W.112Samsung plans 46 trillion won in stages for Onyang HBM packaging, 87% for equipment
Samsung Electronics broke ground on November 12 on a fifth HBM packaging line at its Onyang campus. Press coverage of the ceremony says it plans 46 trillion won there in stages, about $34.6B at that day’s exchange rate: 6 trillion won of construction and about 40 trillion won of equipment. No outlet we read gives an end date, and the figure covers building Onyang out to five lines. It is 0.87 times Samsung’s 2025 capital expenditure and 54.5% of what it expects to spend in 2026. The line is targeted to operate in June 2028. We found no Samsung release on the ceremony.
What was announced
Samsung Electronics broke ground on Onyang Line 5 on Thursday, November 12. The line is at Samsung’s Onyang campus in Asan, which opened in 1991 for assembly and test. Korea Times, The Elec and other outlets describe a three-floor building with about 31,000 m² of cleanroom for packaging high-bandwidth memory (HBM), targeted to operate in June 2028. Korea Times reported that the campus’s floor area will go from about 270,000 m² to about 420,000 m², an increase of 55.6%, and that about 700 jobs are expected. President Lee Jae-myung and Samsung chairman Lee Jae-yong attended.
The 46 trillion won is a plan for the whole campus, to be spent in stages. Outlets covering the ceremony give 6 trillion won for construction and 40 trillion won for advanced equipment; IT Daily puts the equipment at about 40 trillion won. President Lee said, in Seoul Economic Daily’s account, that “an advanced packaging fab worth 6 trillion won will be newly built here” and that 40 trillion won of equipment would follow in stages. IT Daily states that the 46T won is the plan for the Onyang HBM base of five lines, not the cost of Line 5 alone. Hankook Ilbo says only that the 40 trillion won of equipment will be invested in stages going forward; no outlet we read gives an end date.
We found no Samsung release on the ceremony. Samsung’s newsroom carries a release for the July 2 plan but none for November 12, so every figure here from the ceremony comes from press coverage of it. In July Samsung said it planned to invest about 140 trillion won in the Chungcheong region, including five HBM lines at Onyang. That release gave no amounts by affiliate and no end date.
At the November 12 exchange rate 46T won is $34.6B. The won closed at 1,330.7 per dollar that day, according to JKN. At that rate the construction is $4.5B and the equipment $30.1B. Aju Press and Seeking Alpha put the total at $34 billion.
The Onyang plan is 0.87 times Samsung’s 2025 capex and 54.5% of 2026’s
KRW trillion. Top bar: the 46T won plan for Onyang as reported from the ceremony, split into construction (tan, 6T) and equipment (pink, about 40T). It is to be spent in stages over a period no source states. Below: Samsung Electronics’ capital expenditure for all divisions, from its own disclosures. Strong grey bars are reported figures for the full year 2025, the first nine months of 2026 and the third quarter of 2026. The dashed bar is the 2026 full-year figure Samsung said on October 29 it expected. The plan is a multi-year total and the bars below it are single periods.
The plan against Samsung’s capital expenditure (KRW trillion)
| Period | All divisions | 46T ÷ all | DS division | 46T ÷ DS |
|---|---|---|---|---|
| FY2025 | 52.7 | 0.87 | 47.5 | 0.97 |
| 2026, expected | about 84.4 | 0.55 | 76.8 | 0.60 |
| Jan–Sep 2026 | 56.9 | 0.81 | 52.8 | 0.87 |
| Q3 2026 | 29 | 1.59 | 27.2 | 1.69 |
| Q4 2026, implied | 27.5 | 1.67 | 24 | 1.92 |
How large 46 trillion won is
It is 0.87 times everything Samsung Electronics spent on capital projects in 2025. Samsung’s capex was KRW 52.7T in 2025, of which KRW 47.5T was in DS, its chip division. On October 29 Samsung said it expected approximately KRW 84.4T for 2026, with KRW 76.8T in DS. The Onyang plan is 54.5% of the 2026 total and 59.9% of the DS part. It is 1.6 times the KRW 29T Samsung spent in the third quarter of 2026.
