 10-Q says the customer may terminate and be refunded its prepaid amounts if outside delivery dates are missed or certain initial permits are not obtained within 90 days of the effective date. The chief executive described it on the October 1 call as a firm contract with no termination options, according to the transcript.

Nebius’s letter lists a matching site for 2027. Its November 12 shareholder letter lists a new 50 MW colocation in South Carolina, its eighth US site, as coming online in 2027. It does not name AIB. AIB’s estimate is the first hall in the fourth quarter of 2027 and the second in the first quarter of 2028, subject to permitting, financing and construction. The 50 MW is 1% of the 5 GW of contracted power Nebius expects to have by the end of 2026.

About 120 MW is contracted across two sites; another 225 MW is not binding

Utility power at AIB Data Centers’ sites in megawatts, from its third-quarter release and 10-Q. Pink: power under contract, with the outline showing the up to 40 MW of additional service at DFW1 that the company counts in its approximately 120 MW. Faint grey: sites under non-binding letters of intent or, for MSP1, a non-binding arrangement described in the 10-Q, at the approximate or maximum figure the company gives. CLT1’s 65 MW of utility power supports the 50 MW of IT load contracted to Nebius. The 10-Q says the seller of GSO1 is controlled by AIB’s chief executive.

0255075100ContractedCLT1, South Carolina15-year electric service agreementCLT1, South Carolina: 65 MW under a 15-year electric service agreement65 MWDFW1, Texas15 MW energized, up to 40 MW moreDFW1, Texas: 15 MW energizedDFW1, Texas: up to 40 MW of additional service15 + 40 MWLetters of intent, not bindingGSO1, North Carolinaletter of intent, up to 90 MWGSO1, North Carolina: letter of intent, up to 90 MW90 MWMSP1, Minnesotanon-binding, about 75 MWMSP1, Minnesota: non-binding, about 75 MW75 MWDFW2, Texasletter of intent, about 60 MWDFW2, Texas: letter of intent, about 60 MW60 MW
050100ContractedCLT115-year agreementCLT1, South Carolina: 65 MW under a 15-year electric service agreement65 MWDFW115 MW + up to 40DFW1, Texas: 15 MW energizedDFW1, Texas: up to 40 MW of additional service15 + 40 MWNot bindingGSO1not bindingGSO1, North Carolina: letter of intent, up to 90 MW90 MWMSP1not bindingMSP1, Minnesota: non-binding, about 75 MW75 MWDFW2not bindingDFW2, Texas: letter of intent, about 60 MW60 MW

Revenue fell from $4.2M to $0.8M while overhead rose from $0.8M to $4.0M

AIB Data Centers’ third quarter, in millions of dollars, from its November 16 release. Grey: the third quarter of 2025. Pink: the third quarter of 2026. The net loss is shown as a positive number. The hosting site that produced the 2025 revenue was de-energized on June 5, 2026; the electric service agreement for the site carries a minimum demand charge of $400,000 a month, of which $200,000 is payable currently, per the 10-Q.

0$2M$4M$6MRevenue, third quarter of 2025: $4,227,285$4.2MRevenue, third quarter of 2026: $813,229$0.8MRevenueCost of revenues, third quarter of 2025: $3,242,391$3.2MCost of revenues, third quarter of 2026: $1,713,843$1.7MCost of revenuesSelling, general, admin., third quarter of 2025: $792,486$0.8MSelling, general, admin., third quarter of 2026: $4,001,626$4.0MSelling, general, admin.Net loss, third quarter of 2025: $63,363$0.1MNet loss, third quarter of 2026: $4,808,269$4.8MNet loss
0$2M$4M$6MRevenue, third quarter of 2025: $4,227,285$4.2MRevenue, third quarter of 2026: $813,229$0.8MRevenueCost of revenues, third quarter of 2025: $3,242,391$3.2MCost of revenues, third quarter of 2026: $1,713,843$1.7MCost of rev.SG&A, third quarter of 2025: $792,486$0.8MSG&A, third quarter of 2026: $4,001,626$4.0MSG&ANet loss, third quarter of 2025: $63,363$0.1MNet loss, third quarter of 2026: $4,808,269$4.8MNet loss
The quarter and the balance sheet
Item, $Q3 2025Q3 2026
Revenue4,227,285813,229
Cost of revenues3,242,3911,713,843
Selling, general and administrative792,4864,001,626
Net loss63,3634,808,269
Cash, September 3015,258,821
Restricted cash, non-current10,242,372
Total assets91,448,256
Total liabilities13,235,680
Stockholders’ equity78,212,576

