inthesingularity.ai
Wire · Financing · Epoch Digital

W.139Syndication of a $488M Malaysian data center loan was delayed, Bloomberg reports

Bloomberg reported on November 16 that the syndication of a $488 million loan for a Malaysian data center has been delayed, according to summaries of its report; we could not read the article. The summaries say the project is backed by Actis, run by Epoch Digital and meant for ByteDance, that a bank presentation planned for November 2 and a site visit did not take place, and that new dates are being arranged. No summary says the loan was cancelled. A development bank’s documents describe what appears to be the same project: 60 MW contracted to ByteDance’s cloud unit, a cost of about $870 million and a loan capped at $520 million. On that reading the loan is about $8.1 million per megawatt.

Loan whose syndication is delayed, per summaries of Bloomberg
$488M
postponed, not cancelled; new dates being arranged
Capacity contracted to BytePlus, per AIIB
60 MW
on a campus designed for 120 MW; the match to this loan is our inference
The loan as a share of AIIB’s project cost
56%
$488M of about $870M, if the loan is this project’s; AIIB’s ceiling is $520M
Loan per megawatt, on AIIB’s 60 MW
$8.1M
if the loan is this project’s; STT GDC’s Johor loan works out at $8.3M

What was reported

We know the report through its headline and two summaries. Bloomberg’s headline of November 16 says an Asian data center loan syndication is delayed in a rare deal pause. We could not open the article or The Edge Singapore’s copy of it. The details below are from HuggingNews, which cites a post from Bloomberg’s @business account, and from Startup Fortune’s summary. Neither says how Bloomberg sourced them.

The loan is $488 million for a project backed by Actis. HuggingNews says the data center is in Malaysia, is backed by the private equity firm Actis and is operated by Epoch Digital. AIIB’s documents name Actis as the sponsor of an Epoch Digital borrower. Startup Fortune says the facility’s computing capacity is meant for ByteDance. ByteDance is the customer in these accounts, not the borrower.

Two steps in the syndication did not happen. An online presentation for other banks was planned for November 2 and did not take place, Startup Fortune says, and a site visit scheduled for the same week did not happen either. Syndication is the stage at which the arranging banks sell parts of a loan to other lenders.

The reason given is scheduling, and the loan has not been withdrawn. Both summaries say Epoch’s executives were unavailable on the original dates. HuggingNews says banks are arranging new dates for presentations and site inspections. Neither says the loan was cancelled, cut or repriced. Neither names the banks, the margin, the tenor or a new deadline, and neither reports a comment from Actis, Epoch or ByteDance.

Neither summary links the delay to US chip rules or to Nvidia. The backdrop is set out below. Nothing we read connects it to this loan.

The loan is at the small end of the Malaysian data-center financings reported since late 2024

Billions of dollars. Pink: the $488 million loan reported delayed. Faint grey: loans for Malaysian data centers reported as secured, with the date reported. Dashed: amounts sought or under discussion and not reported as closed, which are ZData’s private debt in September 2025 and Bridge Data Centres’ talks in October 2026 to enlarge an existing loan. STT GDC’s figure is an “up to” amount. DayOne’s October 2026 financing was reported as a further RM15 billion; we converted its ringgit tranche at the rate implied by the dollar tranche in the same report. The list is what we found in press reports and is not a complete record of the market; IFR’s reports list three smaller Malaysian loans from 2024 that are not drawn.

