W.164Kentucky Power’s $2.81B gas plant for a TeraWulf campus costs about $3,650 a kilowatt

Kentucky Power, an American Electric Power utility with about 162,500 customers, asked Kentucky regulators on November 13 to approve a 769 MW gas plant it estimates at about $2.81B, to serve a TeraWulf data center campus contracted for up to 1,000 MW. That is about $3,650 a kilowatt, 56% to 107% above six other utility combined-cycle plants filed or approved since late 2024. TeraWulf’s load is due to reach 1,000 MW in October 2029; the plant is due in April 2031.

Estimated cost of the plant
$2.81B
company estimate; $3.10B with a $285M substation
Cost per kilowatt, our division
$3,654
six other plants: $1,768 to $2,344
TeraWulf’s contracted demand
1,000 MW
up from 500 MW; 93% of the utility’s owned generation
Full load before the plant runs
18 months
October 2029 to April 2031, per the filings

What was filed

Kentucky Power asked for a 769 MW gas plant at Big Sandy. The application, filed with the Kentucky Public Service Commission on November 13 as Case 2026-00324, seeks a certificate for a combined-cycle plant beside the existing Big Sandy unit near Louisa, in Lawrence County. Testimony describes two GE Vernova 7F.05 combustion turbines and one steam turbine, with commercial operation on April 1, 2031. The company’s release gives 760 MW, the nameplate figure; the application gives 769 MW with duct firing.

The company estimates the plant at about $2.81B. That is the application’s figure for initial construction. A table in the testimony of AEP’s Alex Vaughan uses a capital cost of $2,846M. Neither is approved. The release gives no cost; the Kentucky Lantern reported the $2.81 billion on November 18. The same case asks for a $285M substation in Boyd County, which takes the total to $3.10B.

The plant is for one customer. A TeraWulf subsidiary has an amended service agreement, filed for approval as Case 2026-00323, that raises its maximum contracted demand at the Muskie Data Campus from 500 MW to 1,000 MW. The case summary says that load would effectively double the company’s existing load. TeraWulf has not named a tenant for Muskie or given its capital cost.

Nothing is approved. The docket shows no procedural schedule. The release says decisions could come as early as mid-2027. The state’s Attorney General moved to intervene on November 3.

At about $3,650 a kilowatt, the plant costs more per unit than six other utility gas plants

Dollars per kilowatt: each plant’s estimated or approved cost divided by its capacity, our division. Pink: Kentucky Power’s Big Sandy plant, at the application’s $2.81B and 769 MW. Grey: six combined-cycle plants that other utilities filed or had approved between November 2024 and November 2026, at the cost and capacity each source gives. The cost bases differ: sources do not say consistently whether financing, transmission or escalation is included, and Kentucky Power’s public filings do not state what its figure covers.