What this changes on inthesingularity.ai

  • Who funds the neoclouds? Lead: part of Nebius’s capacity is being built by a landlord with $25.5 million of cash and no arranged project financing. The pack could separate the capacity a neocloud builds itself from capacity that depends on a third party raising the money.
  • W.096. Nebius said some third-party colocation deliveries had slipped to the first half of 2027. This site’s first hall is targeted for the fourth quarter of 2027.
  • The leveraged middle. Lead: former bitcoin hosts signing long agreements before financing them. AIB’s illustration puts 70% of the cost in construction debt.
  • Lead: a table of data center agreements by value per megawatt-year, with AIB’s entered only if it discloses a contract value.

Sources and method

ItemFigureSource
ResultsThird quarter of 2026 against 2025: revenue $813,229 against $4,227,285; cost of revenues $1,713,843 against $3,242,391; selling, general and administrative $4,001,626 against $792,486; net loss $4,808,269 against $63,363. Nine months: revenue $8,641,890 against $13,471,554; net loss $8,562,700. At September 30: cash $15,258,821; non-current restricted cash $10,242,372; total assets $91,448,256; total liabilities $13,235,680; equity $78,212,576; no traditional debt. Net proceeds of the offering $58,970,837AIB release, Nov 16
ResultsPower: CLT1 65 MW under a 15-year electric service agreement in effect October 1, 2026; DFW1 15 MW energized with up to 40 MW of additional service; contracted power approximately 120 MW, up approximately 85%; DFW2 approximately 60 MW and GSO1 up to 90 MW under non-binding letters of intent. First 25 MW hall targeted for the fourth quarter of 2027 and the second for the first quarter of 2028, subject to permitting, financing and construction. Northland Capital Markets advising on project-level debt and preferred equity. Prepayment funded into escrow; first draw receivedAIB release, Nov 16
The agreementSigned September 25, 2026 with Nebius Inc.: 50 MW of critical IT load in two halls; 12 years from each hall’s rent commencement; two five-year renewal options; parent guarantee from Nebius Group N.V.; monthly charge with annual escalation, amount not stated; Nebius deposited its fit-out charge and security deposit into escrow on October 20; the customer may terminate and be refunded if outside delivery dates are missed or certain initial permits are not obtained within 90 days of the effective dateAIB 10-Q, Sep 30
The companyFormerly BlockchAIn Digital Infrastructure, renamed June 25, 2026; substantially all hosting operations at its 40 MW South Carolina site de-energized June 5, 2026; board approved its wind-down November 11. June 2026 offering: 38,333,333 shares at $1.65. 76,363,639 shares outstanding at November 13. No project-level financing arranged; CLT1 needs capital significantly in excess of cash on hand; cash sufficient for at least twelve months; two material weaknesses in controls. Minimum demand charge of $400,000 a month under the electric service agreement, of which $200,000 is payable currently. DFW1 bought September 11 for $17.2 million, $6.0 million of it deferred. GSO1 seller controlled by AIB’s chief executive. MSP1: about 75 MW, non-bindingAIB 10-Q, Sep 30
The agreementAnnouncement of the Nebius agreement, September 30, 2026AIB release, Sep 30
CostTotal estimated development cost of CLT1 approximately $760–780 million including land; construction about $630–645 million; projected stabilized net operating income about $90.5 million in year five; estimates subject to changeAIB release, Nov 10, via Finviz
FinancingIllustrative financing: construction debt $560 million, preferred equity $140 million, equity $100 million, on a build of about $800 million; described as not a projection or guidance; equity may need to be raised for the project. Implied rate shown as $1.32 billion ÷ 12 years ÷ 50 MWAIB investor deck, Sep 2026
FinancingCost of around $800 million; contract value not disclosed; prepayment larger than the $100 million equity requirement; the chief executive called the contract firm, with no termination options; a moderator cited an analyst estimate of about $1.25 billion; the chief executive said the rate is above three peers’Investor call transcript, Oct 1
FinancingManagement does not currently anticipate requiring corporate-level common equity for CLT1AIB chief executive’s letter, Oct 7
NebiusA new 50 MW colocation in South Carolina, its eighth US site, expected online in 2027; expects 5 GW of contracted power by the end of 2026; some third-party capacity expected this year now scheduled for the first half of 2027Nebius shareholder letter, Nov 12
Other agreementsWhiteFiber and Nscale: 10 years, 40 MW, about $865 millionData Center Dynamics
Other agreementsApplied Digital, Delta Forge 2: 210 MW, 15 years, about $5.2 billion of base-term revenueApplied Digital release, Oct 7
Share priceClose of $0.7601, undated on the page, read November 17StockTitan
Share price$0.7601, down 8.71% on the dayTradingView

