W.156Nvidia’s supply commitments reached $390B, with $203B scheduled for fiscal 2028
Nvidia’s CFO commentary of November 17 puts its supply and capacity commitments at $390B at October 25, up from $279B in July and $50.3B a year earlier. The amount scheduled for fiscal 2028 rose from $87B to $203B. That is 1.7 times the latest quarter’s cost of revenue annualized, and about the cost of revenue implied by the 75% growth Colette Kress described on the call. The commentary says the increase is primarily multi-year memory procurement. An hour after the results, Nvidia announced a new agreement with Kinsus and a new expansion with SPIL; the only amount it gave for them was “multibillion-dollar” funding for SPIL.
What changed since W.122
The figure is $390 billion. W.122 reported $279 billion at July 26, from the 10-Q, and noted that the next figure would follow the results of November 17. The CFO commentary says supply commitments increased from $279 billion to $390 billion. That is $111 billion more in three months and 7.8 times the $50.3B of October 2025.
The growth slowed as a multiple and not in dollars. July’s figure was 2.3 times April’s, a rise of $160 billion. October’s is 1.4 times July’s, a rise of $111 billion. The August commentary said that quarter’s increase was primarily related to the procurement of memory; the November commentary says this quarter’s is primarily related to the multi-year procurement of memory supply.
The 10-Q is still to come. The commentary says Nvidia plans to file it in the coming weeks. It gives the total and the schedule, and no dollar breakdown by supplier or component beyond saying the increase is primarily memory.
Supply commitments rose from $279B to $390B in a quarter
Nvidia’s supply and capacity commitments at each quarter-end, $ billions. Pink: October 25, 2026, from the CFO commentary of November 17. Strong grey: earlier quarter-ends, as W.122 took them from the 10-Q or 10-K for each date; the line’s label changed between filings. July 2025 is not shown.
Commitments, cost of revenue and inventories
| Quarter-end | Commitments, $B | Quarter’s cost of revenue, $B | Ratio | Inventories, $B |
|---|---|---|---|---|
| Oct 2024 (Q3 FY25) | 28.9 | 8.93 | 3.2× | 7.7 |
| Jan 2025 (Q4 FY25) | 30.8 | n/a | 10.1 | |
| Apr 2025 (Q1 FY26) | 29.8 | 17.39 | 1.7× | 11.3 |
| Oct 2025 (Q3 FY26) | 50.3 | 15.16 | 3.3× | 19.8 |
| Jan 2026 (Q4 FY26) | 95.2 | 17.03 | 5.6× | 21.4 |
| Apr 2026 (Q1 FY27) | 119 | 20.46 | 5.8× | 25.8 |
| Jul 2026 (Q2 FY27) | 279 | 24.08 | 11.6× | 31.6 |
| Oct 2026 (Q3 FY27) | 390 | 29.17 | 13.4× | 39.7 |
When it falls due
Fiscal 2028 went from $87 billion to $203 billion. In July the schedule was nearly even across three periods: $92 billion, $87 billion and $88 billion. In October, fiscal 2028 holds 52% of the total. Fiscal 2028 runs from the start of February 2027 to late January 2028.
$69 billion is scheduled for the quarter now under way. The outlook for that quarter is $130.0 billion of revenue at a 71% to 72% gross margin, which implies about $37B of cost of revenue. The scheduled commitments are 1.9 times that. The quarter has 14 weeks. Commitments include payments for capacity and for goods that become inventory before they become cost of revenue, so the two are not the same thing; the gap is consistent with inventories that rose $8.1B in the quarter to $39.7B.
The later years grew too. Fiscal 2030 and beyond hold $26 billion, against $12 billion in July.
The amount scheduled for fiscal 2028 rose from $87B to $203B
The schedule of Nvidia’s supply and capacity commitments, $ billions, by the period in which they fall. Strong grey: the schedule at July 26, 2026, totaling $279 billion. Pink: the schedule at October 25, 2026, totaling $390 billion. “Rest of fiscal 2027” was two quarters in July and is one quarter in October, so that pair is not like for like.