0$1,000$2,000$3,000$4,000Kentucky Power, Big Sandy769 MW; $2.81B estimated; filed November 13, 2026Kentucky Power, Big Sandy: $2,810 million ÷ 769 MW = $3,654 per kW$3,654Duke Energy Carolinas, Anderson County1,365 MW; $3.20B; approved March 2026Duke Energy Carolinas, Anderson County: $3,200 million ÷ 1,365 MW = $2,344 per kW; approved March 2026$2,344Duke Energy Indiana, Cayuga1,476 MW; $3.33B; approved October 2025Duke Energy Indiana, Cayuga: $3,330 million ÷ 1,476 MW = $2,256 per kW; approved October 2025$2,256LG&E, Mill Creek 6645 MW; $1.42B; filed February 2025LG&E, Mill Creek 6: $1,420 million ÷ 645 MW = $2,202 per kW; filed February 2025$2,202Kentucky Utilities, Brown 12645 MW; $1.38B; filed February 2025Kentucky Utilities, Brown 12: $1,380 million ÷ 645 MW = $2,140 per kW; filed February 2025$2,140Mon Power and Potomac Edison, Fort Martin1,200 MW; $2.48B; approved November 17, 2026Mon Power and Potomac Edison, Fort Martin: $2,480 million ÷ 1,200 MW = $2,067 per kW; approved November 17, 2026$2,067East Kentucky Power, Cooper745 MW; $1.32B; announced November 2024East Kentucky Power, Cooper: $1,317 million ÷ 745 MW = $1,768 per kW; announced November 2024$1,768
0$2,000$4,000Kentucky Power769 MW · filed Nov 13Kentucky Power, Big Sandy: $2,810 million ÷ 769 MW = $3,654 per kW$3,654Duke, Anderson Co.1,365 MWDuke Energy Carolinas, Anderson County: $3,200 million ÷ 1,365 MW = $2,344 per kW; approved March 2026$2,344Duke, Cayuga1,476 MWDuke Energy Indiana, Cayuga: $3,330 million ÷ 1,476 MW = $2,256 per kW; approved October 2025$2,256LG&E, Mill Creek 6645 MWLG&E, Mill Creek 6: $1,420 million ÷ 645 MW = $2,202 per kW; filed February 2025$2,202KU, Brown 12645 MWKentucky Utilities, Brown 12: $1,380 million ÷ 645 MW = $2,140 per kW; filed February 2025$2,140Mon Power, Ft Martin1,200 MWMon Power and Potomac Edison, Fort Martin: $2,480 million ÷ 1,200 MW = $2,067 per kW; approved November 17, 2026$2,067EKPC, Cooper745 MWEast Kentucky Power, Cooper: $1,317 million ÷ 745 MW = $1,768 per kW; announced November 2024$1,768
The plants
PlantMWCost$ per kWStatus
Kentucky Power, Big Sandy769$2.81B3,654filed November 13, 2026
Duke Energy Carolinas, Anderson County1,365$3.20B2,344approved March 2026
Duke Energy Indiana, Cayuga1,476$3.33B2,256approved October 2025
LG&E, Mill Creek 6645$1.42B2,202filed February 2025
Kentucky Utilities, Brown 12645$1.38B2,140filed February 2025
Mon Power and Potomac Edison, Fort Martin1,200$2.48B2,067approved November 17, 2026
East Kentucky Power, Cooper745$1.32B1,768announced November 2024

The cost

The estimate works out to about $3,650 a kilowatt. $2.81B over 769 MW is $3,654. On the release’s 760 MW it is $3,697; on the testimony’s $2,846M it is $3,701. The filing itself gives no figure per kilowatt in the parts we read.

Six other plants come to $1,768 to $2,344. Duke Energy’s Anderson County plant in South Carolina, 1,365 MW at a projected $3.2 billion, is the highest of them at $2,344. Mon Power and Potomac Edison’s 1,200 MW Fort Martin plant, which West Virginia’s commission approved on November 17 at $2.48 billion, is $2,067. Two plants that Louisville Gas & Electric and Kentucky Utilities filed in the same state in February 2025 are $2,202 and $2,140. Big Sandy is 56% above the highest and 107% above the lowest.

The comparison is rough. The other plants were costed earlier, three of the six are larger, and their sources do not state a common basis. The Kentucky Lantern wrote that the cost of building combined-cycle plants has surged this year. Its forecasts of the plant’s ongoing operating and capital costs are in exhibits filed as confidential; we did not read the testimony on construction cost. Elliott’s testimony says two requests for proposals, one for 800 MW of capacity and one for a power purchase, both requiring new combined-cycle generation in Kentucky, drew no bids.

The plant is 3.8 times the utility’s annual revenue. Testimony gives Kentucky Power’s total current revenue as $734.9M. The plant’s estimated cost is about $17,300 for each of its roughly 162,500 customers, our division. AEP’s October presentation put Kentucky Power’s capital spending for 2027 to 2031 at $1.6 billion, less than the plant alone.

TeraWulf’s demand reaches 1,000 MW 18 months before the plant is due

Megawatts of contracted demand at the Muskie campus by month, from the ramp schedule in Kentucky Power’s testimony; months with no change are not drawn. Strong grey: phase one, to 500 MW. Pink: phase two, to 1,000 MW. Dashed lines: the new plant’s 769 MW, expected in April 2031, and the 1,075 MW of generation Kentucky Power owns today. The schedule is the contract’s maximum demand, subject to approval; it is not a forecast of metered load.