What we read. AIB’s third-quarter release and 10-Q, its September 30 and November 10 releases, its September investor deck, its chief executive’s October 7 letter, a transcript of its October 1 investor call, Nebius’s third-quarter shareholder letter and the other documents listed. Arithmetic. Cash and restricted cash: 15,258,821 + 10,242,372 = $25,501,193. Against the cost: 25.5 ÷ 780 = 3.27%; ÷ 760 = 3.36%; 760 ÷ 25.5 = 29.8 times and 780 ÷ 25.5 = 30.6 times. Per megawatt of IT load: 760 ÷ 50 = 15.2; 780 ÷ 50 = 15.6. Revenue: 813,229 ÷ 4,227,285 − 1 = -80.8%; nine months 8,641,890 ÷ 13,471,554 − 1 = -35.9%. Gross result: 813,229 − 1,713,843 = −$900,614; a year earlier 4,227,285 − 3,242,391 = $984,894. Overhead: 4,001,626 ÷ 792,486 = 5.05. Offering: 38,333,333 × 1.65 = $63.25 million gross. Contracted power: 65 + 15 + 40 = 120 MW; ÷ 65 − 1 = 84.6%. Letters of intent: 90 + 75 + 60 = 225 MW. Rates, $ million per MW per year: 1,320 ÷ 12 ÷ 50 = 2.20; 865 ÷ 10 ÷ 40 = 2.16; 5,200 ÷ 15 ÷ 210 = 1.65. Income over cost: 90.5 ÷ 780 = 11.6%; ÷ 760 = 11.9%. Illustration: 560 + 140 + 100 = 800. Market value: 76,363,639 × 0.7601 = $58.0 million; 0.7601 ÷ 1.65 − 1 = -53.9%. Nebius: 50 MW ÷ 5,000 MW = 1.0%. Conflicts between sources. The 10-Q describes termination and refund rights for the customer; the chief executive said on the call there are no termination options. The company gave the cost as around $800 million on October 1 and approximately $760–780 million on November 10; the financing illustration predates the lower estimate. Quote pages differ on the share price by about a cent. Limits. Nebius’s letter does not name AIB; that its South Carolina site is this one is our reading. The gross loss is revenue less cost of revenues, before depreciation, and is not a line in the release. The contract value, the monthly charge and the prepayment are not disclosed; the rate in the second chart is implied by one slide. The other agreements’ rates use headline values and may cover different services. The share price is from undated quote pages and predates the results. The cost, delivery dates and income projection are the company’s estimates.

Wire reports are written within hours of the news, on a six-hour schedule. Each lists its sources and shows the arithmetic behind its figures. Not investment advice.