The comparison sets a staged plan against single years. The capex figures are for one year or one quarter. The 46T won has no stated period, so it cannot be divided into a yearly amount. The 6T won of construction, the part tied to the building that broke ground, is 7.1% of expected 2026 capex. The reports do not say which division’s budget carries the plan; HBM is a DS product.
About 87% of the plan is equipment. The equipment figure is 6.7 times the construction figure. IT Daily cited SEMI’s July forecast that worldwide sales of assembly and packaging equipment will be $6.7B in 2026 and of test equipment $15.3B, $22.0B together. Samsung’s $30.1B of equipment for Onyang is 1.4 times that one-year total. The reports do not say what kinds of equipment the 40T won covers or over how many years it is bought.
Samsung said in October that it plans to secure cleanrooms ahead of demand and stay flexible on equipment. According to highlights of its October 29 results call published by Yahoo Finance, Samsung said it plans investment ahead of demand to secure cleanroom space and will stay flexible on equipment. The Onyang figures have the same shape: 6T won for a building with a groundbreaking date and a target date, and about 40T won of equipment with neither.
Samsung Electronics’ part of the regional plan rose from 56T to 60T won; the others did not change
Samsung’s investment plan for the Chungcheong region by affiliate, KRW trillion. Faint grey: the amounts Reuters reported on July 2, which sum to 140T. Coloured: the amounts Korea Times and The Elec reported on November 12 and 13, which sum to 144T. Samsung Electronics’ November bar is split into the 46T won for Onyang (pink) and the remaining 14T (grey), which is our subtraction; the reports say the 60T covers Onyang and Cheonan. Reuters gave 2040 as the end date for SDI and Electro-Mechanics and none for Electronics or Display.
The Chungcheong plan by affiliate (KRW trillion)
| Affiliate | July 2 | November 12 | Change | Share in November |
|---|---|---|---|---|
| Samsung Electronics | 56 | 60 | +4 | 41.7% |
| Samsung Display | 67 | 67 | 0 | 46.5% |
| Samsung SDI | 9 | 9 | 0 | 6.3% |
| Samsung Electro-Mechanics | 8 | 8 | 0 | 5.6% |
| Sum | 140 | 144 | +4 | 100.0% |
| Of which Onyang | n/a | 46 | n/a | 31.9% |
The regional plan
The group’s plan for Chungcheong is now reported at 144 trillion won. Seoul Economic Daily said that is 4 trillion won more than the 140 trillion announced in July. Korea Times and The Elec give 60T won for Samsung Electronics, 67T for Samsung Display, 8T for Samsung Electro-Mechanics and 9T for Samsung SDI. At the November 12 rate 144T won is $108.2B; Korea Times put it at $108.4 billion.
The whole increase is in Samsung Electronics’ line. Reuters reported on July 2 that Samsung Electronics’ part was 56T won, for HBM packaging at Onyang and Cheonan. The November figure is 60T won, and the other three affiliates’ amounts are the same as in July. That match is our reading of the two sets of figures; no outlet states the reason for the increase.
Onyang is 76.7% of Samsung Electronics’ part and 31.9% of the group plan. Korea Times describes the 46T won as within the 60T won for the region. That leaves 14T won, by subtraction. The Elec and Seoul Economic Daily report that the Cheonan HBM packaging plant is also being expanded, with Seoul Economic Daily giving the end of 2027 for that work, but no source says how the 14T won is allocated.
Onyang’s 46T won is 2.4 times SK hynix’s P&T7, over a period no one has stated
Announced spending on plants that package HBM, $ billions. Samsung Onyang: 6T won of construction (grey) and about 40T won of equipment (pink), converted at 1,330.7 won per dollar, the November 12 close. SK hynix P&T7: the 19T won SK hynix announced in January 2026, converted at the same rate; April’s coverage put it at about $13 billion at the rate of the time. Micron Singapore and SK hynix Indiana: the dollar amounts in the Singapore EDB release and on NIST’s page. The line under each name is the period each source gives. The four figures cover different scopes and periods: Onyang is five lines with no end date, P&T7 is one plant due by the end of 2027, Micron’s runs through the end of the decade and beyond, and Indiana’s includes research and development.