Loan whose syndication is delayedReported as securedSought or in talks
0$1B$2B$3B$4B$5B$6B$7BThis loan, Epoch Digitalreported delayed, November 2026This loan, Epoch Digital: $0.49 billion; reported delayed, November 2026$488MZData, Johorabout $500M of private debt sought, September 2025ZData, Johor: $0.50 billion; about $500M of private debt sought, September 2025≈$0.5BYondr, Johorlaunched November 2024, reported closed in 2025Yondr, Johor: $0.84 billion; launched November 2024, reported closed in 2025≈$0.84BPrinceton Digital Group, Johorgreen loan secured, November 2026Princeton Digital Group, Johor: $1.30 billion; green loan secured, November 2026≈$1.3BSTT GDC, Johorgreen loan of up to RM5.6B, August 2026STT GDC, Johor: $1.37 billion; green loan of up to RM5.6B, August 2026$1.37BDayOne, JohorRM15B, June 2025DayOne, Johor: $3.60 billion; RM15B, June 2025$3.6BDayOne, Johor, additionala further RM15B, October 2026; our conversionDayOne, Johor, additional: $3.75 billion; a further RM15B, October 2026; our conversion≈$3.7BBridge Data Centres, Malaysiain talks to enlarge a loan, October 2026Bridge Data Centres, Malaysia: $6.60 billion; in talks to enlarge a loan, October 2026≈$6.6B
0$1B$2B$3B$4B$5B$6B$7BThis loandelayedThis loan, Epoch Digital: $0.49 billion; reported delayed, November 2026$488MZDatasought, 2025ZData, Johor: $0.50 billion; about $500M of private debt sought, September 2025≈$0.5BYondrclosed 2025Yondr, Johor: $0.84 billion; launched November 2024, reported closed in 2025≈$0.84BPrinceton DigitalNov 2026Princeton Digital Group, Johor: $1.30 billion; green loan secured, November 2026≈$1.3BSTT GDCup to, Aug 2026STT GDC, Johor: $1.37 billion; green loan of up to RM5.6B, August 2026$1.37BDayOneJun 2025DayOne, Johor: $3.60 billion; RM15B, June 2025$3.6BDayOne, moreOct 2026DayOne, Johor, additional: $3.75 billion; a further RM15B, October 2026; our conversion≈$3.7BBridge DCin talksBridge Data Centres, Malaysia: $6.60 billion; in talks to enlarge a loan, October 2026≈$6.6B
The loans
BorrowerStatus$ billion$488M as a share
This loan, Epoch Digitalreported delayed, November 20260.49
ZData, Johorabout $500M of private debt sought, September 20250.5098%
Yondr, Johorlaunched November 2024, reported closed in 20250.8458%
Princeton Digital Group, Johorgreen loan secured, November 20261.3038%
STT GDC, Johorgreen loan of up to RM5.6B, August 20261.3736%
DayOne, JohorRM15B, June 20253.6014%
DayOne, Johor, additionala further RM15B, October 2026; our conversion3.7513%
Bridge Data Centres, Malaysiain talks to enlarge a loan, October 20266.607%

The project, in a development bank’s documents

The Asian Infrastructure Investment Bank approved a loan to an Epoch Digital project in April. Its page for “Project Mercury” names the borrower as Epoch Digital (MYLB) Ltd and the sponsor as Actis. The site is in Nusa Cemerlang Industrial Park, which STT GDC’s release on its own campus there places in Johor. The first phase is 60 MW of IT capacity on a campus designed for 120 MW. AIIB says the first 60 MW is fully contracted under an off-take agreement with BytePlus, ByteDance’s cloud business.

We treat it as the same project, which no source confirms. The sponsor, Actis, the operator, Epoch Digital, and the customer match; the summaries say ByteDance and AIIB names its unit BytePlus. The $488 million fits under AIIB’s $520 million ceiling. The summaries give no capacity, borrower entity or site, and neither names Project Mercury. AIIB’s documents date from April, six months before the presentation planned for November 2. Every figure in this section and the next depends on that match.

The reported loan is below the ceiling AIIB describes. AIIB’s project summary gives a total cost of about $870 million and a syndicated loan of the lower of $520 million or 60% of cost. Sixty percent of $870 million is $522 million, so the $520 million limit applies. The $488 million reported is $32 million under it and 56.1% of the cost. AIIB’s own part is up to $125 million, which would be 26% of $488 million.