03006009001,200Oct 2028: 100 MW of contracted demand (phase one)100Oct 28Nov 2028: 200 MW of contracted demand (phase one)200NovDec 2028: 250 MW of contracted demand (phase one)250DecFeb 2029: 350 MW of contracted demand (phase one)350Feb 29Mar 2029: 450 MW of contracted demand (phase one)450MarApr 2029: 500 MW of contracted demand (phase one)500AprJul 2029: 650 MW of contracted demand (phase two)650JulAug 2029: 800 MW of contracted demand (phase two)800AugSep 2029: 950 MW of contracted demand (phase two)950SepOct 2029: 1,000 MW of contracted demand (phase two)1,000Oct 29Kentucky Power’s owned generation today, 1,075 MWthe new plant, 769 MW, expected April 2031
03006009001,200Oct 2028: 100 MW of contracted demand (phase one)100OctNov 2028: 200 MW of contracted demand (phase one)200NovDec 2028: 250 MW of contracted demand (phase one)DecFeb 2029: 350 MW of contracted demand (phase one)350FebMar 2029: 450 MW of contracted demand (phase one)MarApr 2029: 500 MW of contracted demand (phase one)500AprJul 2029: 650 MW of contracted demand (phase two)JulAug 2029: 800 MW of contracted demand (phase two)800AugSep 2029: 950 MW of contracted demand (phase two)SepOct 2029: 1,000 MW of contracted demand (phase two)1,000Octowned today, 1,075 MWnew plant, 769 MW, Apr 2031
The ramp
MonthMWPhase
Oct 2028100one
Nov 2028200one
Dec 2028250one
Feb 2029350one
Mar 2029450one
Apr 2029500one
Jul 2029650two
Aug 2029800two
Sep 2029950two
Oct 20291,000two

The load and the gap

The load arrives first. Under the schedule in the testimony, demand starts at 100 MW in October 2028, reaches 500 MW in April 2029 and 1,000 MW in October 2029. The plant is expected in April 2031, 18 months later. TeraWulf said on October 5 that the second phase had moved from 2030 to 2029, subject to approval and to Kentucky Power’s construction schedule.

A capacity purchase and market energy cover the interval. Kentucky Power asks to buy 693.2 MW of capacity from an AEP affiliate from June 2029 to May 2031: 262.9 MW from the Wolf Hills combustion-turbine plant in Virginia and 430.3 MW from the affiliate’s share of Ohio Valley Electric’s plants in Ohio and Indiana, priced at PJM’s auction price. From October 2028 to April 2031 TeraWulf would pay PJM market prices for its energy. The testimony says the plant and the purchase together do not fully cover the capacity obligation the load creates.

The plant is smaller than the load. 769 MW is 77% of the 1,000 MW contracted. Kentucky Power owns 1,075 MW today: the 295 MW Big Sandy unit and half of the 1,560 MW Mitchell plant. The new plant would add 72% to that. The contracted load is 93% of it.

The contract runs shorter than the plant. Phase one runs 20 years and phase two 15, each renewing unless TeraWulf gives 42 months’ notice. Minimum billing demand is at least 90% of the highest demand established. The company’s fact sheet says TeraWulf cannot reduce its contracted capacity or leave in the first 10 years. The plant’s useful life is given as 40 years. The public filings we read do not say who pays for the plant if the customer leaves when its terms end.

The company’s benefit figures run from $100M to $2.13B, on different bases

Millions of dollars over the life of the contract, as Kentucky Power projects them in testimony. Pink: the two parts that, on our reading, are the release’s “more than $500 million” of rate offsets and $100 million of winter bill credits; the case summary’s “more than $600 million” is plausibly their sum, $635M. Grey: carrying charges and return that TeraWulf would pay in place of customers, and energy and fuel savings during the transition. Black: the total in testimony. All are company projections, not approved and not allocated among customer classes.