HBM packaging plants ($B)
| Plant | As stated | $B | Onyang ÷ this | Period the source gives |
|---|---|---|---|---|
| Samsung Onyang, five lines | 46T won | 34.6 | In stages; no end date. Line 5 targeted to operate June 2028 | |
| SK hynix P&T7, Cheongju | 19T won | 14.3 | 2.4 | Construction from April 2026; completion target end-2027 |
| Micron, Singapore | approximately $7B | 7.0 | 4.9 | Through the end of the decade and beyond; initial output expected early 2027 |
| SK hynix, West Lafayette, Indiana | about $3.87B | 3.87 | 8.9 | Mass production in 2H 2028; includes R&D |
Against other HBM packaging plants
The Onyang plan is 2.4 times the amount SK hynix announced for P&T7. SK hynix announced 19 trillion won in January for P&T7, a packaging and test plant in Cheongju, with construction from April 2026 and completion targeted for the end of 2027, according to Asia Economy. Seoul Economic Daily’s report of the April groundbreaking gave a wafer-level packaging line by February 2028. P&T7 is one plant with a completion date. Onyang’s 46T won is five lines with none.
In dollars it is 4.9 times Micron’s Singapore plant and 8.9 times SK hynix’s in Indiana. Micron said in January 2025 that it would invest approximately $7 billion in an HBM advanced packaging plant in Singapore through the end of the decade and beyond, according to the Singapore Economic Development Board; Bernama reported on November 7 that initial output is expected in early 2027. NIST lists SK hynix’s West Lafayette project at about $3.87B for HBM advanced packaging and research, with mass production in the second half of 2028. The dollar figure for Onyang depends on the exchange rate used, and the plants’ scopes differ, so the ratios are indications of scale only.
The figures are spending, not capacity. None of the coverage we read attributes an output figure for Line 5, or for Onyang’s five lines, to Samsung. The reported facts about size are the cleanroom area, the floor area of the campus and the won amounts.
Dates in the reports, from the July plan to 2029
Each row is a date as the named source gives it. Targets and expectations are the companies’ or the outlets’ own; operation and mass production are different milestones and are labelled as each source labels them.
| When | What | Source |
|---|---|---|
| Jul 2, 2026 | Samsung announces a plan to invest about 140T won in the Chungcheong region, including five HBM lines at Onyang | Samsung Newsroom; Reuters |
| Nov 12, 2026 | Ground broken on Onyang Line 5; the regional plan is reported at 144T won | Korea Times; The Elec |
| 1H 2027 | Samsung’s HBM4E mass production, as the paper reports it | Seoul Economic Daily, Nov 13 |
| End-2027 | Expansion of Samsung’s Cheonan HBM packaging plant due | Seoul Economic Daily, Nov 13 |
| End-2027 | SK hynix P&T7 completion target, as announced in January; April coverage said early 2028 overall | Asia Economy, Jan 13 |
| Jun 2028 | Onyang Line 5 targeted to operate | Korea Times; The Elec; Hankook Ilbo |
| 2H 2028 | SK hynix Indiana mass production | NIST |
| 2028 | Samsung’s HBM5 mass production expected | Seoul Economic Daily, Nov 13 |
| May 2029 | Onyang mass production, in reports from before the ceremony | Seoul Economic Daily, Nov 12; Newspim, in a subheading |
Where the reports disagree
The cost of the new plant was reported as 1.3 trillion won in the morning and 6 trillion won at the ceremony. Seoul Economic Daily reported at 10:19 KST on November 12, before the event, that Samsung would put about 1.3T won into a 31,000 m² cleanroom; its English headline gave $900 million. At the November 12 close 1.3T won is $0.98B. The $900 million is that earlier figure for the plant, not a conversion of the 46T won. At the ceremony the construction figure was 6T won, 4.6 times as much. Newspim, also before the ceremony, wrote of about 6T won in a first phase. We have not found an explanation for the difference.
