W.100SpaceX plans over $74B for two AI campuses; the $50B Arizona figure is new
SpaceX said on November 12 that it plans to invest more than $74B in two supercomputing campuses, Reuters reported: more than $24B at Starbase, Texas, a project a city notice put at about $24B a week ago, and roughly $50B in Cochise County, Arizona, a figure that is new. No account we read gives a period. The total is 3.8 times what SpaceX spent on property and equipment in the third quarter. The Arizona site is planned for up to 6 GW, which puts the $50B at about $8.3M a megawatt, against estimates of about $38M for an AI data center with its servers.
What SpaceX said
The statement is SpaceX’s own, and we have it through Reuters. Reuters reported that SpaceX said it plans to invest more than $74B in two supercomputing campuses: more than $24B at Starbase, Texas, and roughly $50B in Cochise County, Arizona. No account we read gives the period over which the money would be spent. We could not open SpaceX’s page. Neither site has its approvals: the Starbase City Commission is due to consider a property tax abatement on December 9, and the Arizona campus needs a special use authorization from Cochise County, whose planning commission meets the same day, according to AZBEX.
The Texas part is the project in last week’s notice. The City of Starbase posted a notice on November 6 putting about $24B on the initial phases of a gas-fired power plant and super-compute facility on about 444 acres (W.052). SpaceX now says more than $24B, that the site would generate its own electricity and not draw on the public grid, and that it would bring more than 500 permanent jobs, Reuters reported.
The Arizona figure is new; the Arizona site was already on file. AZBEX reported on November 11 that an affiliate, Tombstone Resources, LLC, had applied to build the Cochise Supercomputer Campus on 747 acres across two properties, in four overlapping phases. Securities.io, on SpaceX’s update, describes up to 6 GW of capacity, up to 24 GWh of batteries and 9 single-story buildings of about 493,000 square feet each; AZBEX, from the application, calls it a six-gigawatt campus with nine buildings. Power would come through two electric cooperatives, with no power plant on the site beyond about 90 MW of gas backup; AZBEX reported that about $3.6B of grid spending by SpaceX would expand the cooperatives’ Apache Generating Station from about 1 GW to more than 6 GW. Construction could start as soon as March 2027, Drive Tesla Canada reported from the application. Reuters reported about 5,500 construction jobs and 1,000 permanent ones, and a petition of 2,400 signatures asking the county to refuse.
The $74B is 1.5 times nine months of SpaceX’s capital spending and less than its cash and securities
$ billions. Top: the plan as SpaceX gave it, with the Texas part (faint grey) that was in the City of Starbase’s notice of November 6 and the Arizona part (pink) that is new; no spending period was given. Middle: SpaceX’s purchases of property and equipment from its 10-Q (strong grey) and its fourth-quarter guidance of $35–40B and the full-year total that implies (tan, with the range outlined). Bottom: cash and marketable securities, and purchase obligations not yet on the balance sheet, at September 30. The rows are different kinds of figure, set side by side for scale.
How large it is for SpaceX
The $74B floor is less than the year of capital spending that SpaceX’s guidance implies. SpaceX spent $19.6B on property and equipment in the third quarter, 84% of it in its AI segment, and $48.1B in nine months. Its finance chief guided on October 20 to $35–40B in the fourth quarter, which implies $83.1B to $88.1B for 2026. The $74B is 3.8 times the third quarter and 84% to 89% of that implied year. The roughly $50B for Arizona alone is 2.6 times the third quarter.
SpaceX has the cash on hand, and commitments against it. At September 30 it held $51.3B of cash and $38.6B of marketable securities, $89.9B together, against $38.8B of debt and capital leases. It also had $37.8B of purchase obligations not yet on the balance sheet, primarily for AI infrastructure and third-party cloud capacity, and has since committed to a chip lease of about $40B (W.017). Operations brought in $13.1B in nine months, $35.0B less than it spent on property and equipment.