AIIB’s documents put the project at about $870 million, with a loan of up to $520 million

Millions of dollars. Black: total project cost in AIIB’s project summary, approved April 23, 2026. Strong grey: the ceiling on the syndicated loan, the lower of $520 million or 60% of cost. Pink: the loan Bloomberg reported as delayed, per summaries. Grey: AIIB’s part of the loan, which is an “up to” amount. Faint grey: the cost less $488 million, our subtraction. The rows are separate measures, not parts of one total. The pink and faint grey rows assume the delayed loan is this project’s, which is our inference.

Project costLoan ceilingLoan reportedAIIBRemainder
0$200M$400M$600M$800M$1000MTotal project costAIIB documents: about $870M for the first 60 MWTotal project cost: about $870 million (AIIB)≈$870MCeiling on the syndicated loanAIIB: the lower of $520M or 60% of costSyndicated loan: the lower of $520 million or 60% of project cost (AIIB)$520MLoan in syndication, as reportedBloomberg, per summaries, November 16, 2026Loan reported delayed in syndication: $488 million$488MAIIB’s part of the loanup to, approved April 23, 2026AIIB: up to $125 millionup to $125MCost a $488M loan leaves uncoveredour subtraction, if the loan is this project’s870 − 488 = $382 million≈$382M
0$250M$500M$750M$1000MProject costAIIB, aboutTotal project cost: about $870 million (AIIB)≈$870MLoan ceilingAIIBSyndicated loan: the lower of $520 million or 60% of project cost (AIIB)$520MLoan reportedBloomberg, summariesLoan reported delayed in syndication: $488 million$488MAIIB’s partup toAIIB: up to $125 million≤$125MNot debt-funded870 − 488870 − 488 = $382 million≈$382M

Per megawatt, and against other loans

On AIIB’s figures the project costs $14.5 million per megawatt and the loan is $8.1 million. That divides about $870 million and $488 million by the 60 MW first phase. STT GDC’s Johor loan of up to $1.37 billion for up to 166 MW, in the industrial park AIIB names, works out at $8.3 million per megawatt. Princeton Digital Group secured about $1.3 billion on November 4 for a campus W.Media gives as 200 MW, $6.5 million per megawatt. The first two are close and the third is lower. Each divides a reported loan by a stated capacity, and the loans may fund different scopes: Malay Mail describes STT GDC’s loan as for a first phase, while 166 MW is the planned campus total, and AIIB’s cost may include items for the full 120 MW campus.

The loan is smaller than most of the Johor loans reported this year. It is 36% of STT GDC’s Johor loan, 38% of the about $1.3 billion Princeton Digital Group secured on November 4, and 7% of the about $6.6 billion Bridge Data Centres was reported in October to be seeking. DayOne added RM15 billion in October to the RM15 billion it raised in June 2025.

Other Asian loans were secured this month. Princeton Digital Group’s loan was reported on November 4. Bloomberg reported on November 5 that DayOne secured a HK$1.86 billion loan in Hong Kong at 152 basis points over HIBOR. HuggingNews calls a delay of this kind unusual for Asian data center loans; we did not find Bloomberg’s own basis for calling it rare, and we found no total for the market.

If it is AIIB’s project, the loan is about $8.1 million per megawatt, close to STT GDC’s $8.3 million and above Princeton Digital Group’s $6.5 million

Millions of dollars per megawatt of IT capacity. Black: AIIB’s total project cost divided by the 60 MW first phase. Pink: the $488 million loan divided by the same 60 MW, which assumes the delayed loan is this project’s. Faint grey: STT GDC’s loan of up to $1.37 billion divided by up to 166 MW, and the about $1.3 billion Princeton Digital Group secured in November 2026 divided by its 200 MW campus. Each is our division of a reported figure by a reported capacity; AIIB’s cost may cover more than the first 60 MW.