What $203 billion buys
It is 1.7 times the current run-rate of cost of revenue. Cost of revenue in the quarter to October 25 was $29.17B, or $116.7B annualized. Fiscal 2027’s cost of revenue comes to about $111B if the fourth quarter lands on the outlook.
It matches the growth Kress described. On the call she said revenue is expected to grow about 75% in fiscal 2028 at a 72% to 73% gross margin, according to Investing.com’s transcript. Fiscal 2027 revenue would be about $424B with the fourth quarter at the midpoint; 75% more is about $741B, and at those margins cost of revenue would be $200B to $208B. The $203 billion scheduled for the year sits inside that range. This is our arithmetic on a call remark, and supply commitments are not the whole of cost of revenue, nor is all of cost of revenue committed supply.
The commitment is fixed and the revenue is a forecast. If fiscal 2028 revenue grew less than 75%, the scheduled purchases would not shrink with it unless the contracts allow. Nvidia has not described cancellation terms. Kress said demand far exceeds supply.
The $203B scheduled for fiscal 2028 is about the cost of revenue that 75% growth implies
$ billions. Pink: supply and capacity commitments scheduled for fiscal 2028 at October 25, 2026. Strong grey: Nvidia’s cost of revenue, first the latest quarter times four, then fiscal 2027 with three reported quarters and the fourth implied by the outlook midpoint ($130.0 billion at a 71.5% gross margin). Dashed pink: an illustration of fiscal 2028 cost of revenue, taking implied fiscal 2027 revenue of $423.7B, the 75% growth Kress described on the call and a gross margin of 73% (the bar) to 72% (the extension). The last row is our arithmetic, not a company figure.
Commitments are 13.4 times the quarter’s cost of revenue, from 3.3 a year earlier
Supply and capacity commitments at the quarter-end divided by the cost of revenue of the quarter then ending. Pink: October 2026. Strong grey: earlier quarters. April 2025 is left out because that quarter’s cost of revenue included a charge for H20 inventory, and January 2025 because W.122 did not have that quarter’s cost of revenue.
The supplier release
Nvidia named six partners, one new agreement and one new expansion. The release, issued about an hour after the results, names Amkor, Foxconn, Kinsus, Samsung Electro-Mechanics, SPIL and TSMC. The new agreement is with Kinsus and the new capacity expansion is with SPIL. Samsung Electro-Mechanics amended an existing substrate agreement. The Amkor, TSMC and Foxconn passages describe existing arrangements.
Kinsus plans more than 3.5 times its Nvidia-dedicated substrate capacity. The release says Kinsus plans to expand ABF package-substrate capacity dedicated to Nvidia by more than 3.5 times at its campus in Taoyuan, with production expected to begin in the second half of 2027 and additional capacity targeted for the third quarter of 2028. It gives no dollar amount, quantified baseline or prepayment. Kinsus’s board approved project capital budgets of about NT$59.8 billion in October and NT$19.6 billion in July, Taiwanese outlets reported from its filings; Kinsus has not tied those to Nvidia.
SPIL gets “multibillion-dollar” funding. The release says a new capacity expansion with SPIL, under a multiyear agreement supported by multibillion-dollar funding from Nvidia, will increase contracted advanced-packaging capacity dedicated to Nvidia by mid-2029. It does not give the amount or call it a prepayment. Reuters reported in early November, as relayed by Economic Daily News on November 7, that Nvidia was putting billions of dollars into SPIL’s expansion.
Mid-2029 is a ramp date. One headline says capacity is locked in through mid-2029. The release says SPIL’s dedicated capacity increases by then; it does not give the term of any agreement.
The stated amounts are small against $111 billion. Across this release and October’s, the agreements with a stated value are Amkor’s, which Nvidia puts at nearly $3 billion, and KYEC’s $1.1 billion advance. The supplier releases explain little of a $111 billion quarterly increase, which Nvidia attributes primarily to memory; these releases cover packaging, substrates and testing. Accounts payable rose from $9.8B in January to $21.1B, and other assets from $8.3B to $17.2B; the release does not say how much of other assets is prepaid supply.