The start date was reported as May 2029 mass production and as June 2028 operation. Seoul Economic Daily gave mass production in May 2029 before the ceremony; Newspim gave the same month, as mass production in a subheading and as the start of operation in its text. Korea Times, The Elec and Hankook Ilbo give operation in June 2028, which Hankook Ilbo says is a year earlier than first planned. JoongAng Economy News gives both: operation from June 2028 and HBM mass production from May 2029, 11 months apart. If both hold, the two dates describe different milestones. Aju Press quoted an industry source who said the one-year acceleration was hard to verify independently. June 2028 is 19 months after the groundbreaking.
The regional total moved from 140T to 144T won, and dollar figures vary with the rate. Outlets converting 46T won give $34 billion; at the November 12 close it is $34.6B.
The differing figures side by side
| Item | One figure | Source | The other | Source |
|---|---|---|---|---|
| Cost of the new plant | 1.3T won ($900M) | Seoul Economic Daily, Nov 12, 10:19 KST, before the ceremony | 6T won of construction | President Lee at the ceremony, per Seoul Economic Daily; Korea Times; The Elec |
| Start date | Mass production in May 2029 | Seoul Economic Daily, Nov 12; Newspim, in a subheading (its text says operation) | Operation in June 2028, a year earlier than planned | Korea Times; Hankook Ilbo. JoongAng Economy News gives both dates |
| Regional plan | 140T won | Samsung Newsroom, Jul 2 | 144T won | Korea Times; The Elec; Seoul Economic Daily, Nov 12–13 |
| Samsung Electronics’ part | 56T won | Reuters, Jul 2 | 60T won | Korea Times; The Elec |
| 46T won in dollars | $34 billion | Aju Press; Seeking Alpha, Nov 12 | $34.6B | Ours, at 1,330.7 won per dollar |
What Samsung has said about demand
Samsung said on October 29 that its 2027 HBM is sold. Call highlights published by Yahoo Finance have its memory executive Kim Jae-june saying that “2027 HBM supply volume is already sold out at an agreed target price” and that Samsung expects tight supply to continue into 2028. The same highlights give the reasons as the shift of conventional DRAM capacity to HBM and the larger dies of HBM4E and HBM5.
Forecasts from before the ceremony point the same way on price. TrendForce forecast on September 30 that the blended average selling price of HBM will rise 121% in 2027, as Seoul Economic Daily reported it. Counterpoint put Samsung’s share of HBM revenue at 33% in the second quarter of 2026, up from 21% in the first, against 50% for SK hynix and 18% for Micron; those shares sum to 101 because of rounding.
The HBM4E remark attributed to the chairman rests on industry sources. Seoul Economic Daily reported on November 13, citing industry sources, that chairman Lee stressed mass production of HBM4E at Onyang to the president; its headline called this a vow. It is not an on-record quotation. His on-record remark, in Korea Times, was that Onyang “will become a leading hub for advanced HBM”. The same Seoul Economic Daily report gives HBM4E mass production in the first half of 2027 and expects HBM5 mass production in 2028.
What this changes on inthesingularity.ai
- How much memory can each AI chip get? says no vendor publishes HBM capacity beyond 2027. That still holds: the coverage gives spending, floor area and a June 2028 target for Line 5, and no output figure from Samsung. Lead: the June 2028 date and the five-line plan are dated markers for Samsung’s packaging side in the pack’s 2028–30 path.
- The same pack says wafers, not technology, are the limit. Onyang is packaging; the plan adds no DRAM wafer starts, and Samsung’s stated reasons for tight supply into 2028 are on the wafer side. Lead: check whether Samsung’s packaging floor space is being built ahead of the wafers the pack expects it to have.
- What happens to memory prices if AI capex stops growing in 2028? notes Samsung’s statement that cleanrooms come first and equipment follows demand. Lead: 87% of the Onyang plan is equipment with no schedule, which is the part the pack treats as deferrable; Line 5’s June 2028 target falls in the year the pack asks about.