0$4M$8M$12M$16MEpoch Digital, on AIIB’s 60 MWProject cost per MWabout $870M ÷ 60 MW$870 million ÷ 60 MW = $14.50 million per MW$14.5MThe reported loan per MW$488M ÷ 60 MW, if the loan is this project’s$488 million ÷ 60 MW = $8.13 million per MW$8.1MOther Johor loans per MWSTT GDC, August 2026up to $1.37B ÷ up to 166 MW$1,370 million ÷ 166 MW = $8.25 million per MW$8.3MPrinceton Digital Group, November 2026about $1.3B ÷ 200 MW campus$1,300 million ÷ 200 MW = $6.50 million per MW$6.5M
0$4M$8M$12M$16MEpoch DigitalProject cost870 ÷ 60$870 million ÷ 60 MW = $14.50 million per MW$14.5MThe loan488 ÷ 60$488 million ÷ 60 MW = $8.13 million per MW$8.1MOther Johor loansSTT GDC1,370 ÷ 166$1,370 million ÷ 166 MW = $8.25 million per MW$8.3MPrinceton Digital1,300 ÷ 200$1,300 million ÷ 200 MW = $6.50 million per MW$6.5M

The backdrop

ByteDance is a large customer for Johor data centers. A project tracker citing press reports says ByteDance committed RM10 billion to Johor in June 2024 and that Johor officials put its cumulative investment above RM29.5 billion by January 2026, counting facilities it built and leased. We found no total for the capacity it leases.

A US rule that would cover Malaysia is reported and not published. The Information reported on November 11 that the Commerce Department is preparing to finalise a rule extending chip controls to seven more countries, Malaysia among them. Malaysia’s trade minister said on November 12 that disclosure of power use and imported GPUs will be written into law, and that 55 of 117 approved data center projects are operating. W.132 and W.126 cover both.

Lenders have been selling data-center loans elsewhere. Bloomberg reported on November 6 that ING was offering roughly $500 million of a dozen data-center loans by auction, with bids due November 19. W.120 covers a private debt sale that QTS cut.

What this changes on inthesingularity.ai

  • The leveraged middle. Lead: a project-level example outside the US. AIIB’s documents give a cost of about $14.5 million per megawatt and debt of up to 60% of cost for a 60 MW Johor site with one off-taker.
  • Lead for a tracker: data-center loans by borrower, size, megawatts and status. Three Johor loans here, one of them by inference, fall between $6.5 million and $8.3 million per megawatt. Margins and tenors would be needed to compare terms; the reports we read gave them for few.
  • Lead: whether the syndication resumes. The summaries say new dates are being arranged and give none. A relaunch, a cut in size or a change of terms would each be worth a follow-up, as would Bloomberg’s own text, which we could not read.

Sources and method

ItemFigureSource
The loanHeadline only; we could not open the articleBloomberg, Nov 16
The loanA $488 million loan for a Malaysian data center project backed by Actis and run by Epoch Digital; syndication delayed because executives could not attend on the original dates; banks arranging new dates for online presentations and site inspections; unusual for Asian data center loansHuggingNews, Nov 16, citing a Bloomberg social post
The loanThe facility’s computing capacity is meant for ByteDance; an online presentation for other banks planned for November 2 did not take place, nor did a site visit scheduled the same week; Epoch’s management was unavailableStartup Fortune, Nov 16, summarising Bloomberg
The projectProject Mercury: borrower Epoch Digital (MYLB) Ltd, sponsor Actis; Nusa Cemerlang Industrial Park; initial 60 MW of IT capacity on a campus designed for 120 MW; the first 60 MW fully contracted under an off-take agreement with BytePlusAIIB project page, Apr 2026
The projectTotal project cost about $870 million; syndicated loan the lower of $520 million or 60% of cost; AIIB up to $125 million; approved April 23, 2026; last disbursement estimated April 2028AIIB project summary, Apr 2026
Other loansDayOne: RM15 billion ($3.6 billion) for Johor data centersW.Media, Jun 13, 2025
Other loansDayOne: a further RM15 billion, made up of a $2.4 billion (RM9.8 billion) offshore term loan and RM5.5 billion of Islamic financingThe Edge Malaysia, Oct 13
Other loansBridge Data Centres in talks to raise a Malaysian loan to about $6.6 billion, more than double the originalThe Tech Capital, Oct 13, citing Bloomberg
Other loansPrinceton Digital Group sought up to $1.2 billion over three years for a 198.8 MW Johor campusBloomberg via Yahoo, Oct 15
Other loansPrinceton Digital Group secured green financing of about $1.3 billion from six banks for a 200 MW campus in JohorW.Media, Nov 4
Other loansSTT GDC: green loan of up to RM5.6 billion ($1.37 billion) for a Johor campus of up to 166 MWMalay Mail, Aug 13
Other loansYondr, Johor: preparing a loan of around $835.5 million; also lists smaller 2024 Malaysian loansIFR Asia, Nov 2024
Other loansYondr’s $835.5 million loan wrapped up; DayOne’s 2025 loan at $3.38 billion-equivalentIFR, 2025
Other loansZData seeking about $500 million (RM2.1 billion) of private debt; clients include Alibaba, ByteDance and TencentBloomberg via Malay Mail, Sep 12, 2025
ByteDanceRM10 billion (about $2.13 billion) committed to Johor in June 2024; Johor officials put cumulative investment above RM29.5 billion (about $6.6 billion) by January 2026BEP Research tracker
The marketING offering roughly $500 million of a dozen data-center loans by auction, bids due November 19Bloomberg via The Edge Malaysia, Nov 6
The marketDayOne secured a HK$1.86 billion ($237 million) five-year loan at 152 basis points over HIBORBloomberg via The Edge Malaysia, Nov 5
RulesThe Information: the Commerce Department is preparing to finalise a rule to stop remote access by Chinese firms, covering seven additional countries including MalaysiaInvesting.com, Nov 12
RulesMalaysia’s trade minister: disclosure of power use and GPU imports to be written into law; 55 of 117 approved data center projects operatingThe Star, Nov 13