0$400M$800M$1,200M$1,600M$2,000M$2,400MAvoided return and carrying chargescosts TeraWulf pays in place of customersAvoided return and carrying charges: $1,302 million$1,302MStandard-tariff savingsthe release’s “more than $500 million”, on our readingStandard-tariff savings: $535 million$535MTransitional energy and fuel savingsOctober 2028 to April 2031Transitional energy and fuel savings: $195 million$195MResidential winter bill credits$10 million a year for 10 years from 2029Residential bill credits: $100 million over the first 10 years$100MTotalas totalled in the company’s testimonyTotal projected benefits over the contract's life: $2,132 million$2,132M
0$800M$1,600M$2,400MAvoided carrying costpaid by TeraWulfAvoided return and carrying charges: $1,302 million$1,302MTariff savingsthe “more than $500M”Standard-tariff savings: $535 million$535MEnergy and fueltransition periodTransitional energy and fuel savings: $195 million$195MWinter bill credits$10M a year, 10 yrsResidential bill credits: $100 million over the first 10 years$100MTotaltestimonyTotal projected benefits over the contract's life: $2,132 million$2,132M
Projected savings for existing customers, per the testimony
YearSavingsAverage revenue reduction
2029$43.9M6.0%
2030$61.5M8.4%
2031$51.8M7.0%
2032$48.5M6.6%

Who pays

TeraWulf would pay the financing cost during construction. The agreement has it pay quarterly carrying charges on the plant’s construction spending, capped at about $465M, in place of the utility accruing financing cost. It must also post security of about $756M, by letter of credit or guaranty. Vaughan’s testimony gives $756,013,200; two schedules in Elliott’s exhibits, $435.9M for the service agreement and $320.2M for grid construction, sum to within $6 of that.

Most of the plant’s yearly cost is allocated to large loads. The testimony puts the plant’s revenue requirement at $329.3M in 2032, its first full year, with $276.4M, or 84%, allocated to large-load customers and $52.8M to existing customers, which the company says savings offset. It projects that existing customers’ costs fall by $43.9M in 2029 and $48.5M in 2032, or 6.0% and 6.6% of revenue.

Three benefit figures are in circulation. The release cites more than $500 million of rate offsets and $100 million of winter bill credits. The case summary cites more than $600 million. The testimony totals $2.13B, of which $1.30B is carrying cost and return that customers avoid because TeraWulf pays it. The bill credit is $10 million a year for ten years from 2029, about $25 a month in winter for a typical residential customer by the company’s figure; the Lantern reports $26.

Bills are already an issue. The commission’s February order put the average residential bill at $194.13 a month for 1,208 kWh, about 16.1 cents a kilowatt-hour all-in, and ordered a management audit of the company. A Boyd County ratepayer told the Lantern that people in the region are “at their utter limits”.

The plant’s estimated cost is 3.8 times Kentucky Power’s annual revenue

Millions of dollars. Pink and strong grey: the plant and the Venator substation, at the company’s estimates. Black: Kentucky Power’s total current revenue for a year, per testimony. Grey: the security TeraWulf must post and the cap on the carrying charges it would pay during construction. Last row: the plant’s revenue requirement in 2032, split into the part allocated to large-load customers (grey) and to existing customers before offsetting savings (faint grey). The rows are different kinds of amount: one-off costs, one year of revenue, collateral and a yearly charge.

0$500M$1,000M$1,500M$2,000M$2,500M$3,000MTo build, company estimatesPlant and substation$2.81B plant; $285M Venator substationPlant: about $2,810 millionVenator substation: about $285 million$3.10BKentucky Power todayTotal current revenuea year, per testimonyKentucky Power's total current revenue: $735 million$735MWhat TeraWulf puts upSecurity to be postedletter of credit or guarantySecurity: $756 million$756MCarrying charges in constructionup to; paid quarterlyCarrying charges on construction spending, capped at $465 million≤$465MEach year once runningThe plant’s 2032 revenue requirement$276.4M allocated to large-load customersAllocated to large-load customers: $276.4 millionAllocated to existing customers, before offsetting savings: $52.8 million$329.3M
0$1,000M$2,000M$3,000MTo buildPlant + substation$2.81B + $285MPlant: about $2,810 millionVenator substation: about $285 million$3.10BThe utilityAnnual revenueper testimonyKentucky Power's total current revenue: $735 million$735MFrom TeraWulfSecurityletter of creditSecurity: $756 million$756MCarrying chargesup toCarrying charges on construction spending, capped at $465 million≤$465MEach year2032 cost of plant84% to large loadsAllocated to large-load customers: $276.4 millionAllocated to existing customers, before offsetting savings: $52.8 million$329.3M