Supplier agreements in Nvidia’s October 21 and November 17 releases
| Supplier | Amount | What Nvidia says | Timing |
|---|---|---|---|
| Kinsus | not stated | New agreement, multiyear; plans more than 3.5 times its ABF substrate capacity dedicated to Nvidia | Production expected from 2H 2027; more targeted for Q3 2028 |
| SPIL | “multibillion-dollar” | Multiyear agreement; new capacity expansion, with funding from Nvidia, for advanced packaging lines in Taiwan | Dedicated capacity increases by mid-2029 |
| Samsung Electro-Mechanics | not stated | Existing substrate supply agreement amended | Not stated |
| Amkor | nearly $3B | Multiyear agreements of July and October, including prepayments, for Arizona and South Korea | Announced earlier |
| KYEC | $1.1B | Capacity reservation advance for testing | October release |
| IBIDEN | “multibillion-dollar” | Capacity reservation advance; Ono plant to three times its capacity | October release |
| TSMC, Foxconn | none | No new terms |
What this changes on inthesingularity.ai
- W.122: the $279 billion is now $390 billion, the ratio to quarterly cost of revenue 13.4 times against 11.6, and the first two periods of the schedule hold $272 billion against $179 billion.
- How long can Nvidia run without Jensen Huang? uses the $279 billion. Lead: $390 billion, with $203 billion scheduled for fiscal 2028.
- What happens to memory prices if AI capex stops growing in 2028? Lead: the fiscal 2028 column more than doubled in a quarter, and the commentary says the increase is primarily multi-year memory procurement; the 10-Q should say how much.
- A series worth tracking: the commitments schedule by fiscal year at each quarter-end, with inventories and accounts payable alongside.
- A table worth keeping: Nvidia’s supplier agreements by stated amount, capacity multiple and ramp date. Most have no stated amount.
Sources and method
| Item | Figure | Source |
|---|---|---|
| Commitments | Supply commitments rose from $279 billion to $390 billion at October 25, 2026, primarily related to the multi-year procurement of memory supply; Nvidia plans to file its 10-Q in the coming weeks; schedule: $69B, $203B, $92B, $10B, $8B, $8B for the rest of fiscal 2027, fiscal 2028, 2029, 2030, 2031 and after; inventory $39.7 billion, up from $31.6 billion, to support the Rubin ramp | Nvidia CFO commentary, Nov 17 (8-K exhibit) |
| Commitments | Quarter-end figures through July 26, 2026, the cost of revenue and inventories of each quarter, and the July schedule ($92B, $87B, $88B, $6B, $5B, $1B) | W.122, from Nvidia’s 10-Qs and 10-K |
| Results | Quarter to October 25, 2026: revenue $115,844 million; cost of revenue $29,168 million; inventories $39,724 million; accounts payable $21,074 million ($9,812 million at January 25); other assets $17,166 million ($8,301 million). Outlook: revenue $130.0 billion, plus or minus 3%; gross margins between 71.0% and 72.0% | Nvidia results release, Nov 17 |
| Call | Colette Kress: revenue expected to grow approximately 75% in fiscal 2028, up from 70%; fiscal 2028 gross margin of 72% to 73%; demand far exceeding supply | Investing.com transcript article (machine-assisted), Nov 18 |
| Suppliers, Nov 17 | Kinsus: a new agreement, multiyear; Kinsus plans to expand ABF substrate capacity dedicated to Nvidia by more than 3.5 times at its Taoyuan campus, with production expected to begin in the second half of 2027 and more capacity targeted for the third quarter of 2028. SPIL: a new capacity expansion under a multiyear agreement supported by multibillion-dollar funding from Nvidia; contracted capacity dedicated to Nvidia increases by mid-2029. Samsung Electro-Mechanics: an amended substrate agreement. Amkor: agreements of July and October totaling nearly $3 billion, including prepayments. TSMC and Foxconn: no new terms | Nvidia release, Nov 17 |