What we read, and what we did not. We could not open Bloomberg’s article or The Edge Singapore’s copy. Every detail of the delayed loan is from two secondary summaries, HuggingNews, which summarises a post from Bloomberg’s @business account and not the article, and Startup Fortune, and we do not know Bloomberg’s exact wording, sourcing or publication time. HuggingNews’s feed lists its item at 09:41 UTC. AIIB’s project page and project summary were read directly. The match. That the $488 million loan is the Project Mercury facility is our inference from the sponsor, operator, off-taker and size. If it is wrong, the cost, ceiling, megawatt and per-megawatt figures do not apply to the loan. Arithmetic. 60% × $870 million = $522 million, above the $520 million limit. 488 ÷ 870 = 56.1%. 520 − 488 = $32 million. 125 ÷ 488 = 25.6%; AIIB’s amount is “up to”. 870 − 488 = $382 million. 488 ÷ 60 MW = $8.13 million per MW; 870 ÷ 60 = $14.50 million. STT GDC: 1,370 ÷ 166 = $8.25 million. Princeton Digital Group: 1,300 ÷ 200 = $6.50 million; the up to $1.2 billion it sought in October, on a campus then given as 198.8 MW, works out at $6.04 million. DayOne, October 2026: RM9.8 billion ÷ $2.4 billion = 4.083 ringgit per dollar; RM5.5 billion ÷ 4.083 = $1.35 billion; plus $2.4 billion = $3.75 billion. Shares of other loans: 488 ÷ 1,370 = 35.6%; ÷ 1,300 = 37.5%; ÷ 6,600 = 7.4%. Conflicts between sources. DayOne’s 2025 loan is $3.6 billion in W.Media and $3.38 billion-equivalent in IFR; its October 2026 tranches add to RM15.3 billion against a reported RM15 billion. Reports of the US rule differ on its scope and status; we say reported and not published. Startup Fortune adds its own comment on why banks skip such steps, which we did not use. Not used. A figure of $34 billion of data-center investment in Malaysia, which one headline describes as at risk and the researcher who published it does not; totals for AI-related borrowing; reports on Megaspeed; a report that a $38 billion US construction loan remained in syndication, from a source we rate low; and AirTrunk’s and DayOne’s listing plans.

Wire reports are written within hours of the news, on a six-hour schedule. Each lists its sources and shows the arithmetic behind its figures. Not investment advice.