What this changes on inthesingularity.ai

  • W.033 recorded Muskie’s contracted power as raised from 500 MW to 1,000 MW, subject to approval. The filings now give the monthly ramp, the contract terms and the cost of the generation behind it.
  • Lead: a series of utility gas plants with cost per kilowatt at filing. This one, Fort Martin and the two LG&E and KU units give four from one region.
  • Lead: the terms utilities now require of large loads. This agreement has a minimum bill of at least 90% of established demand, a 10-year lock, about $756M of security and customer-paid carrying charges; W.131 covered tenants asked for power guarantees.
  • For TeraWulf: no lease has been announced at Muskie. The service agreement, if approved, would commit its subsidiary to minimum bills once service starts, no earlier than October 2028, whether or not a tenant is signed.
  • Dates to watch: a procedural schedule in Case 2026-00324; the commission’s decision on the service agreement in Case 2026-00323; a transmission line filing the testimony expects in the first quarter of 2027.

Sources and method

ItemFigureSource
The filingCase 2026-00324: certificates for a gas-fired combined-cycle plant in Lawrence County and a transmission substation in Boyd County, a site compatibility certificate and approval of a short-term capacity purchase; application filed November 13, 2026; the Attorney General moved to intervene on November 3; no procedural schedule postedKentucky PSC docket
The plant769 MW; initial construction cost of approximately $2.81B; commercial operation expected in the second quarter of 2031; Venator substation about $285M; capacity purchase of 262.9 MW and 430.3 MW from June 1, 2029 to May 31, 2031; owned generation of 1,075 MW, including half of the 1,560 MW Mitchell plant; a request for proposals for in-state dispatchable generation drew no responseKentucky Power application, Nov 13
The plantMore than $3 billion of generation and transmission; TeraWulf’s load would effectively double the company’s existing load; more than $600 million of direct customer rate reliefCase summary, Nov 13
The plantTwo GE Vernova 7F.05 combustion turbines and one steam turbine; net heat rate about 6,200 Btu/kWh; 40-year life; commercial operation April 1, 2031Lewis testimony
The plantCapital cost $2,846M in Table AEV-5; net present value of revenue requirement $3,670M; revenue requirement $253.5M in 2031 and $329.3M in 2032, with $276.4M allocated to large-load customers and $52.8M to existing customers; 783 MW in winter; letter of credit of $756,013,200; carrying charges of up to $465 millionVaughan testimony
The agreementDemand ramp by month to 1,000 MW in October 2029; terms of 20 and 15 years; minimum billing demand of at least 90%; no reduction or exit in the first 10 years, per the company’s fact sheet; security of $435,852,549 and $320,160,645; carrying charges capped at $465,366,377; two requests for proposals drew no bids; projected benefits of $2,132,309,176 in four parts; savings by year; total current revenue of $734,884,728Elliott testimony
The agreementContracted power at Muskie raised from 500 MW to 1 GW; second phase moved from 2030 to 2029, subject to PSC approval and Kentucky Power’s construction schedule; first phase targeted to begin ramping in 2028; evaluating up to 2 GW over timeTeraWulf 8-K exhibit, Oct 5
The agreement1,000 MW of contracted power at Muskie, subject to PSC approval; no tenant, lease or capital cost disclosed for the campusTeraWulf third-quarter release, Nov 6
The release760 MW plant; up to 1 gigawatt in phases by 2029; more than $500 million in fixed-cost rate offsets; $100 million in winter bill credits; about 162,000 customers in 20 counties; decisions could come as early as mid-2027Kentucky Power release, via The Lane Report, Nov 16
PressPlant cost of $2.81 billion; up to 769 megawatts; service from 2031; a ratepayer’s and a legislator’s comments; a bill credit estimated at $26 a monthKentucky Lantern, via Yahoo, Nov 18
PressAbout $2.85 billion for the plant and $3.1 billion with the substation; two cases, 2026-00323 and 2026-00324; more than $756 million of securityMountain Top Media, Nov 17
PressAn earlier case sought a combustion turbine of about 450 MW at Big Sandy before the switch to a 760 MW combined cycleWEKU, Oct 12
Kentucky PowerApproximately 162,511 customers; average residential bill of $194.13 a month at 1,208 kWh after a rate order granting $55.0 million of a $95.6 million requestKentucky PSC release, Feb 28
AEP$100 billion capital plan for 2027 to 2031; 84 GW of contracted incremental load by 2031AEP third-quarter release, Oct 28
AEPKentucky Power: 1 GW of the contracted load; $1.6 billion of capital spending for 2027 to 2031; prior plan of $78 billion for 2026 to 2030AEP third-quarter presentation, Oct 28
ComparatorsFort Martin: 1,200 MW, $2.48 billion, approved by West Virginia’s PSC on November 17, 2026Lootpress, Nov 2026
ComparatorsAnderson County: 1,365 MW, $3.2 billion projected, approved by South Carolina’s PSCUpstate Business Journal, Mar 2026
ComparatorsCayuga: 1,476 MW, $3.33 billion; Cooper: 745 MW, $1.317 billion (Table 2)GridLab, Sep 2025
ComparatorsCayuga approved by Indiana’s regulatorWFYI, Oct 2025
ComparatorsBrown 12: 645 MW, $1.38 billion; Mill Creek 6: 645 MW, $1.42 billionPower Magazine, Mar 2025