| Suppliers, Oct 21 | KYEC: a $1.1 billion capacity reservation advance; IBIDEN: a multibillion-dollar capacity reservation advance and a tripling at its Ono plant; substrate capacity to rise 2.5 times over three years; test capacity to double from 2026 to 2027; SPIL optical-engine capacity 15 times by mid-2027 | Nvidia release, Oct 21 |
| Suppliers | Amkor, Arizona: a $1.5 billion multiyear agreement with a prepayment from Nvidia | Amkor release, Jul 23 |
| Suppliers | Amkor, South Korea: $1.3 billion | TIKR, October |
| Kinsus | Board approved a project capital budget of about NT$59.8 billion on October 30 | MoneyDJ, Oct 31, from Kinsus’s exchange filing |
| Kinsus | Board approved NT$19.6 billion of project capital spending on July 31 | Economic Daily News, July |
| SPIL | Nvidia was putting billions of dollars into SPIL’s packaging expansion, Reuters reported; ASE declined to comment | Reuters, early November, via Economic Daily News, Nov 7 |
| Coverage | Headline says capacity is locked in through mid-2029; times the release at 5:18pm Eastern, after results at about 4:20pm | 24/7 Wall St., Nov 17 |
What we read. Nvidia’s CFO commentary and results release of November 17, its supplier releases of November 17 and October 21, outlets’ accounts of the call, and Taiwanese press on Kinsus and SPIL. Figures through July 2026 are from W.122 and were not checked again. The 10-Q for October had not been filed when we wrote, and we did not have Nvidia’s own call transcript. Arithmetic. 390 − 279 = 111; 390 ÷ 279 = 1.40; 390 ÷ 50.3 = 7.75. Schedules: 92 + 87 + 88 + 6 + 5 + 1 = 279; 69 + 203 + 92 + 10 + 8 + 8 = 390; 203 ÷ 87 = 2.33; 203 ÷ 390 = 52.1%; 69 + 203 = 272. Ratios to cost of revenue: 28.9 ÷ 8.926 = 3.24; 50.3 ÷ 15.157 = 3.32; 95.2 ÷ 17.034 = 5.59; 119 ÷ 20.458 = 5.82; 279 ÷ 24.079 = 11.59; 390 ÷ 29.168 = 13.37. Annualized: 29.168 × 4 = 116.67; 203 ÷ 116.67 = 1.74. Fourth quarter: 130.0 × (1 − 71.5%) = 37.05; 69 ÷ 37.05 = 1.86. Fiscal 2027 cost of revenue: 20.458 + 24.079 + 29.168 + 37.05 = 110.76. Fiscal 2027 revenue: 81.615 + 96.221 + 115.844 + 130.0 = 423.68; × 1.75 = 741.44; × 27% = 200.2; × 28% = 207.6. Inventories: 39.724 − 31.575 = 8.15; 39.724 ÷ 19.784 = 2.01. Amkor: 1.5 + 1.3 = 2.8, against “nearly $3 billion” in the release. Conflicts between sources. One headline says capacity is locked in through mid-2029; the release, as we read it in copies, gives mid-2029 as the date by which SPIL’s capacity increases. Amkor’s October amount of $1.3 billion is from an outlet. Limits. The October total and schedule are from the CFO commentary; the 10-Q may label the line differently and will add detail. The fiscal 2028 comparison uses a growth figure and margin from a third party’s transcript of the call and an outlook midpoint. Supply commitments include capacity payments and purchases that pass through inventory, so they are not directly comparable with cost of revenue in the same period. We read the supplier release through copies on GlobeNewswire and Stock Titan. Kinsus’s capital budgets are as reported by Taiwanese outlets.
Wire reports are written within hours of the news, on a six-hour schedule. Each lists its sources and shows the arithmetic behind its figures. Not investment advice.