What $50B buys at 6 GW
Roughly $50B over up to 6 GW is about $8.3M a megawatt. That is well below what a finished AI data center is estimated to cost. Epoch AI estimated in May that a 1 GW site costs about $38B up front with its servers, or $38M a megawatt, and puts OpenAI’s Stargate campus in Abilene at about $31.2B for 824 MW of IT power, $37.9M a megawatt. Venture Global’s chief executive cited $5–7B per 250 MW building excluding chips on November 10 (W.078), which is $20–28M a megawatt.
No source says what the $50B covers. At Epoch’s figure, 6 GW with servers would cost about $228B, and $50B would pay for about 1.3 GW. The $50B may leave out chips, cover only early phases, or count megawatts differently from Epoch, which measures IT power; we cannot tell which. No account we read gives megawatts for the Texas site, so the same sum cannot be done there.
Arizona alone is three and a half times SpaceX’s installed compute. SpaceX had 1.7 GW of nameplate compute at September 30 and targeted 2.5–3 GW for the end of 2026, SpaceQ reported from the October 20 call, on which Elon Musk said he would be surprised to bring on less than 13 GW by the end of 2027. Up to 6 GW at Cochise is 3.5 times the September figure and would be built in phases over several years.
Arizona’s $50B is about $8M a megawatt at 6 GW; estimates for sites with servers are near $38M
$ millions per megawatt. Pink: roughly $50B divided by up to 6 GW, as announced for Cochise County; because 6 GW is a ceiling, the figure is a floor for whatever the $50B covers. Grey: a data center building excluding chips, at the $5–7B per 250 MW that Venture Global’s chief executive cited; the solid bar is the low end. Faint grey: Epoch AI’s estimates for Stargate Abilene, per megawatt of IT power, and for a 1 GW AI data center with servers. The measures of a megawatt differ between rows.
The Cochise campus is planned for up to 6 GW; SpaceX had 1.7 GW installed at September 30
Gigawatts. Strong grey: SpaceX’s nameplate compute at June 30 and September 30, 2026. Grey and dashed: its target of 2.5–3 GW for the end of 2026 and the 13 GW that Musk said he would be surprised not to bring on by the end of 2027, a floor that may count capacity added and not a year-end total, both from the October 20 call as SpaceQ reported it. Pink: the capacity the Cochise County campus is planned for at full build, an upper limit with no completion date.
The two campuses
| Item | Starbase, Texas | Cochise County, Arizona |
|---|---|---|
| Investment, as SpaceX gave it | more than $24B | roughly $50B |
| Land | about 444 acres | 747 acres |
| Capacity | not stated | up to 6 GW; up to 24 GWh of batteries |
| Power | its own generation, off the public grid | two electric cooperatives; no on-site plant beyond 90 MW of gas backup |
| Jobs | more than 3,000 in construction so far; more than 500 permanent | about 5,500 in construction; 1,000 permanent |
| Next step | tax abatement before the city commission, December 9 | county planning hearing, December 9 |
The shares
The shares rose in the morning, and coverage tied the move to other news. SpaceX closed at $139.75 on November 11. At 11:17 a.m. Eastern on November 12 it was at $143.86, up 2.94%, according to the Motley Fool, which attributed the rise to news about Nvidia’s chief executive and did not mention the campuses. We did not have a confirmed close.
What this changes on inthesingularity.ai
- W.052 carries the Starbase project at about $24B for initial phases. Lead: SpaceX now says more than $24B and has added roughly $50B in Arizona; both votes are on December 9.
- What does a blue Texas mean for the data center boom? Lead: Starbase is a self-powered campus of more than $24B awaiting a local tax vote, and the Arizona campus shows SpaceX placing its larger site outside Texas.
- Lead: the Cochise campus, up to 6 GW on cooperative power with about $3.6B of grid upgrades, as two accounts have it, belongs in any count of planned capacity such as Bernstein’s (W.094); what the $50B covers is the open question.