- W.044 carries Samsung’s 2026 capex of about KRW 84.4T. Lead for a capex tracker: the 46T won should not be added to any one year until Samsung gives a period; only the 6T won of construction is tied to a dated building.
- Lead for a tracker: HBM packaging plants by announced amount, period and start date. The four in this post are a starting list.
Sources and method
| Item | Figure | Source |
|---|---|---|
| The ceremony | 46T won at Onyang: 6T of construction and 40T of equipment, in stages; operation targeted for June 2028; three floors and about 31,000 m² of cleanroom; campus floor area from about 270,000 to about 420,000 m²; within 60T won from Samsung Electronics for the region; group total 144T won ($108.4 billion); about 700 jobs; the chairman’s remark on an HBM hub | Korea Times, Nov 12 |
| The ceremony | 60 + 67 + 9 + 8 = 144T won by affiliate; foundation work under way; Cheonan HBM facilities also to be expanded | The Elec, Nov 13 |
| The ceremony | 144T won is 4T more than the 140T announced in July; President Lee on a packaging fab worth 6T won, with 40T of equipment to follow in stages | Seoul Economic Daily, politics desk, Nov 12 |
| The ceremony | The 46T won is the plan for the whole Onyang HBM base of five lines, with equipment at about 40T; SEMI’s July forecast of 2026 equipment sales: assembly and packaging $6.7B, test $15.3B | IT Daily, Nov 12 |
| The ceremony | 40T won of equipment to be invested in stages, no date given; operation in June 2028, a year earlier than first planned | Hankook Ilbo, Nov 12 |
| The ceremony | $34 billion; an industry source said the one-year acceleration was difficult to verify independently | Aju Press, Nov 12 |
| The ceremony | President Lee: 46T won ($34B), of which 40T ($30B) is equipment | Seeking Alpha, Nov 12 |
| Before the ceremony | About 1.3T won ($900 million) for a 31,000 m² cleanroom, mass production targeted for May 2029; 46T won over the medium to long term | Seoul Economic Daily, Nov 12, 10:19 KST |
| Before the ceremony | The same article in Korean | Seoul Economic Daily |
| Before the ceremony | About 6T won in a first phase and 46T in total over the medium to long term; mass production in May 2029 | Newspim, Nov 12, 11:38 KST |
| Before the ceremony | Operation from June 2028 and HBM mass production from May 2029 | JoongAng Economy News, Nov 12, 13:20 KST |
| HBM4E | Industry sources on the chairman’s emphasis on HBM4E at Onyang; HBM4E mass production in the first half of 2027; HBM5 expected in 2028; Cheonan expansion due at the end of 2027 | Seoul Economic Daily, Nov 13 |
| July plan | A plan to invest about 140T won in Chungcheong; five HBM lines at Onyang; no amounts by affiliate and no end date | Samsung Newsroom (Korean), Jul 2, 2026 |
| July plan | Electronics 56T, Display 67T, SDI 9T, Electro-Mechanics 8T; SDI and Electro-Mechanics by 2040 | Reuters, via Yahoo Finance, Jul 2, 2026 |
| Samsung capex | Q3 2026 capex KRW 29T (DS 27.2T); January to September KRW 56.9T (DS 52.8T); 2026 expected at approximately KRW 84.4T (DS 76.8T) | Samsung Electronics, third-quarter results, Oct 29, 2026 |
| Samsung capex | FY2025 capex KRW 52.7T (DS 47.5T) | Samsung Electronics, 2025 capex results, via Investegate |
| Samsung capex | The same FY2025 figures | Investing.com, Jan 29, 2026 |
| Samsung call | 2027 HBM volume sold out at an agreed price; tight supply expected to continue into 2028; investment in cleanrooms ahead of demand, equipment flexible | Samsung third-quarter call highlights, via Yahoo Finance |