What we read. The Public Service Commission’s docket page for Case 2026-00324; Kentucky Power’s case summary, application and the testimony of three witnesses (Elliott’s in part); TeraWulf’s October 5 exhibit and third-quarter release; AEP’s third-quarter release and presentation; the commission’s February release; the Kentucky Lantern’s article through a syndicated copy; and the regional press listed. We could not open the release on AEP’s site and read it through outlets that carried it. We could not open the docket for Case 2026-00323, the Attorney General’s motion, or the testimony on gas supply and on project cost. Arithmetic. Cost per kilowatt: 2,810 × 1,000 ÷ 769 = 3,654; on 760 MW, 3,697; on 2,846, 3,701. Comparators: 3,200 × 1,000 ÷ 1,365 = 2,344; 3,330 × 1,000 ÷ 1,476 = 2,256; 1,420 × 1,000 ÷ 645 = 2,202; 1,380 × 1,000 ÷ 645 = 2,140; 2,480 × 1,000 ÷ 1,200 = 2,067; 1,317 × 1,000 ÷ 745 = 1,768. Premium: 3,654 ÷ 2,344 − 1 = 56%; 3,654 ÷ 1,768 − 1 = 107%. Plant and substation: 2,810 + 285 = 3,095. Owned generation: 295 + 1,560 ÷ 2 = 1,075. Ratios: 1,000 ÷ 1,075 = 93%; 769 ÷ 1,075 = 72%; 769 ÷ 1,000 = 77%. Against revenue: 2,810 ÷ 734.9 = 3.82. Per customer: $2.81 billion ÷ 162,511 = $17,291. Capacity purchase: 262.9 + 430.3 = 693.2. Security: 435,852,549 + 320,160,645 = 756,013,194, about 756.0 million; the testimony’s letter of credit is $756,013,200. Benefits: 1302.1 + 100 + 195.2 + 535.0 = 2132.3; 535.0 + 100 = 635.0. Revenue requirement: 276.4 ÷ 329.3 = 84%. Bill: 194.13 ÷ 1,208 = 16.1 cents. October 2029 to April 2031 is 18 months. Conflicts between sources. Capacity is 760 MW nameplate in the release and in Lewis’s testimony, 769 MW net with duct firing in the filings, and 783 MW in winter. Cost is approximately $2.81 billion in the application, $2,846M in a testimony table and about $2.85 billion in one press account. The benefit figures differ by basis, as charted; matching the release’s figures to lines of the testimony is our reading. The campus is placed in Grayson in the release and at EastPark Industrial Park, in Boyd and Greenup counties, in the filings. The winter bill credit is about $25 a month by the company’s figure and $26 in the Lantern. Limits. Every cost and benefit figure is the company’s estimate or projection and none is approved. The public filings we read do not state the dollar year of the plant’s cost, its contingency, or whether a gas pipeline connection is included; the forecasts of ongoing operating and capital costs are confidential, and we did not read the testimony on construction cost. The comparators’ costs are on bases their sources do not make uniform, and were set at different dates. The ramp is contracted maximum demand, not expected load. TeraWulf has disclosed no tenant at Muskie.