Sources and method
| Item | Figure | Source |
|---|---|---|
| The plan | SpaceX plans to invest more than $74B in two supercomputing campuses: more than $24B at Starbase, on about 444 acres, generating its own electricity; roughly $50B in Cochise County; jobs at each site; dry cooling in Arizona; co-op members’ bills could fall by up to 20%; a petition of 2,400 signatures against; Starbase commission to consider a tax abatement on December 9 | Reuters, via The Star, Nov 12 |
| Arizona | Cochise Supercomputer Campus; applicant Tombstone Resources, LLC; 747 acres across two properties; four overlapping phases; 90 MW of gas backup generation; about $3.6B to expand the Apache Generating Station from about 1 GW to more than 6 GW; county planning hearing on December 9 | AZBEX, Nov 11 |
| Arizona | Up to 6 GW; up to 24 GWh of battery storage; 9 single-story buildings of about 493,000 square feet; power through two electric cooperatives with no on-site power plant; about $3.6B of grid upgrades; the Texas water commitment of $220M | Securities.io, on SpaceX’s update, Nov 12 |
| Arizona | Construction could start as soon as March 2027, per the county application | Drive Tesla Canada, Nov 12 |
| Arizona | Bloomberg first reported the plan; not clear whether new generation in Arizona would be gas | The Next Web, Nov 12 |
| Texas | About $24B for initial phases of a gas-fired power plant and super-compute facility; hearing December 9 | City of Starbase notice, posted Nov 6 (W.052) |
| SpaceX | Purchases of property and equipment: $48,069M in nine months, $19,593M in the third quarter, of which $16,444M in the AI segment; operating cash flow of $13,097M in nine months; cash $51,294M and marketable securities $38,561M; debt and capital leases $38,844M; unrecorded purchase obligations $37,840M | SpaceX, 10-Q for September 30, 2026 |
| SpaceX | Fourth-quarter capex guidance of $35–40B; 1.7 GW of nameplate compute at September 30 and 1.4 GW at June 30; 2.5–3 GW targeted for the end of 2026; Musk would be surprised by less than 13 GW brought on by the end of 2027 | SpaceQ, on the Oct 20 call |
| Benchmarks | A 1 GW AI data center costs about $38B up front, servers included (estimate) | Epoch AI, May 14, 2026 |
| Benchmarks | Stargate Abilene: capital cost about $31.2B; 824 MW of IT power as estimated November 1 (estimates) | Epoch AI, data center directory |
| Benchmarks | $5–7B per 250 MW data center building, excluding chips, cited as an industry benchmark by Venture Global’s chief executive on November 10 | W.078 |
| Shares | Close of $139.75 on November 11 | Gotrade, Nov 12 |
| Shares | $143.86, up 2.94%, at 11:17 a.m. Eastern on November 12; the rise attributed to news about Nvidia’s chief executive | The Motley Fool, Nov 12 |
We could not open SpaceX’s own update or Bloomberg’s report; the plan is as Reuters and others relayed it, and details of the Arizona application are from trade and local accounts, not the county’s docket. Accounts differ on the Texas wording: Reuters has more than $24B, the city notice about $24B for initial phases, and Securities.io has up to $24B in one place. Total: 24 + 50 = 74; “more than” is SpaceX’s. Capital spending: 74 ÷ 19.593 = 3.78; 74 ÷ 48.069 = 1.54; 50 ÷ 19.593 = 2.55; AI segment 16,444 ÷ 19,593 = 83.9%. Implied 2026: 48.069 + 35 = 83.1; + 40 = 88.1; 74 ÷ 88.1 = 84.0%; ÷ 83.1 = 89.1%. SpaceX gave no full-year figure; this adds guidance to nine reported months. Balance sheet: 51.294 + 38.561 = 89.855; capital spending less operating cash flow, 48.069 − 13.097 = 34.972. Per megawatt: 50,000 ÷ 6,000 MW = 8.33; Abilene 31200 ÷ 824 = 37.86; building 5,000 ÷ 250 = 20 and 7,000 ÷ 250 = 28. 6,000 MW × $38M = $228B; 50 ÷ 38 = 1.32 GW. Epoch’s figures are estimates and count IT power; the Cochise figure is whatever capacity the application means by up to 6 GW. Capacity: 6 ÷ 1.7 = 3.53. Buildings: 9 × 493,000 = 4,437,000 square feet. Fourth-quarter guidance and the compute figures are from an account of the October 20 call, as in W.052.
Wire reports are written within hours of the news, on a six-hour schedule. Each lists its sources and shows the arithmetic behind its figures. Not investment advice.