| Exchange rate | Won per dollar closed at 1,330.7 on November 12, 2026 (3:30 pm KST) | JKN, Nov 12 |
| Other plants | SK hynix P&T7, Cheongju: 19T won, completion target end-2027 | Asia Economy, Jan 13, 2026 |
| Other plants | P&T7 groundbreaking: 19T won (about $13 billion); wafer-level packaging line by February 2028 | Seoul Economic Daily, Apr 22, 2026 |
| Other plants | SK hynix board approval of 7.0931T won for P&T7, period to December 31, 2032; not used | TipRanks, Jul 22, 2026 |
| Other plants | SK hynix West Lafayette, Indiana: about $3.87B for HBM advanced packaging and R&D; mass production in the second half of 2028 | NIST, CHIPS for America |
| Other plants | Micron Singapore HBM advanced packaging: approximately US$7 billion through the end of the decade and beyond | Singapore EDB, Jan 8, 2025 |
| Other plants | Micron Singapore: initial output expected in early 2027 | Bernama, via The Star, Nov 7, 2026 |
| Market | Counterpoint, HBM revenue share, Q2 2026: SK hynix 50%, Samsung 33%, Micron 18%; Samsung 21% in Q1 | Seoul Economic Daily, Sep 3, 2026 |
| Market | TrendForce, September 30: 2027 HBM blended average selling price up 121% | Seoul Economic Daily, Oct 1, 2026 |
We searched Samsung’s newsrooms and found no release on the November 12 ceremony; the figures from it are from press coverage, which reports Samsung’s statements and the president’s remarks. We read Samsung’s FY2025 capex in summaries of its regulatory announcement, not on Samsung’s own page, and its October 29 call in published highlights, not a full transcript. Plan: 6 + 40 = 46; 40 ÷ 46 = 87.0%; 6 ÷ 46 = 13.0%; 40 ÷ 6 = 6.7. Dollars, at 1,330.7 won per dollar, the November 12 regular-session close: 46,000 ÷ 1,330.7 = 34.57; 6,000 ÷ 1,330.7 = 4.51; 40,000 ÷ 1,330.7 = 30.06; 144,000 ÷ 1,330.7 = 108.21; 19,000 ÷ 1,330.7 = 14.28; 1,300 ÷ 1,330.7 = 0.98. Each is rounded from the unrounded quotient. The $900 million and $34 billion figures are the outlets’ own conversions at other rates. Capex: 46 ÷ 52.7 = 0.87; ÷ 47.5 = 0.97; ÷ 84.4 = 54.5%; ÷ 76.8 = 59.9%; ÷ 29 = 1.59; 6 ÷ 84.4 = 7.1%; implied fourth quarter 84.4 − 56.9 = 27.5 and, for DS, 76.8 − 52.8 = 24. The 2026 figure is Samsung’s expectation of October 29, given as approximate. Setting a plan with no stated period against one year’s capex is our comparison. Regional plan: 56 + 67 + 9 + 8 = 140; 60 + 67 + 9 + 8 = 144; 60 − 56 = 4; 46 ÷ 60 = 76.7%; 46 ÷ 144 = 31.9%; 60 − 46 = 14. The July amounts by affiliate are Reuters’ and are not in Samsung’s release. Other plants: 46 ÷ 19 = 2.42; 34.57 ÷ 7 = 4.94; 34.57 ÷ 3.87 = 8.93. SK hynix’s board approved 7.0931T won for P&T7 in July with a period running to 2032; we could not reconcile that with the 19T won and use the announced figure. Equipment: 6.7 + 15.3 = 22.0; 30.06 ÷ 22.0 = 1.37. SEMI’s figures are worldwide sales in one year, read through IT Daily. Site: 420,000 ÷ 270,000 − 1 = 55.6%. Dates: November 2026 to June 2028 is 19 months; June 2028 to May 2029 is 11 months. Cost of the plant: 6 ÷ 1.3 = 4.6. Not used: a figure for Samsung’s monthly HBM packaging capacity that circulated on November 13 without a source, and any cost per square metre of cleanroom, because the 46T won covers five lines and the 31,000 m² only one.
Wire reports are written within hours of the news, on a six-hour schedule. Each lists its sources and shows the arithmetic behind its figures. Not investment advice.